Not ensuring the progress of the trillion-dong project in Bai Sau, Vung Tau

thành an |

Ba Ria - Vung Tau - Some items at the Thuy Van road renovation project have not been completed according to schedule, ensuring quality.

On February 14, Mr. Nguyen Van Tho - Chairman of the People's Committee of Ba Ria - Vung Tau province inspected and worked at the Thuy Van road renovation project, Vung Tau city.

This is an urban renovation project with a total investment of more than 1,000 billion VND, expected to be constructed within 180 days and completed before April 30. However, the project is currently behind schedule as planned.

Reporting at the meeting, the representative of the construction unit said that up to now, the package has been constructed for 108/180 days, reaching 60% of the total expected time. However, the construction progress is currently 10 days later than the original plan. The contractor has increased the number of employees to 700 people, along with 74 equipment, double the previous level and implemented additional overnight shifts to speed up the progress.

Previously, according to the announcement on February 11 of the People's Committee of Vung Tau City, after 105/180 days of construction, the completed volume on the project only reached 33% of the contract value, not meeting the requirement to complete at least 58% according to the initial approved schedule and 45% according to the approved adjusted schedule. The number of workers under construction is less than half of the contractor's commitment, as well as not organizing shifts 3... Although the People's Committee of Vung Tau City has issued a reminder document since the end of December 2024, the construction unit has not implemented it seriously, fully and promptly to overcome the situation. Some work items have not been completed according to schedule, ensuring quality.

Therefore, the People's Committee of Vung Tau City has requested the construction unit, Coteccons Construction Joint Stock Company, to strictly and fully implement the signed contracts; handle some work beginnings and fix locations that do not ensure quality; fully implement measures to ensure labor safety, environmental sanitation... at the project site.

After the actual inspection, the Chairman of the Provincial People's Committee requested the contractor to urgently overcome the remaining problems, speed up the construction progress and ensure the quality of the project, strive to complete the project on schedule.

Mr. Nguyen Van Tho also requested units to promptly report difficulties and problems to find solutions, ensuring the project is completed on schedule, contributing to improving the quality of urban infrastructure in Vung Tau City.

thành an
TIN LIÊN QUAN

Speeding up progress, Hoa Lien - Tuy Loan Expressway expected to open to traffic in August

|

The 11.5km Hoa Lien - Tuy Loan expressway project in Da Nang is in the final stage, expected to open to traffic on August 30. However, some difficulties in site clearance still exist as 12 households have not yet accepted the compensation plan.

Dong Nai checks the progress of key transport projects

|

Vice Chairman of Dong Nai People's Committee Ho Van Ha checked the progress of key projects of Bien Hoa - Vung Tau highway, belt 3 of Ho Chi Minh City, Huong Lo 2, Road 25C ...

Ho Chi Minh City speeds up progress of Long Thanh airport connection projects

|

HCMC - The An Phu intersection project, Ring Road 2, 3, and the expansion of the HCMC - Long Thanh - Dau Giay expressway are required to speed up progress to connect to Long Thanh airport.

Mr. Nguyen Van Tho is assigned to be the Standing Vice Chairman of the Ho Chi Minh City People's Committee

|

HCMC - Mr. Nguyen Van Tho was assigned to hold the position of Permanent Vice Chairman of the HCMC People's Committee.

Benchmark scores for grade 10 admission to 4 specialized schools in Hanoi in 2025

|

The benchmark score for grade 10 of 4 high schools for the 2025-2026 school year has been announced by the Hanoi Department of Education and Training.

Ms. Paetongtarn begins her first day of work in her new position

|

On July 4, Ms. Paetongtarn Shinawatra began her first working day as Minister of Culture after being suspended from the position of Prime Minister of Thailand.

List and codes of 34 provinces and cities, 3,321 new commune-level administrative units

|

The decision stipulates the list and codes of Vietnamese administrative units including 34 provinces and cities used uniformly nationwide from July 1, 2025.

AFC denies Malaysia's investigation into naturalized players

|

The Asian Football Confederation (AFC) has dispelled all speculation about the investigation of Malaysian football, related to the use of naturalized players.

Speeding up progress, Hoa Lien - Tuy Loan Expressway expected to open to traffic in August

Nguyễn Linh |

The 11.5km Hoa Lien - Tuy Loan expressway project in Da Nang is in the final stage, expected to open to traffic on August 30. However, some difficulties in site clearance still exist as 12 households have not yet accepted the compensation plan.

Dong Nai checks the progress of key transport projects

HÀ ANH CHIẾN |

Vice Chairman of Dong Nai People's Committee Ho Van Ha checked the progress of key projects of Bien Hoa - Vung Tau highway, belt 3 of Ho Chi Minh City, Huong Lo 2, Road 25C ...

Ho Chi Minh City speeds up progress of Long Thanh airport connection projects

Huyền Trân |

HCMC - The An Phu intersection project, Ring Road 2, 3, and the expansion of the HCMC - Long Thanh - Dau Giay expressway are required to speed up progress to connect to Long Thanh airport.