Lang Son tightens progress to remove obstacles for 2 PPP projects in Loc Binh

Khánh Linh |

Lang Son - The Provincial People's Committee requests departments, branches, localities and investors to accelerate the removal of obstacles at 2 PPP projects in Loc Binh.

On March 12, according to Lao Dong's source, Lang Son Provincial People's Committee has just requested departments, branches, local authorities and investors to focus on thoroughly removing difficulties and obstacles for 2 public-private partnership (PPP) investment projects in old Loc Binh district.

The direction was stated in the conclusion of Standing Vice Chairman of the Provincial People's Committee Dinh Huu Hoc for 2 projects including: Loc Binh Bridge Project No. 1, traffic road and resettlement area of Luc Thon commune; Project to build technical infrastructure, social infrastructure for resettlement area and rural residents of Huu Khanh commune.

For the Loc Binh Bridge Project No. 1, traffic road and Luc Thon commune resettlement area, the Provincial People's Committee basically agreed to adjust the investment policy.

The adjustment content relates to the scale of some items, total investment, land area for BT project implementation and counterpart land fund paid to investors.

To ensure strictness, the Department of Finance is assigned to take the lead in reviewing, supplementing and clarifying in writing the legal bases related to the increase in land area for BT projects and the counterpart land fund, ensuring compliance with regulations.

The adjustment of the land fund for payment must be determined on the basis of being equivalent to the value of the BT project after adjusting the total investment.

The entire content must be completed and reported to the Provincial People's Committee before March 14, 2026.

Along with that, Loc Binh Commune People's Committee is assigned to preside over and coordinate with the Provincial Land Fund Development Center, the Provincial Construction Investment Project Management Board, investors and related units to urgently develop a site clearance plan, and send it to relevant agencies before March 14.

Investors and project businesses are required to urgently complete the resettlement area to meet the conditions for site clearance for residential land, and at the same time complete procedures to submit for appraisal and approval of project adjustments when conditions are met.

For the Huu Khanh commune resettlement area and rural residential area project, the key requirement is to thoroughly handle the contents related to planning.

The Department of Construction is assigned to preside over the overall review, propose adjustments to the planning once in a comprehensive and synchronous direction, clarify the causes, scope and items to be adjusted, ensure connection of technical infrastructure and social infrastructure; complete the report to the Provincial People's Committee before March 14, 2026.

Loc Binh Commune People's Committee continues to be assigned to develop a site clearance plan for the Huu Khanh project, striving to hand over the entire clean site to the investor in the second quarter of 2026.

Lang Son Provincial People's Committee also emphasized that heads of departments, branches, Loc Binh commune government, investors and members of the working group must be responsible to the Provincial People's Committee and the Chairman of the Provincial People's Committee for the results of assigned tasks.

Khánh Linh
RELATED NEWS

200MW hydropower plant project in Dong Nai entangled with site clearance

|

Dong Nai - On March 12, the Provincial People's Committee worked with relevant units on the progress of site clearance for the Tri An Hydropower Plant expansion project.

The army is mobilized to participate in the construction of the Dong Dang - Tra Linh expressway

|

Cao Bang - 107 officers and soldiers of the army are assigned to participate in the construction of the Dong Dang - Tra Linh expressway.

Phase 1 of Dong Dang - Tra Linh route receives completion order in 2026

|

Cao Bang - The Minister of Construction has just paid a visit and directed the construction progress of the Dong Dang - Tra Linh expressway.

Leaving crowded roads and traffic jams, people in Hanoi take the tram home

|

Hanoi - After rush hour, many people have chosen electric trains to travel quickly, reduce congestion, and contribute to promoting green traffic.

63 people in An Giang suspected of poisoning after eating cake

|

An Giang - Functional forces are investigating and verifying a suspected case of collective food poisoning when eating cakes from a facility in Rach Gia ward.

Special polling stations in Hanoi are ready to welcome a big festival

|

Kim Lien communal house (Hanoi) - one of the "Thang Long Tu Tran" districts selected as a voting location for the election of National Assembly Deputies of the 16th term and People's Council Deputies at all levels.

14th Vietnam Trade Union Congress is expected to be held at the end of May 2026

|

Hanoi - The 14th Congress of the Vietnam Trade Union is expected to be held at the end of May 2026. The information was released at a press meeting on the afternoon of March 12 organized by the Vietnam General Confederation of Labour.

Gasoline and oil prices decrease, railway prices and freight rates reduced from March 13

|

After domestic gasoline and oil prices sharply decreased, the railway industry adjusted to reduce passenger fares by 3% and freight rates by 4%, applying from 0:00 on March 13.

200MW hydropower plant project in Dong Nai entangled with site clearance

HÀ ANH CHIẾN |

Dong Nai - On March 12, the Provincial People's Committee worked with relevant units on the progress of site clearance for the Tri An Hydropower Plant expansion project.

The army is mobilized to participate in the construction of the Dong Dang - Tra Linh expressway

Duy Dũng |

Cao Bang - 107 officers and soldiers of the army are assigned to participate in the construction of the Dong Dang - Tra Linh expressway.

Phase 1 of Dong Dang - Tra Linh route receives completion order in 2026

Duy Dũng |

Cao Bang - The Minister of Construction has just paid a visit and directed the construction progress of the Dong Dang - Tra Linh expressway.