Contractor uses bamboo to block electric wires to construct Khanh Hoa - Buon Ma Thuot expressway

BẢO LÂM |

Dak Lak - The Khanh Hoa - Buon Ma Thuot Expressway Project Phase 1 is facing difficulties due to delays in site clearance and relocation of high-voltage power lines.

On July 12, the Dak Lak Province Traffic Construction Investment and Rural Development Project Management Board (representative of the investor) announced the implementation of component project 3.

The announcement also clearly states the shortcomings and problems in the investment project to build the Khanh Hoa - Buon Ma Thuot expressway phase 1.

According to the report from the project investor's representative, at the meeting on March 17, 2025, Deputy Prime Minister Le Thanh Long pointed out that the construction progress at components 1 and 3 of the project has not met requirements, while the remaining workload is very large.

Specifically, the section through Dak Lak province still has 10 hectares of land that need site clearance and a location of a high-voltage power line that has not been handled.

The Deputy Prime Minister requested the Dak Lak Provincial People's Committee to strengthen propaganda and mobilize people to quickly hand over the site, and at the same time direct the acceleration of the relocation of technical infrastructure works. The Deputy Prime Minister requested the completion and handover of the entire site before March 31.

However, up to now, the residential power line running through the construction site has not been relocated, causing difficulties for construction.

At the construction site, contractors have to use bamboo to support the line to ensure the movement of vehicles.

Viec cham di doi duong day dien anh huong den thi cong du an cao toc. Anh: Bao Lam
The delay in relocating the power line affects the construction of the expressway project. Photo: Bao Lam

According to a representative of Dak Lak Power Company, the project to relocate the power system at the expressway project was previously prepared by the Project Management Board of the old Krong Pac district.

However, during the process of submitting the funding application, the power line behind the people's meters was not included in the estimate.

The electricity industry has continued to support the locality in developing a new plan and submitting to the competent authority additional funding estimates to relocate the people's power line in the coming time.

This delay is believed to be due to a mistake by the Project Management Board of the old Krong Pac district. Next week, the leaders of Dak Lak Provincial People's Committee will conduct a field inspection of the project to provide timely instructions.

Component project 3, Khanh Hoa - Buon Ma Thuot expressway is 48.093km long. The project has a total investment of more than 6,100 billion VND.

BẢO LÂM
TIN LIÊN QUAN

transparent handling of Son Hai Group's failed high-speed bidding will create confidence for businesses

|

The Ministry of Finance has just reported the results of the inspection of the selection of contractors for the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway project.

Despite the danger, many drivers on the Van Ninh - Cam Lo expressway have not completed

|

Quang Tri - Van Ninh - Cam Lo Expressway has not been put into operation, many items are unfinished, but people are driving motorbikes and cars, posing a potential risk of accidents.

Building the North-South high-speed railway, Hanoi Chairman assigns tasks to the Secretaries of communes and wards

|

The Chairman of Hanoi believes that the Party Secretaries of the communes must be the head of the commune's steering committee for site clearance to implement the North-South high-speed railway project.

Young people with the dream of settling down in the cycle of house loan interest rates

|

With the end of fixed interest rate incentives, young people are worried about burdening with fluctuating debts, and owning their first home becomes even more difficult.

Cai Luong combines Chinese drama and Phuong My Chi's strategy in Sing! Asia

|

Phuong My Chi and Kha Lau brought a surprising performance when combining two art forms of Vietnam and China in Sing! Asia.

Gaza peace negotiations fall into a deadlock

|

The long-standing deadlock between demands for withdrawing troops from Gaza and returning hostages has left the negotiation process between Israel and Hamas in a deadlock.

Resolutely handle 11 illegal projects in Khanh Hoa in 2025

|

Khanh Hoa - According to the draft Resolution on double-digit economic growth targets, the Provincial Party Committee aims to complete the final handling of 11 illegal projects in 2025.

transparent handling of Son Hai Group's failed high-speed bidding will create confidence for businesses

Lê Thanh Phong |

The Ministry of Finance has just reported the results of the inspection of the selection of contractors for the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway project.

Despite the danger, many drivers on the Van Ninh - Cam Lo expressway have not completed

HƯNG THƠ |

Quang Tri - Van Ninh - Cam Lo Expressway has not been put into operation, many items are unfinished, but people are driving motorbikes and cars, posing a potential risk of accidents.

Building the North-South high-speed railway, Hanoi Chairman assigns tasks to the Secretaries of communes and wards

Anh Tuấn |

The Chairman of Hanoi believes that the Party Secretaries of the communes must be the head of the commune's steering committee for site clearance to implement the North-South high-speed railway project.