Urgently level the ground for the expressway rest stop through Thanh Hoa

QUÁCH DU |

Thanh Hoa - At the Truc Lam rest stop project, the construction unit is mobilizing machinery and manpower to level hills and deploy construction items.

According to records of Lao Dong Newspaper reporters in the Truc Lam rest stop project area, Truc Lam ward, Thanh Hoa province, in the last days of August, the construction unit is focusing machinery and vehicles to level, create ground and deploy some items.

Khu vực trạm dừng nghỉ Trúc Lâm (bên phải tuyến cao tốc Bắc - Nam). Ảnh: Quách Du
Truc Lam rest stop area (right side of the North - South expressway). Photo: Quach Du

Truc Lam rest stop is located at Km366+850 (right route) and Km366+920 (left route), belonging to the component project of National Highway 45 - Nghi Son on the North - South expressway in the East.

Records at the scene show that in both the right and left positions of the expressway, the project site is being leveled. Many excavators, vehicles and construction equipment have been mobilized to the construction site to excavate, transport soil and create ground for the construction of subsequent items.

Some initial items of the rest stop are also being implemented. However, most of the project area is still in the leveling and completion phase.

Đơn vị thi công khẩn trương san gạt đồi để thực hiện dư án. Ảnh: Quách Du
The construction unit urgently leveled the hill to implement the project. Photo: Quach Du

Talking to a reporter from Lao Dong Newspaper, a representative of the Appraisal Department, Vietnam Road Administration, said that so far the investor has completed the connection system and access roads to the rest stop area. Some items serving the immediate needs of traffic participants such as parking lots and toilets have also been arranged.

According to a representative of the Vietnam Road Administration, the contract progress is expected to be completed by the end of 2026.

The project is affected by the progress due to slow site handover. Currently, the investor is focusing on implementing items to ensure progress according to the contract" - representative of the Appraisal Department, Vietnam Road Administration said.

Khu vực trạm dừng nghỉ đã được đấu nối, các phương tiện có thể ra vào. Ảnh: Quách Du
The rest stop area has been connected, vehicles can enter and exit. Photo: Quach Du
Nhiều trang thiết bị, vật tư được tập kết để phục vụ việc thi công. Ảnh: Quách Du
Many equipment and materials are gathered to serve the construction. Photo: Quach Du
Một số hạng mục như trạm tiếp nhiên liệu đã được xây dựng và đang trong quá trình hoàn thiện. Ảnh: Quách Du
Some items such as the refueling station have been built and are in the process of completion. Photo: Quach Du

QUÁCH DU
RELATED NEWS

Traveling on the North-South Expressway on September 2nd, stay right at 27 rest stops and gas stations, charging stations

|

On September 2nd, the North-South expressway has 27 rest stops, 11 places with gas stations and 5 places equipped with charging stations.

Lang Son considers terminating contract for expressway rest stop project

|

Lang Son - The Huu Lung Rest Stop project contract was signed in September 2023, but after nearly three years, it is still necessary to review obligations, progress and termination conditions.

Only 4/21 rest stops on the North - South expressway in the East have electric vehicle charging stations operating

|

Only 4/21 rest stops on the North - South expressway in the East have put part of the electric vehicle charging station system into operation.

Request immediate construction of the remaining rest stop on Vinh Hao - Phan Thiet expressway

|

Lam Dong - Although there is still 1 household that has not handed over the site, the investor is required to accelerate the construction of a rest stop on the Vinh Hao - Phan Thiet expressway.

Overnight completion of Muong Khuong boarding school before opening

|

Lao Cai - Workers are working overnight, urgently completing the final parts at Muong Khuong boarding school before the opening day.

Dak Lak Department of Health Party Committee disciplined with a warning for violations related to the hospital project

|

Dak Lak - The Party Committee of the Provincial Department of Health was disciplined with a warning by competent authorities for violations related to the Tay Nguyen Regional General Hospital project.

5-day weather forecast for September 2nd holiday nationwide, areas with thunderstorms

|

The National Center for Hydro-Meteorological Forecasting has updated detailed weather forecast information during the National Day holiday of September 2nd.

Urgently level the ground for the expressway rest stop through Thanh Hoa

|

Thanh Hoa - At the Truc Lam rest stop project, the construction unit is mobilizing machinery and manpower to level hills and deploy construction items.

Traveling on the North-South Expressway on September 2nd, stay right at 27 rest stops and gas stations, charging stations

Tô Thế |

On September 2nd, the North-South expressway has 27 rest stops, 11 places with gas stations and 5 places equipped with charging stations.

Lang Son considers terminating contract for expressway rest stop project

Khánh Linh |

Lang Son - The Huu Lung Rest Stop project contract was signed in September 2023, but after nearly three years, it is still necessary to review obligations, progress and termination conditions.

Only 4/21 rest stops on the North - South expressway in the East have electric vehicle charging stations operating

Tô Thế |

Only 4/21 rest stops on the North - South expressway in the East have put part of the electric vehicle charging station system into operation.

Request immediate construction of the remaining rest stop on Vinh Hao - Phan Thiet expressway

Duy Tuấn |

Lam Dong - Although there is still 1 household that has not handed over the site, the investor is required to accelerate the construction of a rest stop on the Vinh Hao - Phan Thiet expressway.