Package 5. 10 passenger terminals of Long Thanh airport under construction reach more than 77%

HÀ ANH CHIẾN |

Dong Nai - Package 5. 10 construction of Long Thanh airport passenger terminal has achieved an implementation value of about 77.37%.

On September 21, according to Vietnam Airports Corporation (ACV), package 5.10 - Long Thanh airport passenger terminal is large in scale, with a complex scope of work, including the construction, completion and synchronous installation of many technical systems and equipment serving the operation of the terminal.

To date, the realized value has reached about 77.37%. Construction and completion have reached about 82.93%; electricity system has reached about 94% and station equipment has reached about 70.39%.

Also according to ACV, in the current period, the workload is highly concentrated in architectural, electromechanical, fire prevention and fighting, ICT completion and technology equipment installation.

Bên trong nhà ga hành khách sân bay Long Thành đang thi công. Ảnh: HAC
Inside the passenger terminal of Long Thanh airport under construction (Photo taken in August 2026). Photo: HAC

The systems are closely related to each other, so site handover, construction organization and system integration need to be coordinated by region.

ACV has requested the VIETUR consortium to supplement human resources, strengthen coordination between items, organize construction by area and apply progress management tools, BIM.

At the same time, ACV is focusing on prioritizing completing the West wing area and the central area of the passenger terminal, ensuring the necessary conditions for operation and exploitation. The completion and repair of defects in some remaining areas are organized according to the plan in accordance with operating requirements.

Component project 3 - Essential works of Long Thanh International Airport (phase 1) invested by ACV, has 16 main construction packages, of which 4 packages have been completed and 12 packages are being implemented. The accumulated value of 16 main construction packages as of September 5 reached about 79.46% of the contract value.

HÀ ANH CHIẾN
RELATED NEWS

The 2nd runway of Long Thanh airport is under construction, reaching more than 80% progress

|

Dong Nai - The 2nd runway at Long Thanh airport, with a length of 4km and a width of 75m, has been constructed on schedule with more than 80% progress.

Dong Nai recovers more than 239,000m2 of land for Long Thanh airport-related project

|

Dong Nai - The drainage project outside Long Thanh airport (phase 1) recovers 239,054m2 of land with 35 cases.

3 roads connecting Long Thanh airport are handed over more than 380ha of land

|

Dong Nai - More than 380ha of land of 3 traffic road projects connecting Long Thanh airport has been handed over to construction contractors.

Dong Nai auctions 4 golden land plots in the central area and near Long Thanh airport

|

Dong Nai - Dong Nai City Land Fund Development Center announces the auction of land use rights for 4 land plots in the central area and near Long Thanh airport.

Police and military help Thanh Hoa people harvest rice after floods

|

Thanh Hoa - After rain and floods, officers and soldiers of the police and army went to the fields to help people harvest rice and minimize damage.

Colonel Nguyen Dinh Duong becomes Director of Hue City Police

|

Colonel Nguyen Dinh Duong - Deputy Director of Ho Chi Minh City Police was transferred to be Director of Hue City Police.

Da Nang Trade Union affirms its role in the case of recovering over 10.5 billion VND of social insurance debt

|

Da Nang - Trade union affirms its role in contributing to bringing more than 10.5 billion VND of social insurance debt of Minh Hoang 2 Garment Co., Ltd. into the judgment enforcement account.

Hanoi bans vehicles from passing deep flooded points on Thang Long Avenue

|

Hanoi - Thang Long Avenue is flooded 0.7-1m deep due to rising Tich River water, vehicles are prohibited from passing through flooded points and traffic is organized to be diverted.

The 2nd runway of Long Thanh airport is under construction, reaching more than 80% progress

HÀ ANH CHIẾN |

Dong Nai - The 2nd runway at Long Thanh airport, with a length of 4km and a width of 75m, has been constructed on schedule with more than 80% progress.

Dong Nai recovers more than 239,000m2 of land for Long Thanh airport-related project

HÀ ANH CHIẾN |

Dong Nai - The drainage project outside Long Thanh airport (phase 1) recovers 239,054m2 of land with 35 cases.

3 roads connecting Long Thanh airport are handed over more than 380ha of land

HÀ ANH CHIẾN |

Dong Nai - More than 380ha of land of 3 traffic road projects connecting Long Thanh airport has been handed over to construction contractors.

Dong Nai auctions 4 golden land plots in the central area and near Long Thanh airport

MINH CHÂU |

Dong Nai - Dong Nai City Land Fund Development Center announces the auction of land use rights for 4 land plots in the central area and near Long Thanh airport.