Nhon - Hanoi Railway Station metro tunnel excavator has arrived at S10 station

Tô Thế |

The Hanoi Urban Railway Management Board (MRB) has just issued new information on the progress of the Nhon - Hanoi Railway Station metro tunnel excavation, the location of the TBM is available.

On March 7, MRB informed that the TBM No. 1 tunnel excavator named " expressway" has officially arrived at S10 - Cat Linh station, marking an important milestone in the construction of the Nhon - Hanoi Railway Station urban railway line.

The TBM is the first tunnel excavator to start construction in the CP03 package - tunnel and underground stations of the project. Starting from S9 - Kim Ma station from July 30, 2024, after many months of safe operation, the engine has completed the drilling and installation of a tunnel shell with a length of more than 1,338m to S10 - Cat Linh station, strictly complying with technical and environmental standards.

sss
The TBM1 engine digging to S10 station is an important milestone. Photo: MRB

TBM No. 2 has also started starting from S9 station (Kim Ma station) since February 3, 2025. It is expected that both TBMs will complete all tunnel drilling work by the end of 2025.

"The official arrival of the TBM to Station S10 - Cat Linh is an important step forward for the project. This is the result of continuous efforts to overcome difficulties, as well as close coordination between MRB, Consultants, contractors and stakeholders in ensuring the progress, quality and safety of the project.

This is an important milestone, bringing the project closer to the goal of completing the underground section to serve the people of the capital", said Mr. Nguyen Ba Son - Deputy Head of the Hanoi Railway Management Board.

d
Diagram of the underground section of the Nhon - Hanoi Railway Station metro. Photo: MRB

As of March 2, 2025, the overall construction progress of the CP03 - tunnel and underground stations package has reached 55.38%; The underground slope has been completed 76.63%; Station S9 has completed 50.50%; The vertical well is completed 24.51%; the tunnel has reached 51.48%.

Stations S10, S11, S12 (including lane change and garage) are completed with 64.64%, 58.1%, 59.74%, respectively.

It is expected that the underground section will be completed in 2027, after which the entire urban railway line No. 3, the Nhon - Hanoi Railway Station section will be put into operation, contributing to changing the appearance of the capital, conveniently connecting areas and promoting sustainable development and greening urban traffic.

Tô Thế
TIN LIÊN QUAN

Seen from above, Metro No. 2 ground is clear

|

HCMC - The site clearance work for Metro Line 2 has reached nearly 100%. The final items are being urgently completed, ready to start construction at the end of 2025.

Subsidence exceeds warning threshold at the site of metro tunnel excavation

|

According to monitoring data from the Nhon - Hanoi Railway Station metro project construction unit, some points in lane 7 Giang Van Minh (Hanoi) have subsidence exceeding the warning threshold.

New images at the site affected by the metro tunnel excavation incident

|

After 5 days of the incident of overflowing allowances during the digging of the Nhon - Hanoi Railway Station metro tunnel, the repair work has been basically completed.

Colonel Tran Hong Minh becomes Deputy Director of Ho Chi Minh City Police

|

HCMC - On March 10, Colonel Tran Hong Minh - Deputy Director of Tra Vinh Provincial Police - was transferred to the position of Deputy Director of HCMC Police.

Ukraine smashes missiles into Russian squat

|

Ukraine's airstrike on Russia by rocket launched from the HIMARS system on March 9 damaged many facilities and caused casualties.

The 2025 National Volleyball Championship is about to kick off

|

Phase 1 - the 2025 National Volleyball Championship will kick off on March 22.

EU still considers using frozen Russian assets

|

Despite Moscow's warnings, EU member states and the UK are still planning to use frozen Russian assets to support Ukraine.

May have to pay 300,000 VND/guest for route No. 6 Ha Long Bay

|

Quang Ninh - The Ha Long 6 Bay Journey has no points for tourists to visit, while the fee calculation method will be very difficult to connect the Ha Long Bay - Cat Ba tour.

Seen from above, Metro No. 2 ground is clear

Anh Tú |

HCMC - The site clearance work for Metro Line 2 has reached nearly 100%. The final items are being urgently completed, ready to start construction at the end of 2025.

Subsidence exceeds warning threshold at the site of metro tunnel excavation

Tô Thế |

According to monitoring data from the Nhon - Hanoi Railway Station metro project construction unit, some points in lane 7 Giang Van Minh (Hanoi) have subsidence exceeding the warning threshold.

New images at the site affected by the metro tunnel excavation incident

Tô Thế |

After 5 days of the incident of overflowing allowances during the digging of the Nhon - Hanoi Railway Station metro tunnel, the repair work has been basically completed.