A series of unfinished transportation projects in Hoai Duc, Hanoi

HỮU CHÁNH |

Hanoi - Difficulties in site clearance have caused a series of traffic projects in Hoai Duc district to stall for many years, with no completion date set.

slower construction

According to the report of the Hoai Duc District Investment and Construction Project Management Board (Hanoi), up to now, the progress of the district's infrastructure projects has not been largely completed, so the connection between communes is still not complete.

For example, at the Ring Road 3.5 project (phase 1), although construction started on October 28, 2017, the implementation is estimated to reach 90% of the contract volume.

The Ring Road 3.5 project (phase 2) started construction on January 28, 2019, but so far the implementation volume has only reached about 80%.

The Ring Road 3.5 project (phase 3), implementation period from 2022-2025 (started on June 30, 2023), has only reached about 40% of the construction volume.

a
The project to build the 3.5 Ring Road (from Thang Long Avenue to National Highway 32, Hoai Duc, Hanoi) is 5.5km long and has been unfinished for many years. Photo: Huu Chanh

With the Lien Hoan 1 project (from National Highway 32 to the intersection with Lai Yen - Van Canh road) over 6km long, construction has been implemented since December 2020, expected to be completed after about 540 days, but so far only 80% of the work has been completed.

The situation of delays also occurs in the Lai Yen - Van Canh road project (from Lien Hoan Lo 2 to Ring Road 3.5).

The route is 2.9km long, with a total investment of about 470 billion VND. The project started construction in October 2020, expected to be completed in the third quarter of 2022, but the entire route has not yet been opened to traffic.

s
Lai Yen - Van Canh road is still unfinished after more than 4 years of construction. Photo: Huu Chanh

The Lien Khu 6 road project (from Lien Khu 1 road to Ring Road 3.5), has currently only reached 55% of the contract volume. The construction site is unfinished, with no construction activities.

Difficulties waiting to be resolved

According to the representative of the Hoai Duc District Construction Investment Project Management Board, the reason for the delay in the progress of infrastructure projects in the area is due to problems in site clearance.

For example, in the Ring Road 3.5 project (phase 2), although started in 2019, the section from Km5+020 - Km5+300 has not yet been handed over the site due to the Vuon Chuoi Archaeological Site.

The Ring Road 3.5 project (phase 3) needs to reclaim land from 6 enterprises in the An Khanh Industrial Cluster, but so far only 4/6 enterprises have been counted.

s
An Khanh Industrial Cluster has not been cleared to complete the Ring Road 3.5 project, phase 3. Photo: Huu Chanh

The reason for the delay in the Inter-regional Road 1 project is that some sections have not completed site clearance, including about 1ha of national defense land.

In Duc Thuong commune, there are still about 50 plots of land that have not been clearly identified as owners and purposes of use to have a basis for submitting to the District People's Committee to issue a notice of land reclamation.

s
Lien Duong Khu 1 is stuck with a part of the national defense land area and 50 plots of land have not yet been identified for use. Photo: Huu Chanh

At the Lai Yen - Van Canh road project, the site clearance work is still stuck with residential land of 9 households and individuals (54.9m2) and business and service land of 4 households and individuals (6.3m2) in Lai Yen commune, and has only issued a notice of land reclamation.

In Van Canh commune, there are still 21 graves, including 16 graves of households that have not received money and have not been relocated, and 5 graves of households that have not been declared and counted.

The Lai Yen - Van Canh road project is still stuck with a warehouse managed by the Logistics Department - Ministry of National Defense with an area of 1,044m2.

s
A part of the site has not been handed over to the Lai Yen - Van Canh road project. Photo: Huu Chanh

A representative of the Hoai Duc District Construction Investment Project Management Board said that to ensure good implementation of assigned tasks in 2025, the Project Management Board hopes that Hoai Duc District will prioritize the allocation of implementation funds, to ensure the settlement progress and project implementation time.

The functional units and the People's Committees of communes promptly organize the declaration of the inventory, establishment, listing, submission for approval of the plan and payment of compensation to organizations, households, and individuals, so that the implementation of the projects is in accordance with the set progress plan.

The Urban Management Department needs to coordinate with the Project Management Board to organize appraisal, adjust and supplement arising issues under the authority of project investors, ensuring progress according to regulations.

HỮU CHÁNH
TIN LIÊN QUAN

Khuat Duy Tien intersection after 1 month of traffic reorganization

|

Hanoi - After 1 month of traffic reorganization, the Nguyen Trai - Khuat Duy Tien intersection is more orderly, but congestion still occurs on some roads around the area.

Tam Trinh Street after half a year of expansion

|

Hanoi - The site is still "oo dau" which makes it impossible for the contractor to synchronously construct the Tam Trinh road expansion project, with a capital of nearly VND3,400 billion.

Tomorrow, Hanoi will reorganize traffic on the 8-lane road

|

Hanoi - On February 24, the authorities will fence off the Tran Huu Duc - Nguyen Van Giap intersection and turn off the light signal at this intersection to reduce traffic conflicts.

Cold air is about to get stronger, causing rain, forecasting the coldest day

|

According to the meteorological agency, from tonight, February 23, the cold air will begin to cause a deeper drop in temperature in the North.

Appointment of Police Director and 2 Chief Prosecutors

|

Last week (February 17-23) recorded the appointment of the Director of the Bac Giang Provincial Police and two Chief Prosecutors of the Military Procuracy.

NATO spills $22 billion to expand fuel pipeline on the east side

|

NATO plans to expand the pipeline from Germany to Poland and the Czech Republic to speed up fuel transportation in case of conflict.

Continue to forecast optimism about Vietnam's GDP growth in 2025

|

International economic and financial organizations forecast Vietnam's GDP growth in 2025 to be optimistic.

Union Newsletter: Basic salary coefficient according to the new decree

|

Union newsletter: Basic salary coefficient according to the new decree; Union proposes to increase salaries and benefits for the textile and garment industry;...

Khuat Duy Tien intersection after 1 month of traffic reorganization

HỮU CHÁNH |

Hanoi - After 1 month of traffic reorganization, the Nguyen Trai - Khuat Duy Tien intersection is more orderly, but congestion still occurs on some roads around the area.

Tam Trinh Street after half a year of expansion

HỮU CHÁNH |

Hanoi - The site is still "oo dau" which makes it impossible for the contractor to synchronously construct the Tam Trinh road expansion project, with a capital of nearly VND3,400 billion.