Construction through Tet on key projects in Tuyen Quang

Nguyễn Tùng |

Many key projects in Tuyen Quang province aim to be completed in 2025, and organizing construction during Tet will ensure the set progress.

The construction site of Ham Yen Bridge over Lo River and Km48 viaduct of Tuyen Quang - Ha Giang Expressway project is still bustling with the sound of machinery in the early spring of 2025. This is one of the important river crossing bridge items of the project.

Currently, the contractor has arranged 6 drilling lines, 3 service cranes, 6 excavators and service cars. Each shift, the unit arranges one-third of the staff to work, ensuring continuous construction.

Mr. Nguyen Duc Thanh - Deputy Director of the Management Board of Package 24 (Deo Ca Group Joint Stock Company) said that to ensure the progress of the project, the construction was organized throughout Tet.

Cong trinh cau vuot song Lo tren tuyen cao toc Tuyen Quang - Ha Giang.
Lo River overpass project on Tuyen Quang - Ha Giang highway.

"Understanding the psychology of workers and laborers, we ensure the best treatment for those who stay to work during Tet.

In addition to receiving 300% salary, the company also prepares enough food, including peach blossoms, organizes Chung cake wrapping, creating a joyful atmosphere for staff and workers to feel like they are celebrating Tet in their hometown," Mr. Thanh informed.

Trong nhung ngay Tet cong tac thi cong cac mong tru cau van duoc tien hanh.
During Tet holiday, construction of bridge foundations is still in progress.

With the Tuyen Quang General Hospital project, the construction site has not stopped during Tet holidays. Although the number of workers and machines is not 100% as usual, there are still workers working on the items.

At the construction package of the hospital's technical building, the welding machine's light still shines on the scaffolding. The working atmosphere is urgent, ensuring progress, striving to complete the project by the end of 2025.

Cong tac dam bao an toan thi cong duoc chu trong.
Construction safety is emphasized.

Mr. Tran Van The (from Nam Dinh), a construction worker at the project, said that this year he was encouraged to stay and work through Tet. He knew that not being able to go home to celebrate Tet with his family would be a bit sad, but there were still many other workers at the construction site, and the working atmosphere was still very urgent.

"We can't go home for Tet this year, but the company will provide us with all the necessities, just like at home. We plan to gather together on New Year's Eve at the construction site, hoping for a new year with many good results," said Mr. The.

Cong truong du an Benh vien da khoa Tuyen Quang van khong ngung tieng may, viec thi cong xuyen Tet trong khong khi khan truong.
The construction site of Tuyen Quang General Hospital project is still humming non-stop, construction work is taking place during Tet in an urgent atmosphere.

Tuyen Quang Provincial General Hospital with a total investment of nearly 1,800 billion VND and Tuyen Quang - Ha Giang Expressway (section through Tuyen Quang) with an investment of 6,800 billion VND are 2 of many key projects aiming to be completed in 2025. Organizing construction during Tet will help ensure the completion progress of the projects.

Speaking to reporters, Mr. Nguyen Thien Tuyen - Director of the Project Management Board for Investment and Construction of Traffic Works in Tuyen Quang province said that to ensure the progress of implementation according to plan, in the last months of 2024, the unit has basically handed over 100% of the site to the construction unit.

"The investor has asked contractors to focus resources to carry out construction in 3 shifts and 4 teams to make up for the slow progress due to site clearance problems and unfavorable weather conditions. During the 2025 Lunar New Year, over 40 site construction sites and 20 bridge construction sites will be constructed along the entire route," said Mr. Tuyen.

Nguyễn Tùng
TIN LIÊN QUAN

Ready to stay on site, work through Lunar New Year

|

On the first day of the new year 2025, the construction site of the Ring Road 4 project was almost always quiet. Many officers, engineers, and workers stuck to the construction site, working in "3 shifts, 4 shifts" to strive to complete the Ring Road 4 project in the Capital region by the end of 2025.

Workers work through Tet on Rach Mieu 2 Bridge project

|

Ben Tre - On the morning of January 1, at the Rach Mieu 2 bridge project, many workers and engineers were working on items such as leveling the ground, bundling cable-stayed cables, etc.

Ready to construct roads through 7 districts in Hanoi during Tet

|

Hanoi - If there is a construction plan during the Lunar New Year, the contractor will mobilize enough machinery and personnel to stay at the construction site, speeding up the progress of the parallel road of Ring Road 4.

Singer Duy Manh demands Mercedes-Benz Company to compensate more than 2.5 billion VND

|

According to the lawsuit on singer Duy Manh's side, the male singer requested Mercedes-Benz Vietnam Co., Ltd. to compensate a total of more than 2.5 billion VND after the car fire.

Ho Chi Minh City admits shortcomings in public investment disbursement

|

Recognizing the shortcomings in the disbursement of public investment capital, Vice Chairman of Ho Chi Minh City People's Committee Bui Xuan Cuong said that he had identified the backlog and would review and overcome it.

A huge Nord Stream pipeline warehouse fever, worth millions of euros in Germany

|

About 1,000 sections of the Nord Stream pipeline have been stored in Germany for many years.

US declares Russia agrees to agree to end the conflict in Ukraine

|

US President Donald Trump said Russia had agreed to an agreement to end the conflict in Ukraine.

The Ministry of Public Security proposes to sentence people selling fake food to up to 10 years in prison

|

The Ministry of Public Security said it will propose to increase the severity of penalties for crimes in the food sector when amending and supplementing the Penal Code.

Ready to stay on site, work through Lunar New Year

HỮU CHÁNH - KHÁNH AN |

On the first day of the new year 2025, the construction site of the Ring Road 4 project was almost always quiet. Many officers, engineers, and workers stuck to the construction site, working in "3 shifts, 4 shifts" to strive to complete the Ring Road 4 project in the Capital region by the end of 2025.

Workers work through Tet on Rach Mieu 2 Bridge project

Thành Nhân |

Ben Tre - On the morning of January 1, at the Rach Mieu 2 bridge project, many workers and engineers were working on items such as leveling the ground, bundling cable-stayed cables, etc.

Ready to construct roads through 7 districts in Hanoi during Tet

HỮU CHÁNH |

Hanoi - If there is a construction plan during the Lunar New Year, the contractor will mobilize enough machinery and personnel to stay at the construction site, speeding up the progress of the parallel road of Ring Road 4.