Repairing a 5,000 billion VND road that has just been inaugurated for 1 year has been damaged

ĐÌNH TRỌNG |

HCMC - Units are deploying patchwork and repairing damaged points on the Bac Tan Uyen - Phu Giao - Bau Bang force road.

On October 3, speaking with reporters, the leader of the People's Committee of Phuoc Thanh commune, Ho Chi Minh City said that the commune had inspected and recorded damaged points on the Bac Tan Uyen - Phu Giao - Bau Bang force road.

According to the survey results, Phuoc Thanh commune recorded that the Bac Tan Uyen - Phu Giao - Bau Bang power generation road was damaged and degraded on both sides of the road. The degraded section occurred in the bridge area across the Be River.

To ensure traffic safety and avoid unfortunate accidents, the People's Committee of Phuoc Thanh commune has sent a document to the Phu Giao Construction Investment Project Management Board to repair this damaged section.

Viec sua chua doan hu hong, o ga dang bat dau duoc thuc hien. Anh: Co quan chuc nang cung cap
The repair of the damaged section is starting to take place. Photo: Provided by the authorities

According to the People's Committee of Phuoc Thanh commune, this route is still under warranty maintenance, so when discovered, the locality has petitioned the route management unit for coordination in handling.

Currently, relevant units are deploying vehicles and human resources to patch and repair the damaged section.

Previously, Lao Dong Newspaper reported that the Bac Tan Uyen - Phu Giao - Bau Bang power generation road, after a year of use, showed signs of deterioration.

Nhung ho sau xuat hien tren mat duong. Anh: Dinh Trong
Deep holes appear on the road surface. Photo: Dinh Trong

It is noted that from the intersection of DT.741 road to Bau Bang (in Phuoc Thanh commune, Ho Chi Minh City) there are many small holes, even holes about 15 cm deep. Scattered along this route are also rocks and gravel that have peeled off, creating deep holes on the road surface.

It is known that the route was started in 2021, inaugurated and put into use at the end of September 2024. The project is about 48 km long, 6 lanes wide, and has a design speed of 80 km/h. The project has a total investment of more than 5,000 billion VND.

Hien tuyen duong dang duoc sua chua dam bao an toan cho nguoi dan. Anh: Dinh Trong
The road is currently being repaired to ensure the safety of the people. Photo: Dinh Trong
ĐÌNH TRỌNG
RELATED NEWS

A road worth over VND5,000 billion in Ho Chi Minh City that has just been inaugurated for a year has seen many potholes

|

HCMC - The Bac Tan Uyen - Phu Giao - Bau Bang dynamic road has just been put into use for a year and has shown signs of deterioration, with many potholes.

Ha Tinh has more than 84,000 houses damaged by storm No. 10

|

According to the latest statistics, the impact of storm No. 10 caused 1 death, 15 injuries, and more than 84,000 damaged houses in Ha Tinh.

Close-up of a series of potholes on the repaired and damaged road in the East of Ho Chi Minh City

|

HCMC - People in Long Binh Ward, HCMC have continuously reported the deterioration of Nguyen Xien Street, causing difficulties in traffic.

Flooding after heavy rain, warning of skin diseases and things people need to pay attention to

|

The prolonged heavy rain causing flooding in many localities not only seriously affects daily life but also increases the risk of skin disease outbreaks.

Order to open 2 consecutive bottom spillways of Hoa Binh Hydropower Reservoir today

|

2 bottom spillways of Hoa Binh Hydropower Reservoir were ordered to open.

Lao Cai tourism stagnates, many roads collapse

|

Lao Cai - National Highway 32 - the section passing through Khau Pha Pass - suffered a serious landslide, cutting off traffic from Nghia Lo to Mu Cang Chai. Tourism activities are affected.

Develop a unified salary and allowance project to submit to the Politburo

|

In the fourth quarter of 2025, the Ministry of Home Affairs will advise on the development of a salary and allowance project for cadres, civil servants, public employees, and armed forces.

Results of the meeting on compensation for the case of throwing sandals into a water valve that damaged an elevator in Hanoi

|

Hanoi - The families of the 3 boys involved in the case of throwing sandals into the water valve that damaged the 2 elevators of the Kim Van - Kim Lu apartment building have all committed to compensate for the cost of repairing the elevator.

A road worth over VND5,000 billion in Ho Chi Minh City that has just been inaugurated for a year has seen many potholes

ĐÌNH TRỌNG |

HCMC - The Bac Tan Uyen - Phu Giao - Bau Bang dynamic road has just been put into use for a year and has shown signs of deterioration, with many potholes.

Ha Tinh has more than 84,000 houses damaged by storm No. 10

TRẦN TUẤN |

According to the latest statistics, the impact of storm No. 10 caused 1 death, 15 injuries, and more than 84,000 damaged houses in Ha Tinh.

Close-up of a series of potholes on the repaired and damaged road in the East of Ho Chi Minh City

NHÓM PV |

HCMC - People in Long Binh Ward, HCMC have continuously reported the deterioration of Nguyen Xien Street, causing difficulties in traffic.