The Ho Chi Minh City Ring Road 3 overpass has crossed Nguyen Thi Minh Khai Street

ĐÌNH TRỌNG |

HCMC - The overpass span (under construction package 3 of the former Ho Chi Minh City Ring Road 3 project through Binh Duong) has been spanning Nguyen Thi Minh Khai Street.

On September 29, contractors are urgently constructing and speeding up the construction progress of the construction package of 3 sections from Binh Chuan to Saigon River under the Ho Chi Minh City Ring Road 3 project.

Notably, in this section, the Ring Road 3 project will pass through 2 major routes, Nguyen Thi Minh Khai and National Highway 13 (nearly 1 km apart). These are 2 routes with a large volume of traffic. The investor has decided to build an overpass across the two routes above.

According to records, the section across National Highway 13 is currently being paid as a bridge abutment. Meanwhile, the section passing through Nguyen Thi Minh Khai Street, the pile system, pillars, and supporting funds have been completely built. The spans of the bridges have been crossed over Nguyen Thi Minh Khai Street.

Xe container chay tren duong Nguyen Thi Minh Khai duoi gam nhip cau vuot du an Vanh dai 3 TPHCM. Anh: Dinh Trong
Container trucks run on Nguyen Thi Minh Khai Street under the overpass of the Ho Chi Minh City Ring Road 3 project. Photo: Dinh Trong

The next section, Ho Chi Minh City Ring Road 3 running parallel to a real estate project is also designed to build an elevated overpass.

According to the Binh Duong Traffic Construction Investment Project Management Board, construction package 3 will start in February 2024. The bridge has completed 318/318 bored piles, the abutment rack has reached 38/40 platforms, the abutment rack has reached 37/40 pillars, the girder cast has reached 244/304 girders, and the girder installed has reached 196/304 girders. Meanwhile, the road construction volume has also reached about 48%.

Cau vuot la giai phap giup cac tuyen duong duoc thong suot. Anh: Dinh Trong
The overpass is a solution to help the roads become smooth. Photo: Dinh Trong

The total volume of construction package 3 reached VND798 billion/VND1,654.6 billion (completion rate of 48.23% compared to the contract volume).

According to records, the construction of construction package 3 is currently facing many difficulties due to weather. Heavy rain hinders the construction of workers. In addition, the heavy rain at the construction site also made it difficult to transport machinery and materials.

Contractors are overcoming difficulties and taking advantage of time for construction. In addition, increase materials and labor to speed up progress.

Cac nha thau dang day nhanh tien do goi xay lap so 3. Anh: Dinh Trong
Contractors are speeding up the progress of construction package No. 3. Photo: Dinh Trong
ĐÌNH TRỌNG
RELATED NEWS

The largest intersection in Ho Chi Minh City is about to open an overpass and underpass, reducing traffic congestion by 80%

|

HCMC The N2 bridge branch and the HC1-02 underpass at the An Phu intersection will be open to traffic before the Lunar New Year 2026, helping to reduce traffic congestion at the eastern gateway by 80%.

A survey will be conducted to compensate for damages to households affected by the construction of Ho Chi Minh City Ring Road 3

|

HCMC - Many households in Thuan An ward were affected during the construction of the Ho Chi Minh City Ring Road 3 project, the section passing through Binh Duong province before.

Deputy Prime Minister directs to remove 4 obstacles at the Ho Chi Minh City Ring Road 3 project

|

The Deputy Prime Minister requested the Ho Chi Minh City People's Committee and relevant localities to focus on removing difficulties and obstacles in the Ring Road 3 project.

Hue hotels and villas open to welcome people to avoid storms and floods

|

Hue - Many luxury hotels and apartments welcome people for free accommodation during the time the Central region was heavily affected by storm No. 10 Bualoi.

Hanoi contracts to spend the highest amount of VND94 million/year for each payroll

|

Hanoi - The highest standard of regular spending contracts for cadres, civil servants; non-professional workers in communes and wards is 94 million VND/year.

"Heavy waves hit, ship sank at night"

|

The fierce waves hit, 2 ships sank at night, 9 crew members were missing, Quang Tri authorities tried to search in harsh conditions.

Storm and tornado in Ninh Binh killed 6 people, injured 7

|

Ninh Binh - On the morning of September 29, due to the impact of storm No. 10, a tornado and heavy rain occurred in Ninh Binh province, killing 6 people and injuring 7 others.

Mr. Trinh Viet Hung was appointed to hold the position of Secretary of Lao Cai Provincial Party Committee

|

The 1st Lao Cai Provincial Party Congress, term 2025-2030, announced the Politburo's decisions on key personnel.

The largest intersection in Ho Chi Minh City is about to open an overpass and underpass, reducing traffic congestion by 80%

MINH QUÂN |

HCMC The N2 bridge branch and the HC1-02 underpass at the An Phu intersection will be open to traffic before the Lunar New Year 2026, helping to reduce traffic congestion at the eastern gateway by 80%.

A survey will be conducted to compensate for damages to households affected by the construction of Ho Chi Minh City Ring Road 3

ĐÌNH TRỌNG |

HCMC - Many households in Thuan An ward were affected during the construction of the Ho Chi Minh City Ring Road 3 project, the section passing through Binh Duong province before.

Deputy Prime Minister directs to remove 4 obstacles at the Ho Chi Minh City Ring Road 3 project

PHẠM ĐÔNG |

The Deputy Prime Minister requested the Ho Chi Minh City People's Committee and relevant localities to focus on removing difficulties and obstacles in the Ring Road 3 project.