An Phu intersection, the largest in Ho Chi Minh City, continues to postpone progress to April 2027

MINH QUÂN |

Ho Chi Minh City - The An Phu intersection project worth more than 3,400 billion VND has reached 78% of the construction volume but continues to postpone the completion progress to April 30, 2027.

On June 18, the Ho Chi Minh City Traffic Construction Investment Project Management Board (Ho Chi Minh City Transport Board) said that the total construction volume of the An Phu intersection project currently reaches about 78%.

According to the new plan, the items of the project will be successively completed and put into operation in the near future.

Bridge branch N4 - serving traffic direction from Giong Ong To bridge turning right into Mai Chi Tho avenue, is expected to be completed and opened to traffic at the end of July 2026.

Thi công nhánh cầu vượt N4 thuộc dự án nút giao An Phú.  Ảnh: Anh Tú
Construction of the N4 overpass branch under the An Phu intersection project. Photo: Anh Tu

Two bridge branches N1.1 and N1.3 - allowing vehicles from Mai Chi Tho Avenue to turn left to the Ho Chi Minh City - Long Thanh - Dau Giay expressway access road, will be opened to traffic at the end of September 2026.

For the N1.2 bridge branch - heading from Luong Dinh Cua street straight to the Ho Chi Minh City - Long Thanh - Dau Giay expressway access road, along with the Luong Dinh Cua road expansion item from Mai Chi Tho to Nguyen Hoang, it is expected to be completed by the end of April 2027.

However, this progress depends on completing the site clearance of about 22,012m2 belonging to An Phu Development Urban Area before the end of October 2026.

In addition, the central tower and green landscape system of the project are expected to be completed by the end of December 2026.

According to the Ho Chi Minh City Transport Board, if site clearance is carried out according to plan, the entire An Phu intersection project will be completed on April 30, 2027.

Thus, this is the next time the An Phu intersection project has had to postpone its progress. At the beginning of 2026, the Ho Chi Minh City People's Committee approved the adjustment of the project implementation time from the 2021-2025 period to the 2021-Q2/2026 period.

Toàn cảnh nút giao An Phú.  Ảnh: Anh Tú
Overview of An Phu intersection. Photo: Anh Tu

The An Phu intersection project was started at the end of 2022, with a total investment of more than 3,400 billion VND. The project is built according to a three-story intersection model, including a system of underpasses, overpasses and central roundabouts to solve traffic congestion at the eastern gateway of Ho Chi Minh City.

In the past time, a number of important items have been put into operation, contributing to improving traffic capacity in the area.

Including underpass HC1-01 at the Mai Chi Tho - Dong Van Cong intersection; branch of bridge N2 connecting from the Ho Chi Minh City - Long Thanh - Dau Giay expressway to Mai Chi Tho avenue; underpass HC1-02 connecting the expressway with Mai Chi Tho avenue; overpass branch N3 from Mai Chi Tho avenue turning left into Dong Van Cong street.

MINH QUÂN
RELATED NEWS

Ho Chi Minh City recovers 2.2ha of land to remove obstacles at An Phu intersection, Luong Dinh Cua street

|

Ho Chi Minh City will recover more than 2.2ha of land on Luong Dinh Cua street before November 30, 2016, helping to remove site obstacles to accelerate the construction of An Phu intersection and Luong Dinh Cua street.

Another overpass branch at the largest intersection in Ho Chi Minh City is about to reach the finish line

|

Ho Chi Minh City is working hard to complete the N4 overpass branch belonging to An Phu intersection in order to promptly open to traffic by the end of June.

Ho Chi Minh City's largest intersection project is quiet after Tet, people worry about further delays

|

Ho Chi Minh City - An Phu intersection project at the eastern gateway of Ho Chi Minh City - the largest intersection project in the city has not yet resumed construction, even though the Tet holiday has ended.

Reasons why the Ministry of Home Affairs proposed that the Prime Minister decide on the entire holiday schedule

|

According to the Ministry of Home Affairs, the Prime Minister's proposal to decide on the entire holiday schedule will help proactively arrange holidays and notify people and businesses early.

Israel negotiates with the US on the continued deployment of troops in Lebanon

|

Exchanges between the US and Israel took place after the US and Iran signed a temporary agreement related to Lebanon's sovereignty.

Tricks to take advantage of business models such as vacation ownership for profit

|

The spokesperson of the Ministry of Public Security mentioned tricks to take advantage of business models to appropriate and profit from such models as resort real estate, vacation ownership...

Supervisory program of the National Assembly Standing Committee in 2027

|

National Assembly Chairman Tran Thanh Man has signed and promulgated Resolution No. 287/NQ-UBTVQH16 on the Supervision Program of the National Assembly Standing Committee in 2027.

Ho Chi Minh City recovers 2.2ha of land to remove obstacles at An Phu intersection, Luong Dinh Cua street

MINH QUÂN |

Ho Chi Minh City will recover more than 2.2ha of land on Luong Dinh Cua street before November 30, 2016, helping to remove site obstacles to accelerate the construction of An Phu intersection and Luong Dinh Cua street.

Another overpass branch at the largest intersection in Ho Chi Minh City is about to reach the finish line

Minh Tâm - Anh Tú |

Ho Chi Minh City is working hard to complete the N4 overpass branch belonging to An Phu intersection in order to promptly open to traffic by the end of June.

Ho Chi Minh City's largest intersection project is quiet after Tet, people worry about further delays

MINH QUÂN |

Ho Chi Minh City - An Phu intersection project at the eastern gateway of Ho Chi Minh City - the largest intersection project in the city has not yet resumed construction, even though the Tet holiday has ended.