Prime Minister finalizes progress of many key transport projects

PHẠM ĐÔNG |

The Prime Minister set deadlines for key transport projects and requested localities not to "slip" the progress, identifying this as a criterion for evaluating cadres.

On April 9, the Government Office announced that it had just issued Notice No. 168/TB-VPCP on the conclusion of the Government Standing Committee on the inspection results, urging the Inspection Teams to review and remove difficulties and obstacles related to key transport projects planned to be completed in 2025 to achieve the target of 3,000 km of expressway.

Politburo member and Prime Minister Pham Minh Chinh requested the Ministry of Construction and relevant ministries and branches to send a deputy minister in charge of each project, proactively and promptly inspect and resolve problems.

Ministries, localities, and contractors must immediately handle the bottlenecks and take appropriate solutions; attach importance to the work of fighting waste, corruption, and negativity during the implementation process.

Localities must mobilize the entire political system to completely complete site clearance and material supply, not to continuously "slip" the completion progress as committed and determine this as a criterion for evaluating cadres.

Regarding the group of projects that still face many difficulties, the progress has not met the set plan (including 10 projects/291km with a plan to complete in 2025: Ministry of Construction has 1 project/18km; localities have 9 projects/273km) and 2 projects Huu Nghi - Chi Lang and Dong Dang - Tra Linh strive to complete in 2025.

The Prime Minister requested localities and investors to urgently coordinate to handle problems related to site clearance, relocation of technical infrastructure and increase the capacity of material mines as reported by the Ministry of Construction.

Investors, consultants, and contractors have updated the construction progress, clearly defining the "gasoline" road.

Provinces with large volumes of site clearance such as Dong Nai (Bien Hoa - Vung Tau), Khanh Hoa (Khanh Hoa - Buon Ma Thuot), Tuyen Quang (Tuyen Quang - Ha Giang), Binh Duong (Ho Chi Minh City Ring Road 3), Quang Tri (Van Ninh - Cam Lo) focus on directing completion before April 15, 2025 and do not delay the progress.

The provinces of Dong Nai, Khanh Hoa, Dak Lak, Lang Son, Binh Duong, Long An will coordinate with Vietnam Electricity Group (EVN) to complete the relocation of high-voltage power lines, without affecting the construction progress.

Da Nang localities (Hoa Lien - Tuy Loan project) and Ha Giang province (Tuyen Quang - Ha Giang project) speed up licensing procedures, increase the capacity of stone quarries, to be completed no later than April 15, 2025.

Long An province (Ho Chi Minh City Ring Road 3) speeds up the implementation of the intersection with Ben Luc - Long Thanh expressway to ensure synchronous exploitation of 20km of the Ben Luc - Long Thanh project on April 30, 2025 (expected on April 19, 2025).

Tuyen Quang, Ha Giang provinces (Tuyen Quang - Ha Giang project), Dong Thap (Cao Lanh - An Huu project) proactively coordinate with the Ministry of Finance in supplementing capital for the project to complete in 2025.

Lang Son province ( Huu Nghi - Chi Lang project) and Cao Bang (Dong Dang - Tra Linh project) direct investors to resolutely implement to ensure completion in 2025.

Ho Chi Minh City and the provinces of Dong Nai and Binh Duong (Ho Chi Minh City Ring Road 3 project), Dong Thap (An Huu - Cao Lanh data project), Tuyen Quang (Tuyen Quang - Ha Giang project) review the progress, proactively source materials, have appropriate and effective technical treatment solutions, do not delay the project completion progress.

PHẠM ĐÔNG
RELATED NEWS

Prime Minister directs not to let congestion in motor vehicle inspection

|

The Prime Minister requested that there should be no congestion in road motor vehicle inspection activities, causing difficulties for people and businesses.

The shape of the expressway from Cao Bang to Ca Mau has been seen

|

The Prime Minister emphasized that he had seen the shape of the expressway from Cao Bang to Ca Mau and assigned tasks and finalized the implementation progress of the projects.

Deadline for completing the expansion of Ho Chi Minh City - Long Thanh Expressway

|

Deputy Prime Minister Tran Hong Ha requested to strive to inaugurate the Ho Chi Minh City - Long Thanh expressway expansion project on September 2, 2026.

"Call for help" case suspected of being abused by stepmother: Baby once suffered a psychological shock

|

Hanoi - Relatives said that in the past, H often showed signs of panic and psychological trauma suspected of being abused by her stepmother.

Hoang Anh Gia Lai eliminates Thanh Hoa in the National Cup

|

On the evening of September 13, Hoang Anh Gia Lai defeated Thanh Hoa 2-0 in the qualifying round of LPBank Securities National Cup 2025-2026.

Apartment fire in central apartment building of Ho Chi Minh City

|

HCMC - Fire at an apartment on Pasteur Street, Ben Nghe Ward, fortunately did not cause any casualties.

Suing a company that owes wages, many workers in Gia Lai have their petitions returned to court

|

Gia Lai - Many workers sued Phuc Thinh Binh Dinh Company Limited for unpaid wages and benefits and were court-issued because they had not yet passed the mandatory mediation step.

Associate Professor, Dr. Tran Dinh Thien: There may be attacks using fake news to destroy leading enterprises

|

Associate Professor, Dr. Tran Dinh Thien - Member of the Prime Minister's Policy Advisory Council, former Director of the Vietnam Economic Institute - said that fake news is no longer a simple "social networking story" but has become a danger to the entire economy.

Prime Minister directs not to let congestion in motor vehicle inspection

PHẠM ĐÔNG |

The Prime Minister requested that there should be no congestion in road motor vehicle inspection activities, causing difficulties for people and businesses.

The shape of the expressway from Cao Bang to Ca Mau has been seen

PHẠM ĐÔNG |

The Prime Minister emphasized that he had seen the shape of the expressway from Cao Bang to Ca Mau and assigned tasks and finalized the implementation progress of the projects.

Deadline for completing the expansion of Ho Chi Minh City - Long Thanh Expressway

PHẠM ĐÔNG |

Deputy Prime Minister Tran Hong Ha requested to strive to inaugurate the Ho Chi Minh City - Long Thanh expressway expansion project on September 2, 2026.