Hanoi Ring Road 2.5 enters the final stage, contractors mobilize maximum human resources for construction

SÓNG HỮU |

Hanoi - The contractor has completed the C15 asphalt paving item at the beginning of the route of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, with a total capital of more than 1,300 billion VND.

According to Lao Dong on the morning of November 23, the contractor has basically completed the asphalt paving of the road surface in the area at the beginning of the Ring Road 2.5 project, Dam Hong - National Highway 1A section.

Speaking to reporters, Mr. Tran Dinh Hoc - Director of the contractor for package No. 1 (Ring Road 2.5 Project, Dam Hong - National Highway 1A section) said that from the night and early morning of November 23, nearly 40 officers, engineers, and workers along with many equipment and machines were mobilized to asphalt the road surface in this area, in which the left section of the route is 240m long, the right section is 80m long.

a
Construction site of package 1, Ring Road 2.5 project, Dam Hong - National Highway 1A section (Hanoi), early morning of November 23. Photo: Song Huu
a
a
Machinery is mobilized to the construction site of the asphalt paving project. Photo: Song Huu

According to Mr. Hoc, construction work at night causes many obstacles for contractors, however, due to the nature of the work, the construction unit will gradually overcome the difficulties, ensure safe and quality construction and ensure the set progress.

In parallel with the asphalt paving item, the contractor also implemented the construction of sidewalk floors as well as trees in the median strip.

The contractor also committed to implementing all measures during the construction process to minimize dust and dirt that pollutes the environment and affects people's lives.

"A section of the route after being paved with asphalt will help reduce the dust and pollution in the area, while making people's travel more convenient" - Mr. Hoc said.

a
a
a
Many workers worked through the night at the project site. Photo: Song Huu
a
a
The road asphalt paving items are urgently and safely deployed by workers and engineers, ensuring the quality and progress set out. Photo: Song Huu

In addition to package 1, the L3 bridge construction package across the Lu River (package No. 2) is also being urgently implemented by the construction unit. The overall progress of the entire Ring Road 2.5 project, Dam Hong - National Highway 1A section, has reached more than 70%.

The project to build the Ring Road 2.5, Dam Hong - National Highway 1A section, is invested in the form of a BT (build - transfer) contract with a length of 1.3km, with a total investment of more than 1,300 billion VND.

The project started in 2014 and was expected to be completed in 2017 but was behind schedule.

In 2020, the project was temporarily suspended when it had only reached about 40% of the workload. The reason is that the contract implementation period has not been extended, and the adjusted feasibility study report has not been approved.

By May 2025, the project was restarted, planned to be completed in the first quarter of 2026. When put into use, the project will contribute to promoting socio-economic development, helping to reduce traffic congestion, and change the appearance of traffic in the southern area of the capital.

SÓNG HỮU
RELATED NEWS

Throughout the night of constructing a billion-dollar road in Hanoi, the finishing time is very close

|

Hanoi - The contractor mobilized many machines and workers overnight to construct the Ring Road 2.5 project, ensuring the quality and progress set out.

Image of 2 billion-dollar bridges across the river in Hanoi facing difficulties, having to delay progress

|

Hanoi - The road and railway bridges across the Duong River are under construction mainly in the middle of the river, while most of the land at both ends of the bridge has not been cleared.

Voters petition about the billion-dollar road project in Hanoi that has not been completed for more than 10 years

|

Hanoi - The Ring Road 2.5 project has been extended for more than 10 years but has not been completed, voters requested the city to give strong direction and speed up the progress.

Proposal to build Vietnam's first boat museum from the Hoi An ancient boat incident

|

Da Nang - The ancient ship "forgotten" under the sand of Hoi An sea revealed the secret to trading in the once bustling port.

Da Nang proposes to increase flood prevention capacity of upstream hydroelectric reservoirs

|

Da Nang reported a loss of VND1,300 billion due to floods at the end of October, and proposed adjusting the inter- Lake operation process on the Vu Gia - Thu Bon river.

The flood swept away mother and child, etc., leaving behind a painful farewell in a cramped scene

|

Dak Lak - Amidst the flood, people in Hoa Thinh commune (old Phu Yen province) had to say goodbye to their relatives in pain and hardship.

Multiple accidents on Ring Road 3 in Hanoi, many vehicles are severely deformed

|

Hanoi - A series of accidents occurred late on November 22 at the elevated Ring Road 3.

The White Stone suspension bridge was destroyed by floods, Khanh Hoa people traveled dozens of kilometers to make a living

|

Khanh Hoa - As of the evening of November 22, traffic in Nam Khanh Vinh and Bac Khanh Vinh communes was still cut off, communication and electricity had not been restored after the flash flood.

Throughout the night of constructing a billion-dollar road in Hanoi, the finishing time is very close

SÓNG HỮU |

Hanoi - The contractor mobilized many machines and workers overnight to construct the Ring Road 2.5 project, ensuring the quality and progress set out.

Image of 2 billion-dollar bridges across the river in Hanoi facing difficulties, having to delay progress

SÓNG HỮU |

Hanoi - The road and railway bridges across the Duong River are under construction mainly in the middle of the river, while most of the land at both ends of the bridge has not been cleared.

Voters petition about the billion-dollar road project in Hanoi that has not been completed for more than 10 years

SÓNG HỮU |

Hanoi - The Ring Road 2.5 project has been extended for more than 10 years but has not been completed, voters requested the city to give strong direction and speed up the progress.