Hanoi is about to clear land for 2 key traffic projects

HỮU CHÁNH |

Hanoi assigned departments, branches and localities to plan and implement compensation, support and resettlement to serve the site clearance of 2 railway projects through the area.

The Hanoi People's Committee has just issued a plan to clear the land for the Lao Cai - Hanoi - Hai Phong railway and the high-speed railway on the North - South axis (section passing through the city).

Accordingly, the People's Committees of Dai Xuyen, Phuong Duc, Chuyen My, Thuong Tin, Thuong Phuc, Ngoc Hoi, Tien Thang, Quang Minh, Thu Lam, Phuc Thinh, Dong Anh, Phu Dong, Thuan An communes directly organize the implementation of compensation, support and resettlement within the scope of local administrative management; coordinate in preparing documents, plans and detailed plans to implement site clearance work on schedule.

Based on the approved site clearance boundary documents in the project's pre-feasibility study report and the overall progress requirements, coordinate with departments, branches and localities to develop a detailed plan and organize the implementation of compensation, support and resettlement work to serve site clearance for projects.

The Hanoi People's Committee assigned the Department of Finance to preside over advising on the city budget allocation plan to implement compensation, support and resettlement for projects.

The Department of Planning and Architecture shall preside over and coordinate with the Department of Agriculture and Environment, the Institute of Construction Planning and the People's Committees of communes to determine the location and scale of resettlement areas to serve site clearance for projects.

The Department of Agriculture and Environment shall preside over and guide the People's Committees of communes to implement land acquisition and site clearance work to ensure compliance with procedures and processes.

The Department of Construction will act as a unit, coordinating with the Railway Project Management Board (Ministry of Construction) to receive the preliminary design documents in the Pre-Feasibility Study Report and the preliminary boundary documents for site clearance to review and agree on the route plan, station location and other technical factors.

The Hanoi Institute of Construction Planning coordinates with the Department of Planning and Architecture and related units to update and propose competent authorities to consider and approve planning adjustments if necessary.

The Hanoi Urban Railway Management Board will coordinate with the Railway Project Management Board to collect and update relevant information of the Project including route directions, station locations as a basis for the development of the Outline, Expectations to serve the selection of Consultants to set up tasks and prepare TOD Plans around the expected station locations...

HỮU CHÁNH
TIN LIÊN QUAN

Morning news 27.6: Hanoi is about to clear land to build a road connecting Gia Binh Airport

|

Morning news 27.6: Hanoi is about to clear the land to build a road connecting Gia Binh Airport; Bringing a phone into the exam room, a candidate was suspended;...

Hanoi is about to clear the land to build a road connecting to Gia Binh Airport

|

Hanoi plans to spend more than VND 7,600 billion to clear the land to build a road connecting Hanoi with Gia Binh Airport.

Clearing land, expanding Ba Dinh Square area for parade and march

|

The Deputy Prime Minister requested Hanoi to focus on directing site clearance and expanding the Ba Dinh Square area to organize commemorative ceremonies, parades and parades.

HCMC reports after residents texted Standing Deputy Secretary of the City Party Committee Nguyen Thanh Nghi

|

HCMC - Regarding the reporter's text message to Standing Deputy Secretary of the HCMC Party Committee Nguyen Thanh Nghi, the HCMC People's Committee has just reported the handling results.

The contrasting picture behind PJICO's growth figures

|

Motor vehicle insurance brings a large source of income to PJICO, but also carries high risks because all compensation is borne by the enterprise itself.

Proposal to repair the headquarters of the district-level People's Court in Hanoi as the headquarters of the regional People's Court

|

The Chief Justice of the Hanoi People's Court proposed that the city support funding for repairing and renovating existing district-level People's Court headquarters to be used as regional People's Court headquarters.

Fire in a tourist electric vehicle parking lot in Huong Tich pagoda area, many cars burned down

|

Ha Tinh - At noon on July 8, a major fire broke out at the electric car parking lot in the Huong Tich pagoda tourist area, burning down 9 electric cars and 1 car.

Consider handling organizations and individuals if there are violations in the bidding package proposed by Son Hai Group

|

The Ministry of Finance has just sent a document reporting to the Government on the bid package previously proposed by Son Hai Group.

Morning news 27.6: Hanoi is about to clear land to build a road connecting Gia Binh Airport

HUYỀN TRANG - DUY HƯNG |

Morning news 27.6: Hanoi is about to clear the land to build a road connecting Gia Binh Airport; Bringing a phone into the exam room, a candidate was suspended;...

Hanoi is about to clear the land to build a road connecting to Gia Binh Airport

HỮU CHÁNH |

Hanoi plans to spend more than VND 7,600 billion to clear the land to build a road connecting Hanoi with Gia Binh Airport.

Clearing land, expanding Ba Dinh Square area for parade and march

ANH HUY |

The Deputy Prime Minister requested Hanoi to focus on directing site clearance and expanding the Ba Dinh Square area to organize commemorative ceremonies, parades and parades.