The heavy damage of the people
Hurricane Yagi swept over, 4 works including the 1st of the village of Dai, Ha Thanh, Ha Trang Dong and Ha Trang Tay were seriously damaged, causing flooding for about 400 households, swept away many assets and devastating fields.
Mr. Nguyen Quang Vu's family (64 years old), Na Lo village, Dong Hai commune is one of the most severe damaged households after Storm Yagi.
Mr. Hop's house was about 30m from the left shoulder of Ha Thanh. Due to the influence of the storm, when the left shoulder was broken, the flooded water followed the trees and gravel, pouring the walls, causing flooding 1m high, leading to tables and chairs, many assets towards downstream. A grapefruit garden has given a 2 -year fruit with no traces, 500 chickens have only 70, more than 100 coffee (like a hybrid between ducks and goose) leaving only 4.
Mr. Hop said: "Through the new flood, the neighborhood of the village is valuable. Restore production, crank the grazing garden back.
Ha Thanh Dam is responsible for supplying irrigation water to nearly 180 hectares of agricultural land in Dong Hai commune. Currently the work is being repaired in the direction of restoring the land broken on the left bank, reinforcing the top of the dam, the upper roof, lowering the reinforced concrete.
Mr. Van Thong - Head of Na Cha village - expressed: "Currently the project is under construction is incomplete, to ensure the safety of households after the work incident, I have contacted you at the beginning. Source such as Dai Duc (Tien Yen district), Quang An (Dam Ha district), heavy rain, report to the people in the village to proactively prevent floods ".
Urgently overcome irrigation works
Earlier, due to the heavy damage of typhoon Yagi, on September 26, 2024, the People's Committee of Quang Ninh province decided to announce an emergency situation of natural disasters to respond and overcome damage to 4 irrigation works on public interface. Eastern Irrigation One Member Limited Liability and the authorities assess the status, deploy remedies.
Son Ha Joint Stock Company is appointed to be a construction contractor with a total value of more than 12 billion dong. In the process of repairing, until 11.1.2025, the new company has embankment to implement the project.
Mr. Ha Van Phan, commander of the project, Son Ha Joint Stock Company - said: According to the progress of the commitment, 4 works will be completed to the locality on April 30, 2025. The company has mobilized 2 excavators, 4 cars and 30 workers working day and night at the project. The time to wait for the embankment soil also makes the work progress extended compared to expected.
Up to the present time, Ha Thanh Dam has finished the embankment, is pouring concrete; damn the 1st of the radio village still has a stone work; Ha Trang Dong and Ha Trang Tay dams have also basically completed. With this schedule, we will hand over 1 month earlier, around early March 3.2025.
The quick remedy of irrigation works not only helps to ensure safety for people, but also contributes to stabilizing agricultural production after the storm.