Prime Minister finalizes progress of many key transport projects

PHẠM ĐÔNG |

The Prime Minister set deadlines for key transport projects and requested localities not to "slip" the progress, identifying this as a criterion for evaluating cadres.

On April 9, the Government Office announced that it had just issued Notice No. 168/TB-VPCP on the conclusion of the Government Standing Committee on the inspection results, urging the Inspection Teams to review and remove difficulties and obstacles related to key transport projects planned to be completed in 2025 to achieve the target of 3,000 km of expressway.

Politburo member and Prime Minister Pham Minh Chinh requested the Ministry of Construction and relevant ministries and branches to send a deputy minister in charge of each project, proactively and promptly inspect and resolve problems.

Ministries, localities, and contractors must immediately handle the bottlenecks and take appropriate solutions; attach importance to the work of fighting waste, corruption, and negativity during the implementation process.

Localities must mobilize the entire political system to completely complete site clearance and material supply, not to continuously "slip" the completion progress as committed and determine this as a criterion for evaluating cadres.

Regarding the group of projects that still face many difficulties, the progress has not met the set plan (including 10 projects/291km with a plan to complete in 2025: Ministry of Construction has 1 project/18km; localities have 9 projects/273km) and 2 projects Huu Nghi - Chi Lang and Dong Dang - Tra Linh strive to complete in 2025.

The Prime Minister requested localities and investors to urgently coordinate to handle problems related to site clearance, relocation of technical infrastructure and increase the capacity of material mines as reported by the Ministry of Construction.

Investors, consultants, and contractors have updated the construction progress, clearly defining the "gasoline" road.

Provinces with large volumes of site clearance such as Dong Nai (Bien Hoa - Vung Tau), Khanh Hoa (Khanh Hoa - Buon Ma Thuot), Tuyen Quang (Tuyen Quang - Ha Giang), Binh Duong (Ho Chi Minh City Ring Road 3), Quang Tri (Van Ninh - Cam Lo) focus on directing completion before April 15, 2025 and do not delay the progress.

The provinces of Dong Nai, Khanh Hoa, Dak Lak, Lang Son, Binh Duong, Long An will coordinate with Vietnam Electricity Group (EVN) to complete the relocation of high-voltage power lines, without affecting the construction progress.

Da Nang localities (Hoa Lien - Tuy Loan project) and Ha Giang province (Tuyen Quang - Ha Giang project) speed up licensing procedures, increase the capacity of stone quarries, to be completed no later than April 15, 2025.

Long An province (Ho Chi Minh City Ring Road 3) speeds up the implementation of the intersection with Ben Luc - Long Thanh expressway to ensure synchronous exploitation of 20km of the Ben Luc - Long Thanh project on April 30, 2025 (expected on April 19, 2025).

Tuyen Quang, Ha Giang provinces (Tuyen Quang - Ha Giang project), Dong Thap (Cao Lanh - An Huu project) proactively coordinate with the Ministry of Finance in supplementing capital for the project to complete in 2025.

Lang Son province ( Huu Nghi - Chi Lang project) and Cao Bang (Dong Dang - Tra Linh project) direct investors to resolutely implement to ensure completion in 2025.

Ho Chi Minh City and the provinces of Dong Nai and Binh Duong (Ho Chi Minh City Ring Road 3 project), Dong Thap (An Huu - Cao Lanh data project), Tuyen Quang (Tuyen Quang - Ha Giang project) review the progress, proactively source materials, have appropriate and effective technical treatment solutions, do not delay the project completion progress.

PHẠM ĐÔNG
RELATED NEWS

Prime Minister directs not to let congestion in motor vehicle inspection

|

The Prime Minister requested that there should be no congestion in road motor vehicle inspection activities, causing difficulties for people and businesses.

The shape of the expressway from Cao Bang to Ca Mau has been seen

|

The Prime Minister emphasized that he had seen the shape of the expressway from Cao Bang to Ca Mau and assigned tasks and finalized the implementation progress of the projects.

Deadline for completing the expansion of Ho Chi Minh City - Long Thanh Expressway

|

Deputy Prime Minister Tran Hong Ha requested to strive to inaugurate the Ho Chi Minh City - Long Thanh expressway expansion project on September 2, 2026.

vHandicap removes notification of identity verification request after Lao Dong's reflection

|

vHandicap - a social network application for golfers, immediately made adjustments after Lao Dong Newspaper's reflection on the issue of overusing personal information collection.

School has 40 students suspected of food poisoning, locking access to kitchen cameras of the vice principal

|

Quang Tri - After the case of 40 students hospitalized for suspected poisoning, the school has locked access to the kitchen camera of the female vice principal in charge of the boarding school.

Ail music that went viral around the world puts artists in the challenge of finding their own path

|

AI music spread strongly on social networks, creating a new phenomenon, while putting artists in the challenge of finding their own path.

Believing the tips of applying shingles leaves to treat Hereafter, a patient was hospitalized with widespread ulcers and seizures

|

Arbitrarily using leaves to treat shingles, an 88-year-old man in Hanoi had to be hospitalized in a state of seizure, severe pain and widespread ulcers in the head.

Truck overturned across the road, Hanoi - Hai Phong expressway was seriously congested

|

Hai Phong - On the morning of October 18, a truck overturned at Km59 of the Hanoi - Hai Phong expressway, causing traffic congestion for many kilometers towards Hai Phong.

Prime Minister directs not to let congestion in motor vehicle inspection

PHẠM ĐÔNG |

The Prime Minister requested that there should be no congestion in road motor vehicle inspection activities, causing difficulties for people and businesses.

The shape of the expressway from Cao Bang to Ca Mau has been seen

PHẠM ĐÔNG |

The Prime Minister emphasized that he had seen the shape of the expressway from Cao Bang to Ca Mau and assigned tasks and finalized the implementation progress of the projects.

Deadline for completing the expansion of Ho Chi Minh City - Long Thanh Expressway

PHẠM ĐÔNG |

Deputy Prime Minister Tran Hong Ha requested to strive to inaugurate the Ho Chi Minh City - Long Thanh expressway expansion project on September 2, 2026.