Progress of the nearly VND4,000 billion reservoir project in Phu Tho

Minh Nguyễn- Thu Hằng |

Phu Tho - On July 9, Deputy Minister of Agriculture and Environment Nguyen Hoang Hiep inspected the progress of the Canh Tang Reservoir Project.

Accompanying him were Vice Chairman of Phu Tho Provincial People's Committee Dinh Cong Su and leaders of a number of related departments, branches and sectors.

The Canh Tang Reservoir Project was built in Lac Son and Yen Thuy districts (old Hoa Binh province), with a total investment of over VND3,900 billion. The project includes a main dam over 53m high, 850m long, an auxiliary dam and a water supply pipeline system nearly 30km long.

When completed, the reservoir will have a capacity of nearly 91 million m3, contributing to ensuring irrigation water for thousands of hectares of agricultural land, while creating conditions for aquaculture development and eco-tourism.

Thu truong Bo Nong nghiep va Moi truong Nguyen Hoang Hiep, dong chi Dinh Cong Su, Pho Chu tich UBND tinh Phu Tho chu tri buoi lam viec.
Deputy Minister of Agriculture and Environment Nguyen Hoang Hiep, comrade Dinh Cong Su, Vice Chairman of Phu Tho Provincial People's Committee chaired the meeting.

Up to now, the Canh Tang Lake project has been completed and put into use 8 resettlement points and 2 flood avoidance routes. However, site clearance (GPMB) progress is still the biggest bottleneck. The newly completed pipeline item has been handed over more than 5.6/29km (equivalent to 19.38%). The unit item cannot reclaim residential land and garden land due to no decision on resettlement land allocation.

According to the representative of the Irrigation Investment and Construction Management Board 1, the inventory has been completed, but the main problem lies in the stage of verifying the origin of the land. Many households have transferred but have not completed their documents; many plots of land do not have red books; The People's Committee of Lac Son district (old) - the investor of the GPMB component has expired, the seal is no longer legally valid, making it difficult to transfer procedures to the new unit.

Relevant communes also reported further on the overlapping situation, lack of legal documents and the number of households affected. The leaders of the communes pledged to closely coordinate, mobilize people to agree, and create conditions for early handover of construction sites.

Deputy Minister of Agriculture and Environment Nguyen Hoang Hiep requested units to focus highly on site clearance, especially speeding up the verification of land origin in canals that have completed the counting. The appraisal and approval of the compensation plan will be carried out in stages, ensuring timely payment conditions and compliance with regulations.

The Deputy Minister also emphasized that the project needs to be completed on schedule to serve the inauguration goal on the occasion of August 19, 2025 - the 80th anniversary of the August Revolution. He suggested that the People's Committee of Phu Tho province study and supplement the area for anchoring boats in the lake and taking advantage of the water surface to develop an eco-tourism model, linking environmental protection with regional economic development.

Mot goc Du an ho chua nuoc Canh Tang, muc dau tu tren 3.900 ti dong.
A corner of the Canh Tang Reservoir Project, with an investment of over VND3,900 billion.

Concluding the meeting, Vice Chairman of Phu Tho Provincial People's Committee Dinh Cong Su assigned the Department of Agriculture and Environment to preside over, guide and coordinate to speed up the progress of land acquisition and resettlement procedures. Assign the Provincial Irrigation Works Exploitation Company to receive and operate the unit, ensuring the safety of the project, especially during the rainy and flood season.

Yen Phu Commune People's Committee was assigned to preside over the handover of the site clearance documents on the same day, coordinating with the Project Management Board of Region 3 to continue implementing the next steps. The Chairman of the People's Committees of Yen Phu, Lac Son, Dai Dong communes is responsible for directing and coordinating with units to promote progress.

Minh Nguyễn- Thu Hằng
TIN LIÊN QUAN

Reservoirs in Dien Bien are still thirsty in the rainy season

|

Dien Bien - Although it is the peak of the rainy season, the total capacity of the 13 reservoirs is still thirsty when it has only reached more than 50% of the design.

Digging into a reservoir in Lam Dong, discovering something that looks like a giant bomb

|

Lam Dong - While digging a reservoir, a household in Residential Group 7 (Phuoc Cat town, Da Huoai district, Lam Dong) discovered an object resembling a giant bomb.

On the large reservoir construction site worth over VND500 billion in the far West of the country

|

Dien Bien - After more than a year of construction, the reservoir project worth more than 500 billion VND in Muong Nhe district - the far western part of the country has completed about 30% of the volume.

Looking for contractors for construction package worth nearly 850 billion VND of Canh Tang Lake Project

|

Hoa Binh - The investor is issuing bidding documents for Package No. 46 Construction and equipment of Canh Tang Lake Project.

Minister of National Defense chaired the Conference on handover of the position of Commander of Military Region 7

|

HCMC - On July 9, General Phan Van Giang, Politburo member, Deputy Secretary of the Central Military Commission, Minister of National Defense chaired the Conference to hand over the position of Commander of Military Region 7.

Hanoi sets out the principles for arranging commune-level cadres and civil servants

|

Hanoi - The arrangement of commune-level civil servants and public employees is carried out according to the principle of maintaining existing staff, allocating them in accordance with job positions and training levels.

Close-up of the proposed street named Hang Long

|

Hanoi - The name of Hang Long ancient town is proposed to be restored, giving the name to the road from Tran Binh Trong intersection to Yet Kieu intersection.

Noi Bai - Lao Cai Expressway is expected to be expanded to 4 lanes in September 2025

|

Lao Cai - The Standing Committee of the Provincial Party Committee and the Vietnam Expressway Corporation (VEC) agreed to soon upgrade the Yen Bai - Lao Cai Expressway to 4 lanes.

Reservoirs in Dien Bien are still thirsty in the rainy season

NHÓM PV |

Dien Bien - Although it is the peak of the rainy season, the total capacity of the 13 reservoirs is still thirsty when it has only reached more than 50% of the design.

Digging into a reservoir in Lam Dong, discovering something that looks like a giant bomb

LAM HỒNG |

Lam Dong - While digging a reservoir, a household in Residential Group 7 (Phuoc Cat town, Da Huoai district, Lam Dong) discovered an object resembling a giant bomb.

On the large reservoir construction site worth over VND500 billion in the far West of the country

VĂN THÀNH CHƯƠNG |

Dien Bien - After more than a year of construction, the reservoir project worth more than 500 billion VND in Muong Nhe district - the far western part of the country has completed about 30% of the volume.

Looking for contractors for construction package worth nearly 850 billion VND of Canh Tang Lake Project

Đặng Tình |

Hoa Binh - The investor is issuing bidding documents for Package No. 46 Construction and equipment of Canh Tang Lake Project.