Focus on removing the bottleneck of the 9,590 billion VND project in Hanoi

SÓNG HỮU |

Hanoi - Xuan Mai commune is focusing on propaganda and mobilizing the remaining households to agree to hand over the site for the National Highway 6 expansion project, Ba La - Xuan Mai section.

Started in December 2022, the project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section has a total investment of about 9,590 billion VND.

The project has a length of 21.7km, a cross-section scale of 50-60m. This is a key traffic project of the city, of particular importance in completing the radial traffic axis in the Southwest of the Capital.

The project has a total area to be recovered of about 105.13 ha in wards and communes, including: Kien Hung, Duong Noi, Phu Luong, Yen Nghia, Chuong My, Phu Nghia and Xuan Mai.

To date, most localities have completed site clearance and handed over to investors to implement projects; the remaining communes and wards that have not completed are also urgently speeding up progress.

At the dialogue conference with cases that have not agreed to hand over land in Xuan Mai commune on the evening of July 15, Mr. Trinh Ba Thuong, Vice Chairman of Xuan Mai Commune People's Committee emphasized that the project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section is a key traffic project of Hanoi, which is of great significance in completing traffic infrastructure, reducing congestion, promoting socio-economic development of the area and improving people's lives.

Over the past time, with the drastic involvement of the entire political system, the close coordination of specialized agencies and the consensus and responsibility of the majority of people, land clearance work in the commune has achieved many positive results.

Most households and individuals agreed with the Party and State's policies, agreed with the compensation, support and resettlement plan; many households have proactively handed over the land even when they have not received the official compensation plan, showing a spirit of responsibility for the common interests of the community.

However, to date, there are still some households and individuals who have not agreed with the land acquisition decision and the compensation, support, and resettlement plan.

Người dân nêu ý kiến tại buổi đối thoại giữa xã Xuân Mai với các trường hợp chưa đồng thuận bàn giao mặt bằng, tối 15.7. Ảnh: Trang tin điện tử xã Xuân Mai
People express their opinions at the dialogue between Xuan Mai commune and cases that have not agreed to hand over land, evening of July 15. Photo: Xuan Mai commune electronic information page

Vice Chairman of Xuan Mai Commune People's Committee affirmed that the commune government always determines that ensuring the legitimate and lawful rights and interests of the people is a consistent principle in the process of implementing compensation, support and resettlement.

All policies are implemented in accordance with the law, publicly, transparently, ensuring fairness, objectivity, and not affecting the rights of households whose land is recovered.

Currently, some households are still concerned about regimes and policies for compensation, support, resettlement, recovered area and some other contents in the project implementation process.

Regarding this issue, representatives of the Hanoi Traffic Construction Investment Project Management Board and leaders of the Commune People's Committee directly exchanged, explained and clarified each content under their authority based on current legal regulations, helping people better understand the legal basis, compensation, support and resettlement policies when the State recovers land.

Local leaders hope to receive coordination between people in site clearance so that the project can be implemented soon and completed according to plan.

Inspecting the site at the project to renovate and upgrade National Highway 6, Ba La - Xuan Mai section on June 28, Politburo member, Secretary of the Hanoi Party Committee Tran Duc Thang requested that the demolition of the works must be completed in July 2026 to hand over the clean site to the construction contractor.

Contractors when handed over a clean site need to mobilize sufficient manpower and vehicles to accelerate progress to resolutely implement technical traffic opening before the Lunar New Year Dinh Mui 2027 and complete the entire project in the first quarter of 2027.

SÓNG HỮU
RELATED NEWS

Enforcement of 17 land-violating projects, construction on agricultural land in Hanoi

|

Hanoi - Hoai Duc Commune People's Committee has just carried out coercion against 17 land-violating projects in the area.

Revealing the shape of a road project over 90m wide in the center of Hanoi

|

Hanoi - After a long period of construction, the Dang Thai Mai road phase I project (Tay Ho ward) 1,260m long, with a total capital of more than 550 billion VND, has revealed its true form.

Hanoi is ready to operate 40 flood prevention items before the rainy season

|

Hanoi has basically completed 40 drainage items and 5 flood control pumping stations, gradually improving urban drainage capacity before the 2026 rainy season.

Disciplining former Chief of Office of Thua Thien Hue Provincial Party Committee related to the Provincial Party Committee Guesthouse Project

|

The Standing Committee of Hue City Party Committee disciplined Mr. Luu Duc Hoan with a reprimand for violations in leading and directing the implementation of the Provincial Party Committee Guest House Project.

Police inform about the case of a car driver not giving way to an ambulance in Tuyen Quang

|

Tuyen Quang - Functional agencies determined that the car driver had the act of not giving way to priority vehicles, with a fine of 6 - 8 million VND and 4 points off the driver's license.

Prolonging the term of Deputy Inspector General of the Government with Mr. Le Sy Bay

|

The Prime Minister decided to extend the term of office of Deputy Inspector General of the Government to the time of retirement according to regulations for Mr. Le Sy Bay.

Many people came to Le Thi Rieng Park to burn incense to commemorate heroic martyrs

|

Before the information that martyrs' remains are being gathered at Le Thi Rieng Park, Ho Chi Minh City, many people came to offer incense and express their respect to the spirits of the martyrs.