Construction of 3 shifts with 4 crews to accelerate the progress of upgrading and repairing Ke Go lake

TRẦN TUẤN |

Ha Tinh - To speed up progress, contractors are deploying 3 shifts of 4 crews on the construction site to upgrade and repair Ke Go lake.

On December 28, Lao Dong Newspaper reporters were present at the construction site for upgrading and repairing Ke Go lake in Cam Due commune, recording that contractors are mobilizing maximum manpower and machinery to focus on constructing new spillway construction items.

Mr. Nguyen Minh Hieu - official of Irrigation Investment and Construction Management Board 4 - said that at this time, contractors are focusing on speeding up progress, constructing 3 shifts and 4 crews day and night.

Moi ngay tren cong truong co hon 100 cong nhan. Anh: Tran Tuan.
There are more than 100 workers on the construction site every day. Photo: Tran Tuan.
Cong nhan thi cong hang muc tran xa lu. Anh: Tran Tuan.
Workers constructing the flood spillway item. Photo: Tran Tuan.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Currently, more than 100 workers are focusing on constructing the iron part to pour concrete from the flood discharge spillway every day.

Up to this point, the excavation of the spillway foundation has reached more than 90%; more than 2,000 m3 of spillway concrete has been poured; the bridge across the spillway has basically been completed, only railings are installed and soil is poured at 2 bridge abutments.

The weather is favorable, so contractors are highly focused on construction. Currently, the construction site is very bustling. It is believed that from now on, when the weather is favorable, the project progress will be ensured," Mr. Hieu shared.

The project to upgrade and repair Ke Go lake with a total investment of more than 350 billion VND is constructed by the joint venture of Joint Stock Company 47 - Lilama 10 Joint Stock Company - Construction Joint Stock Company 465.

The main items of the project include: repairing and upgrading the main dam; building a new flood discharge spillway; building a new operating house; upgrading the mechanical system at Doc Mieu spillway and surrounding dyke.

The project to upgrade and repair Ke Go Lake was started on December 27, 2024, and is expected to be completed in June 2026.

Cau bac qua tran da co ban xong. Anh: Tran Tuan.
The bridge across the spillway is basically completed. Photo: Tran Tuan.
Mat cau dang cho lap lan can. Anh: Tran Tuan.
The bridge surface is waiting to be installed with railings. Photo: Tran Tuan.

According to Mr. Nguyen Minh Hieu, basically, construction is currently smooth on the construction site. Currently, only 2 power poles are stuck. A few days ago, the investor also worked with the People's Committee of Cam Due commune to request early release.

Cam Due commune authorities said that they will focus on consolidating site clearance officers to soon carry out the task of relocating the 2 remaining power poles.

Regarding the recent incident of a contractor carrying soil from the construction site to dump at the landfill to spread dust and affect the environment, Mr. Nguyen Minh Hieu said that for nearly a week now, he has no longer been carrying soil to dump at the landfill but is focusing on completing the temporary road, in order to carry soil to build at the foot of the main dam.

Currently, the volume of soil to be dumped into the waste disposal site is not much, so the contractor is focusing on transporting and filling at the foot of the main dam.

Ke Go Lake was built in 1976, with a capacity of 345 million m3, is the most important irrigation project of Ha Tinh. Ke Go Lake not only serves irrigation for tens of thousands of hectares of agricultural land but also has the task of cutting and reducing floods for downstream areas, providing domestic water and maintaining the ecological environment.

It's a bit of a bit of a bit of a bit of a bit of a bit.

TRẦN TUẤN
RELATED NEWS

Land clearance progress of 2 key industrial park projects in Hai Phong

|

Hai Phong - On December 27, Vice Chairman of the City People's Committee Le Trung Kien inspected the progress of site clearance for Trang Due 3 and An Duong Industrial Park projects.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Progress of the urban area project worth nearly VND11,000 billion in Cat Ba, Hai Phong

|

Hai Phong - The Cai Gia and Cat Ba urban tourism project is gradually completing many technical infrastructure items and works on the land, striving to inaugurate in 2029.

Progress of Gia Binh airport project with an investment capital of VND196,378 billion in Bac Ninh

|

Bac Ninh - The Gia Binh International Airport project (abbreviated as Gia Binh International Airport) is being accelerated.

Russia warns Europe of strong retaliation if attacked

|

The Russian Foreign Minister said that the EU is not ready to negotiate the Ukraine conflict, continue to support Kiev and publicly prepare for a scenario of confrontation with Moscow.

U23 Vietnam trains for the first time in Qatar

|

U23 Vietnam trains for the first time in Qatar in the training camp towards the 2026 AFC U23 Championship finals.

Illegal sand gathering yard in Hue City to be handled after reflection from Lao Dong Newspaper

|

Hue - Businesses temporarily suspend the operation of illegal sand gathering yards in Hue City when there is a reflection from Lao Dong Newspaper.

Ho Van Cuong answers questions about himself after a 10-year journey

|

As an artist in Nhu Quynh's "Huong sac giai nhan" music festival, Ho Van Cuong shared his nearly 10-year journey since being crowned "Children's Music Idol 2016".

Hanoi requires leaders to declare all red books, money, precious metals, and foreign assets

|

Hanoi has just issued an official dispatch requesting declaration and control of assets and income for people with positions and powers in organizations and units in 2025.

Land clearance progress of 2 key industrial park projects in Hai Phong

Hoàng Khôi |

Hai Phong - On December 27, Vice Chairman of the City People's Committee Le Trung Kien inspected the progress of site clearance for Trang Due 3 and An Duong Industrial Park projects.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Progress of the urban area project worth nearly VND11,000 billion in Cat Ba, Hai Phong

Băng Tâm |

Hai Phong - The Cai Gia and Cat Ba urban tourism project is gradually completing many technical infrastructure items and works on the land, striving to inaugurate in 2029.

Progress of Gia Binh airport project with an investment capital of VND196,378 billion in Bac Ninh

Vân Trường |

Bac Ninh - The Gia Binh International Airport project (abbreviated as Gia Binh International Airport) is being accelerated.