Ho Chi Minh City leaders request maximum mobilization of human resources and equipment to speed up Xuyen Tam canal

Anh Tú |

On the morning of November 18, Ho Chi Minh City started construction of two packages XL-01 and XL-02 of the Xuyen Tam canal project, completing the entire implementation of nearly 9 km and setting a goal of shortening the progress.

On the morning of November 18, the Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board (UICI) held a groundbreaking ceremony for the XL-01 and XL-02 packages, the last two packages of the Xuyen Tam Canal dredging, environmental improvement and infrastructure construction project.

Khoi cong 2 goi thau con lai cua du an cai tao rach Xuyen Tam. Ảnh: Anh Tu
Starting construction of the remaining 2 packages of the Xuyen Tam canal renovation project. Photo: Anh Tu

The XL-01 package has a range from Nhieu Loc - Thi Nghe canal to Bui Dinh Tuy bridge, including Cau Son canal, about 2.94 km long. Package XL-02 continues from Bui Dinh Tuy Bridge to Luong Ngoc Quyen Street, including Binh Loi and Binh Trieu Canals. These are two sections with a large population, degraded infrastructure, flooding and pollution for many years.

According to the investor, the two packages were implemented by consortia, with a total value of more than VND 2,300 billion. The units have fully prepared human resources, machinery, and materials for construction immediately after the groundbreaking ceremony.

Speaking at the ceremony, Vice Chairman of the Ho Chi Minh City People's Committee Bui Xuan Cuong emphasized that Xuyen Tam canal is an important infrastructure project with a large impact area with more than 2,000 households. He requested that compensation and resettlement work must be prioritized to both ensure construction site and stabilize people's lives.

Rach Xuyen Tam noi tu kenh Nhieu Loc - Thi Nghe den song Vam Thuat. Ảnh: Anh Tu
Xuyen Tam Canal connects from Nhieu Loc - Thi Nghe Canal to Vam Thuat River. Photo: Anh Tu
Mot so doan ngap day rac. Ảnh: Anh Tu
Some sections are flooded with garbage. Photo: Anh Tu

Regarding progress, Mr. Cuong suggested that the XL-03 package that had started construction before should shorten the completion date from November 2026 to around September 2026. The two packages XL-01 and XL-02 started construction today and have an approval date until 2028, but Ho Chi Minh City requires striving to complete them in 2027. Immediately after the groundbreaking ceremony, contractors must immediately deploy construction, mobilize all necessary machinery and workers; organize construction in 3-4 shifts if necessary, taking advantage of the time the rainy season has ended to speed up, not allowing the work to start and then be delayed, Mr. Cuong directed.

He also noted that in 2025, the project was allocated VND1,800 billion but only disbursed nearly 50%, lower than the general level of Ho Chi Minh City, the Investor and contractor must speed up construction and disbursement, ensuring the completion of 100% of the capital plan. In terms of land, the four wards involved must hand over all in November according to the direction of the City Party Committee; any problems with resettlement and compensation must be reported immediately to be resolved.

"The city also requires wards to review and adjust the planning along the route to synchronize with the infrastructure after completion. Departments such as Construction, Architectural Planning, Finance... must accompany investors in quality supervision and capital allocation," said Mr. Cuong.

Today's groundbreaking marks the official implementation of all three packages of the Xuyen Tam canal project on the entire route. The project has a total length of nearly 9 km, a total investment of more than VND 17,000 billion from the City budget, including dredging items, renovating canals, building anti-landslide embankments, wastewater collection and drainage systems, traffic roads along both sides of the canals, parks and green areas. When completed, the project is expected to solve flooding and pollution that has lasted for many years, while forming a new traffic landscape axis, improving the living environment for tens of thousands of residents in Binh Thanh, Gia Dinh, Binh Loi Trung and An Nhon areas.

Anh Tú
RELATED NEWS

More than 2,200 households were cleared, Xuyen Tam canal must complete compensation in November

|

HCMC The Xuyen Tam canal renovation project needs to reclaim land from more than 2,200 households. The Ho Chi Minh City People's Committee requested to complete site clearance in November 2025.

Starting construction of a social housing project worth nearly 1,000 billion VND to serve the resettlement of the Xuyen Tam canal project

|

On the morning of August 8, Ho Chi Minh City started the 864 apartment social housing project at 4 Phan Chu Trinh, Binh Thanh Ward.

People expect the government to be determined to renovate Xuyen Tam canal in Ho Chi Minh City

|

HCMC - People expect the Xuyen Tam canal renovation project to be implemented on schedule, soon returning a clean living environment to the area.

Live football U22 Vietnam vs U22 Korea at Panda Cup 2025

|

Live football U22 Vietnam and U22 Korea at Panda Cup 2025, taking place at 2:30 p.m. today (November 18).

Minister of Finance: Many projects have money but cannot be disbursed

|

Explaining to the National Assembly, the Minister of Finance admitted that investment procedures are still cumbersome, many projects have money but cannot be disbursed.

Khanh Le Pass connecting Nha Trang - Da Lat continues to collapse, preparing to blast to break rocks to clear the route

|

Khanh Hoa - The authorities recorded a large rock block blocking the road surface on Khanh Le Pass, forcing a blasting plan to clear the route soon.

162 cosmetic products of Mailisa Aesthetic Institute were discovered to be urgently inspected

|

The Ministry of Health requested the urgent testing and review of more than 162 cosmetic products of Mailisa Aesthetic Institute.

Turning the strength of great solidarity into a soft power in developing the capital

|

The Secretary of the Hanoi Party Committee emphasized the need to continue to strengthen the great national unity bloc; turn the strength of great solidarity into "soft power" in developing the capital.

More than 2,200 households were cleared, Xuyen Tam canal must complete compensation in November

MINH QUÂN |

HCMC The Xuyen Tam canal renovation project needs to reclaim land from more than 2,200 households. The Ho Chi Minh City People's Committee requested to complete site clearance in November 2025.

Starting construction of a social housing project worth nearly 1,000 billion VND to serve the resettlement of the Xuyen Tam canal project

Anh Tú |

On the morning of August 8, Ho Chi Minh City started the 864 apartment social housing project at 4 Phan Chu Trinh, Binh Thanh Ward.

People expect the government to be determined to renovate Xuyen Tam canal in Ho Chi Minh City

ÁNH TÚ |

HCMC - People expect the Xuyen Tam canal renovation project to be implemented on schedule, soon returning a clean living environment to the area.