Hanoi accelerates the progress of Yen Nghia 1 regulating lake, reducing flooding pressure before the rainy season

Minh Hạnh |

Hanoi accelerates the progress of Yen Nghia 1 regulating lake worth more than 850 billion VND, expecting to increase drainage capacity and reduce flooding in the western area.

Although the drainage plan has been approved for a long time, the infrastructure system of Hanoi City currently only meets about 20% of actual needs. Faced with increasing flooding pressure, accelerating the progress of the emergency project of Yen Nghia 1 regulating lake has become an urgent task to ensure the lives of tens of thousands of households in the western area.

According to reporters' records, the capital's drainage system is in a serious overloaded state. The Hanoi City People's Committee's issuance of a decision to urgently deploy works for the Yen Nghia 1 regulating lake project (Decision No. 6079/QD-UBND) is considered a drastic step to overcome infrastructure limitations.

The project has a total investment of 854.4 billion VND, a water surface area of 20ha, and a regulating capacity of 0.5 million m3. The lake is not only a water storage area but also plays the role of a "regulating valve" connecting to the La Khe canal, contributing to increasing the buffer water storage capacity for the Yen Nghia pumping station, thereby supporting drainage into the Day River.

As of mid-April 2026, the project has completed the handover of 100% of the 23.54 ha area. This is considered a remarkable result, because site clearance is often a major "bottleneck" for infrastructure projects in Hanoi.

Mr. Nguyen Thanh Tung - Head of the Project Management Board for Investment and Construction of Technical and Agricultural Infrastructure Works of Hanoi City said that there are currently 15 construction teams with more than 150 personnel working continuously, including during holidays to compensate for progress. The pre-pressure pile pressure volume has reached over 53%, while the lakebed excavation work has reached about 40%, equivalent to 380,000 m3.

The project applies prestressed reinforced concrete pile technology (SW600B) continuously constructed on a 2.5 km long embankment system. This solution is expected to ensure the durability of the project, limit erosion and shorten construction time, in time to serve the 2026 rainy season.

Bí thư
Hanoi Party Secretary - Mr. Tran Duc Thang inspects the progress of Yen Nghia regulating lake. Photo: Minh Hanh

At the field inspection on the afternoon of April 18, Hanoi Party Secretary - Mr. Tran Duc Thang requested units to accelerate progress and ensure the actual effectiveness of the project. According to him, the construction of regulating lakes or traffic works is not only to complete targets but must contribute to reducing congestion and flooding for people.

The flooding situation after heavy rain for many years is still a pressing issue. Therefore, the pressure on progress for the investor and contractor is very high. According to the plan, before April 30, 2026, the lakebed and connecting culvert system will be completed to be ready for operation; landscape items, green trees, and lighting will continue to be completed afterwards.

The determination of city leaders and the efforts of construction units are creating expectations for a project to "reach the finish line" on schedule. However, reality shows that many infrastructure projects have previously been delayed due to various reasons. Therefore, public opinion also raises questions about responsibility if the project is not completed before the 2026 rainy season.

Director of Hanoi Department of Construction Nguyen Phi Thuong said that when the chain of 10 emergency projects is completed, the city's drainage capacity is expected to increase by about 20%, and at the same time basically handle 60% of flooded points.

Minh Hạnh
RELATED NEWS

Enforced land recovery for 27 households to implement the regulating lake project in Hanoi

|

Hanoi - Tu Liem Ward People's Committee has just organized the enforcement of land recovery for 27 households to implement the Phu Do regulating lake construction project.

Hanoi accelerates site clearance for Phu Do regulating lake

|

Hanoi accelerates site clearance for Phu Do regulating lake project - an emergency project to reduce flooding in the western area of the Capital.

Fight against false and hostile information with scientific and persuasive arguments

|

Regulation No. 19-QD/TW has stated the proactive struggle against false and hostile information and arguments with scientific and persuasive arguments.

Thousands of tons of eels are in stock, farmers in Can Tho and Ca Mau face the risk of losses

|

Can Tho - Eel prices in Can Tho and Ca Mau have dropped sharply, causing farmers to face the risk of losses.

Veteran and the journey of more than 30 years of "keeping the fire" of national history

|

Instead of choosing a comfortable retirement age, the veteran entered a new "job" - educating national historical traditions.

Iran opens fire on container ship in the Strait of Hormuz

|

Iran fired at a container ship in the Strait of Hormuz on April 22, causing the ship to be damaged.

Long Thanh airport lacks labor

|

Dong Nai - Long Thanh Airport is targeted to be put into commercial operation in the fourth quarter of 2026, but still faces difficulties due to labor shortages.

Britain, France convene multinational military alliance, discuss reopening the Strait of Hormuz

|

According to the British Ministry of Defense, more than 30 countries will attend a conference in London to build a military plan to reopen the Strait of Hormuz after reaching a ceasefire agreement.

Hồ điều hòa Mễ Trì hơn 370 tỉ đồng ở Hà Nội tăng tốc trước mùa mưa 2026

Minh Hạnh |

Hà Nội - Hồ điều hòa Mễ Trì hơn 370 tỉ đồng tăng tốc thi công, dự kiến hoàn thành hạng mục chính trước mùa mưa.

Enforced land recovery for 27 households to implement the regulating lake project in Hanoi

Anh Tuấn |

Hanoi - Tu Liem Ward People's Committee has just organized the enforcement of land recovery for 27 households to implement the Phu Do regulating lake construction project.

Hanoi accelerates site clearance for Phu Do regulating lake

Minh Hạnh |

Hanoi accelerates site clearance for Phu Do regulating lake project - an emergency project to reduce flooding in the western area of the Capital.