Mobilizing nearly 9,000 workers to build Long Thanh airport

HÀ ANH CHIẾN |

The investor is drastically requesting contractors to mobilize nearly 9,000 direct workers to accelerate the progress of the Long Thanh airport project.

The airport is short of 1,500 to 2,000 workers

According to Vietnam Airports Corporation (ACV), to date, the total value of output implemented of component project 3 of Long Thanh airport has reached more than 77% of the total value of signed contracts.

On the construction site, an average of 7,170 direct workers are currently maintained. However, personnel mobilization is currently a major obstacle when the entire project is short of about 1,500 to 2,000 workers, concentrated in the main bidding packages such as: 5. 10; 4. 8; 7. 8 and 11. 5.

Regarding progress, package 5.10 construction of passenger terminals has only achieved a volume of over 67% and must basically complete all items put into trial operation in batches from September 2026 and commercial operation in December 2026; Package 4.8 construction of inland port traffic has only achieved nearly 65% of the value of implementation; package 7.8 construction of freight terminal No. 1 has only achieved about 36% of the value of the volume of implementation; package 11.5 construction of parking garages has only achieved over 36%.

Construction and living conditions at the construction site, Long Thanh airport project area are still difficult; the construction site is large, many items are deployed outdoors, affected by hot sun and dust, leading to difficulties in attracting and maintaining the labor force.

To ensure detailed progress, ACV is drastically requesting contractors to mobilize more human resources, aiming for the target of nearly 9,000 direct workers and indirect staff to accelerate internal work and complete dossiers.

Establish scientific construction progress in the rainy season

Statistics show that in the 2025 rainy season, construction progress was delayed by 2 to 4 months due to the direct impact of weather, especially greatly affecting the progress of outdoor construction items.

Therefore, to organize construction to ensure progress and quality of works in the rainy season, ACV has requested contractors to thoroughly implement construction measures in the rainy season. In which, it is necessary to establish a scientific construction progress from the beginning, clearly divide each construction phase, estimate materials, human resources, and reasonable finances, prioritize items in the house during heavy rain; At the same time, establish an effective drainage system at the project, dig drainage ditches, collection pits and arrange backup water pumps in construction areas;

Contractors also need to closely monitor weather developments and flexibly adjust construction according to actual conditions, have contingency plans for arising situations...

The preparation for the operation of Long Thanh airport is also being accelerated. To date, Long Thanh International Airport said that it has received a total of 257 personnel to prepare for operation.

Talking to a reporter of Lao Dong Newspaper, Mr. Truong Trung Thanh - Deputy Director of Long Thanh International Airport - said that personnel are being arranged to work in reality at Tan Son Nhat International Airport and at the Long Thanh International Airport Project to accumulate experience; at the same time, learn from the new technical systems equipped in the near future when Long Thanh airport goes into operation, planned for the end of 2026.

Long Thanh Airport phase 1 builds 2 runways, 1 passenger terminal and synchronous auxiliary items, with a capacity of 25 million passengers/year and 1.2 million tons of cargo/year; completion and commissioning time at the end of 2026.

HÀ ANH CHIẾN
RELATED NEWS

Long Thanh Airport: Some bidding packages exceed 90%, new bidding packages reach 36%

|

Dong Nai - Many main construction packages at Long Thanh airport have reached over 90%, including a package that has been basically completed.

Long Thanh airport approaches the milestone of having 2 runways 4km long

|

Dong Nai - Package 4.12 construction of the 2nd runway of Long Thanh airport is expected to complete all items before September 30, 2026.

Long Thanh airport reaches nearly 78%, still lacking 2,000 workers

|

Dong Nai - Long Thanh airport construction site is maintaining more than 7,000 direct workers and will increase to 9,000 people to complete the project.

"I am 95 years old, and my husband is still forever the most beautiful youth on the battlefield"

|

Although the war has receded, many families of martyrs are still diligently on their journey to find their loved ones - those who have spent their whole youth on the fierce battlefield.

Russia attacks Chernomorsk container port and cargo ship

|

The Russian Ministry of Defense said it has used high-precision weapons launched from the sea and drones targeting Ukrainian transport infrastructure.

Ho Chi Minh City Trade Union lights candles, takes care of martyrs' cemeteries

|

The Ho Chi Minh City Trade Union organization always cherishes and has many practical activities to show gratitude to people with meritorious services to the revolution.

Ho Chi Minh City College of Economics and Technology owes teachers and staff more than 26 billion VND

|

13 teachers of Ho Chi Minh City College of Economics and Technology recently filed a lawsuit and authorized officials of the Ho Chi Minh City Trade Union Workers' Counseling and Support Center to protect their rights, requesting the school to pay outstanding salaries from 2022 with a total amount of more than 4 billion VND.

Long Thanh Airport: Some bidding packages exceed 90%, new bidding packages reach 36%

HÀ ANH CHIẾN |

Dong Nai - Many main construction packages at Long Thanh airport have reached over 90%, including a package that has been basically completed.

Long Thanh airport approaches the milestone of having 2 runways 4km long

HÀ ANH CHIẾN |

Dong Nai - Package 4.12 construction of the 2nd runway of Long Thanh airport is expected to complete all items before September 30, 2026.

Long Thanh airport reaches nearly 78%, still lacking 2,000 workers

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport construction site is maintaining more than 7,000 direct workers and will increase to 9,000 people to complete the project.