Hanoi reclaims land to build a large intersection, many households do not cooperate in handing over the site

SÓNG HỮU |

Hanoi - The Pham Tu - Provincial Road 70 intersection has not been implemented for many years due to problems in site clearance.

The overpass at the intersection of Pham Tu - Cau Buu - Phuc La (Hanoi) is an important item of the traffic investment project surrounding the Chu Van An Memorial Site (now Pham Tu Street) connecting from Ring Road 3 to Cau Buu Street (Provincial Road 70).

After 5 years of operation, Pham Tu Street has been stuck in site clearance, so the intersection (including the overpass) has not been able to be implemented, turning Pham Tu - Road 70 - Phuc La intersection into a traffic hot spot in the city, causing difficulties for people to travel.

Recorded during rush hour, at Pham Tu - Road 70 intersection, traffic density is high. Container trucks, heavy trucks, and passenger cars are next to each other inching forward. Motorbikes squeeze into the middle of cars, many vehicles on the sidewalk.

s
Road 70, the intersection with Pham Tu Street (Hanoi) is often congested. Photo: Song Huu

"Although authorities are often on duty to regulate traffic, the congestion shows no signs of cooling down. I hope the government will soon resolve the land bottleneck and speed up the construction progress of the intersection so that people can travel conveniently" - Mr. Nguyen Van Ha (34 years old, Thanh Liet ward, Hanoi) said.

According to the Thanh Liet Ward Infrastructure Investment Project Management Board, the project to clear the intersection between the traffic road surrounding the Chu Van An Memorial Site (now Pham Tu Street) and route 70 in Tan Trieu commune, Thanh Tri district (old) has a total land area to be recovered of 50,910 m2.

Of which, agricultural land is 27,239.5 m2; residential land for households and individuals is 8,401.5 m2; land for agencies and organizations is 15,269.1 m2.

Up to now, the volume of recovered land has been completed at 27,239.5 m2; the volume of uncleared land is 23,670.6 m2. In addition, 110kV power lines, below 35kV, lighting systems, and water supply and drainage pipes have not been relocated.

s
Many households within the construction area of the intersection have not been cleared. Photo: Song Huu

In 2017, the People's Committee of Thanh Tri district (old) began implementing site clearance work, however, most households and individuals did not comply and did not provide relevant documents.

The reason given by the Project Management Board was that at that time, the project did not have a resettlement area to arrange for households whose residential land was recovered.

"Households do not agree to let the project measurement unit measure data on land and construction works, so the People's Committee of Thanh Tri district must use the map system and land records stored at the People's Committee of Tan Trieu commune as a basis for regulating land users, calculating the area of land acquisition and issuing a notice of land acquisition, leading to many adjustments in the ownership" - the Thanh Liet Ward Infrastructure Investment Project Management Board stated difficulties.

s
Land clearance problems have delayed the construction progress of the Pham Tu - Provincial Road 70 intersection. Photo: Song Huu

Regarding solutions in the coming time, the Thanh Liet Ward Infrastructure Investment Project Management Board said that it will continue to focus on accelerating site clearance work, while closely following departments and branches to seek opinions to resolve problems in the implementation process.

Recently, the Hanoi Department of Construction has issued a document requesting a number of localities and related units to speed up site clearance work, accelerating the progress of key transport projects.

For the Pham Tu intersection - Road 70, the Department of Construction requires completion of construction in the second quarter of 2026.

SÓNG HỮU
RELATED NEWS

Hanoi Secretary points out experience in site clearance from Ring Road 1 project

|

Hanoi - Mr. Nguyen Duy Ngoc pointed out the experiences in site clearance for Ring Road 1, which need to be replicated for other projects.

Hanoi announces good news about the Ring Road 1 project

|

Hanoi has basically completed the land acquisition and site clearance for the Ring Road 1 project (Hoang Cau - Voi Phuc section) after 7 years of implementation.

The first ward to complete site clearance for the Ring Road 1 project

|

Hanoi - O Cho Dua Ward has officially completed site clearance for the Hoang Cau - Voi Phuc section of Ring Road 1 construction project.

Resolutely handle households placing containers in the construction site of the Ring Road 2.5 project

|

Hanoi - The authorities of Phuong Liet ward have cleared the areas encroaching on the underpass project and Ring Road 2.5.

Car catches fire in the middle of rush hour in Hanoi

|

Hanoi - During rush hour this afternoon, a car was traveling at the Xuan La - Vo Chi Cong intersection when it suddenly caught fire.

Coach Kim Sang-sik: "We are ready to win the SEA Games"

|

Coach Kim Sang-sik affirmed that U22 Vietnam is ready for the goal of winning the 33rd SEA Games men's football championship.

Advising Vietnamese citizens on the Cambodia - Thailand conflict

|

The Ministry of Foreign Affairs recommends that Vietnamese citizens living in border provinces between Cambodia and Thailand.

SEA Games 33 Medal Schedule on December 15

|

Updated total medal table of the 33rd SEA Games on December 15.

Hanoi Secretary points out experience in site clearance from Ring Road 1 project

SÓNG HỮU |

Hanoi - Mr. Nguyen Duy Ngoc pointed out the experiences in site clearance for Ring Road 1, which need to be replicated for other projects.

Hanoi announces good news about the Ring Road 1 project

SÓNG HỮU |

Hanoi has basically completed the land acquisition and site clearance for the Ring Road 1 project (Hoang Cau - Voi Phuc section) after 7 years of implementation.

The first ward to complete site clearance for the Ring Road 1 project

SÓNG HỮU |

Hanoi - O Cho Dua Ward has officially completed site clearance for the Hoang Cau - Voi Phuc section of Ring Road 1 construction project.