More than 3km of Tan Son Nhat gateway road, Ho Chi Minh City has not been expanded for 20 years

MINH QUÂN |

HCMC - After 20 years of approval, the Pham Van Bach road expansion project, adjacent to Tan Son Nhat airport, is still unfinished due to the problem of 57 households not yet handing over the site.

The Pham Van Bach Street expansion project, passing through Tan Binh and Go Vap districts, was approved by the Ho Chi Minh City People's Committee in 2005 with a total initial investment of more than 273 billion VND.

This is a project implemented in the form of "The State and the People work together". Households that were partially cleared contributed by reducing the compensation value by 50%.

The total initial cost of compensation and site clearance is more than 195 billion VND, of which the Ho Chi Minh City budget spends nearly 148 billion VND, and the people contribute more than 47.6 billion VND.

However, over time, the project has been adjusted many times, the total investment capital has increased to about 680 billion VND, mainly to supplement compensation costs.

The project is divided into two branches. In particular, branch 1 (on Tan Son Street, Go Vap District) extending 2.2km from the Military Control Gate to Quang Trung Street, with a 12 - 22m wide road surface for 2 - 4 lanes of traffic, has been completed and put into use.

Duong Pham Van Bach doan gan Truong Chinh chua duoc mo rong, thuong xuyen un tac. Anh: Minh Quan
Pham Van Bach Street near Truong Chinh has not been expanded, and is often congested. Photo: Minh Quan

On the contrary, branch 2 on Pham Van Bach Street is 3.2km long, 13.5 - 23m wide, and is still unfinished. Since 2019, the project has had to be temporarily suspended due to land clearance problems from 57 households that have not yet handed over.

Currently, on Pham Van Bach Street, many houses that have not been cleared are still interspersed between households that have handed over the site, creating a messy and unsynchronized landscape.

Many narrowed sections of the road are only 6 - 7m wide, forming "bottleneck" bottlenecks, causing frequent traffic congestion, especially during rush hour.

The situation of encroaching on sidewalks for business and spontaneous markets has further caused chaos in traffic in the area, especially the section adjacent to Truong Chinh Street.

Nguoi dan tren duong Pham Van Bach bay ban tran lan ra ngoai duong. Anh: Minh Quan
People on Pham Van Bach Street sell goods that overflow onto the street. Photo: Minh Quan

According to the People's Committee of Tan Binh District, compensation and site clearance work has encountered many difficulties because some households have not agreed with the policy of "The State and the people work together". These households have opinions on the route, land prices and support policies for encroached land, causing the progress to be prolonged.

To date, out of a total of 702 related cases, 631 cases have agreed to receive compensation (reaching 89.88%), and 645 cases have handed over the site (reaching 91.88%).

However, there are still 57 cases that have not yet handed over the site, which is the main reason why branch 2 of the project cannot continue implementation.

Nhung can nha tren duong Pham Van Bach chua ban giao mat bang.  Anh: Anh Tu
The houses on Pham Van Bach Street have not yet been handed over the land. Photo: Anh Tu

Tan Binh District People's Committee said that it has directed functional units to continue to increase mobilization, contact with people, answer questions, and reach consensus to soon complete site clearance work.

In addition, the Traffic Construction Investment Project Management Board (investor) is required to review the route, resolve people's petitions and immediately deploy construction at locations with vacant premises, in order to improve urban aesthetics and reduce traffic pressure.

Tan Binh District People's Committee aims to complete compensation and site clearance in the third quarter of 2025, creating conditions for the completion of the entire route, improving traffic capacity connecting the gateway area of Tan Son Nhat airport.

MINH QUÂN
TIN LIÊN QUAN

Ho Chi Minh City gateway expansion project: The district has completed site reporting, the investor says there are still problems

|

HCMC - The National Highway 50 expansion project reported by Binh Chanh District has completed site clearance, but the investor said there are still 3 areas that have not been handed over.

2 routes worth VND5,100 billion open the entrance to Tan Son Nhat T3 terminal

|

HCMC - The expanded Tran Quoc Hoan - Cong Hoa and Hoang Hoa Tham connecting road will open to traffic before April 30, creating two convenient directions to Tan Son Nhat T3 station.

The Eastern road of Ho Chi Minh City has been waiting for 9 years but still has not been widened

|

HCMC - The project to expand Luong Dinh Cua Street (Thu Duc City) with an investment capital of 826 billion VND has been implemented for 9 years, but the completion date has not yet been determined.

Updated gold price at the end of session 20.5: Gold rings continue to decrease

|

Updated gold prices at the end of the session on May 20 did not have any major fluctuations. Domestic gold ring prices decreased by 300,000-400,000 VND/tael.

The Fatherland Front has grown in organization, affirming its position and prestige

|

Chairman of the Central Committee of the Vietnam Fatherland Front Do Van Chien said that in the general development trend of the country, under the leadership of the Party, the Fatherland Front has had strong growth in organization and affirmed its position and prestige.

Department of Health Inspectorate inspects cosmetics company related to Doan Di Bang's husband

|

Dong Nai - The Department of Health Inspectorate inspected the company involved in the production and trading of cosmetics related to Doan Di Bang's husband.

Principal required to revoke letter of mobilization for funding for high school graduation exam

|

Tien Giang - The Department of Education and Training of Tien Giang province requested the revocation of the open letter to mobilize funding for the high school graduation exam.

Senior Lieutenant General Tran Quoc To: Avoid playing down the commune-level police as an investigation agency

|

Deputy Minister of Public Security Tran Quoc To affirmed that the commune-level police are not an investigation agency.

Ho Chi Minh City gateway expansion project: The district has completed site reporting, the investor says there are still problems

MINH QUÂN |

HCMC - The National Highway 50 expansion project reported by Binh Chanh District has completed site clearance, but the investor said there are still 3 areas that have not been handed over.

2 routes worth VND5,100 billion open the entrance to Tan Son Nhat T3 terminal

MINH QUÂN |

HCMC - The expanded Tran Quoc Hoan - Cong Hoa and Hoang Hoa Tham connecting road will open to traffic before April 30, creating two convenient directions to Tan Son Nhat T3 station.

The Eastern road of Ho Chi Minh City has been waiting for 9 years but still has not been widened

MINH QUÂN |

HCMC - The project to expand Luong Dinh Cua Street (Thu Duc City) with an investment capital of 826 billion VND has been implemented for 9 years, but the completion date has not yet been determined.