Ho Chi Minh City sets milestone for opening 13km of 4-lane elevated road in Thu Duc

MINH QUÂN |

HCMC – The 13km-long, 4-lane elevated road through Thu Duc City (part of Ho Chi Minh City's Ring Road 3) is targeted to open to traffic on January 30, 2026.

The Beltway 3 project through Ho Chi Minh City is more than 47km long, including an elevated road section of more than 13km through Thu Duc City.

Designed with 4 lanes in the first phase, this section connects from Nhon Trach Bridge (Dong Nai), crosses Ho Chi Minh City - Long Thanh - Dau Giay Expressway and ends at Tan Van intersection (Binh Duong).

The elevated road construction option was chosen to adapt to the complex terrain, while saving land area and minimizing site clearance costs, as only a 63m wide clearance area is needed instead of a larger area if a ground road is built.

This elevated road also extends to Tan Van intersection connecting with ICD Long Binh port - the future logistics center area, creating convenience for traffic and operational safety.

Duong tren cao thuoc Vanh dai 3 qua TP Thu Duc dang duoc day nhanh thi cong.  Anh: Minh Quan
The elevated road of Ring Road 3 through Thu Duc City is being accelerated in construction. Photo: Minh Quan

According to the Management Board of Investment and Construction of Traffic Works in Ho Chi Minh City, this elevated road section is divided into 5 main bidding packages.

Currently, the XL3 package, which started construction in June 2023, has completed 34.11% of the work volume.

The remaining packages, which started construction in January 2024, are also being accelerated with different completion levels: XL1 reached 14.67%, XL2 reached 13.96%, and XL4 and XL5 both reached 10.3%.

In early November, hundreds of engineers and workers focused on constructing the foundation, pedestal, and pier of the viaduct.

At the construction site, the shape of dozens of viaduct piers has been determined, and the installation of girders is also taking place continuously. As observed from above, the direction and route of Ring Road 3 through Thu Duc City are gradually becoming clear.

Vanh dai 3 di tren cao qua TP Thu Duc dan lo dien.  Anh: Minh Quan
The elevated Ring Road 3 passing through Thu Duc City is gradually emerging. Photo: Minh Quan

Vice Chairman of Ho Chi Minh City People's Committee Bui Xuan Cuong has just directed to strive to complete and open the elevated road section through Thu Duc City to traffic on January 30, 2026.

To achieve this goal, the HCM City Traffic Construction Investment Project Management Board is required to direct construction units to increase human resources, machinery and equipment, and add more construction teams to speed up progress.

The 76km-long Ho Chi Minh City Ring Road 3 project passes through Ho Chi Minh City, Binh Duong, Long An and Dong Nai with a total investment of more than VND75,378 billion, including construction and site clearance costs.

In addition to the section through Thu Duc City, which has a determined opening date, other sections of Ring Road 3 also have specific completion dates.

According to plan, by April 30, 2025, the section from Nhon Trach bridge to Ho Chi Minh City - Long Thanh - Dau Giay expressway will be completed and put into operation.

In December 2025, the expressway section through Long An, from Kenh Thay Thuoc bridge to Ben Luc intersection will be open to traffic.

By April 30, 2026, the sections of Ring Road 3 through Binh Chanh, Hoc Mon and Cu Chi districts (HCMC) will be open to traffic along with the sections through Dong Nai and Binh Duong.

In December 2026, the entire Ho Chi Minh City Ring Road 3 expressway will be officially completed and open to traffic.

MINH QUÂN
TIN LIÊN QUAN

Shape of Ring Road 3 through Cu Chi district after 14 months of construction

|

The atmosphere at the Ho Chi Minh City Ring Road 3 project passing through Cu Chi district is currently very bustling with the efforts of hundreds of workers working day and night to speed up the project's progress.

Ho Chi Minh City Ring Road 3 through Dong Nai clears 90% of land

|

Dong Nai - Component 3 project of Ho Chi Minh City Ring Road 3, section through Nhon Trach district, has cleared more than 90% of the land.

Viewing Ho Chi Minh City Ring Road 3 after more than 1 year of construction

|

HCMC - The Ho Chi Minh City Ring Road 3 project through Hoc Mon district has reached 15% progress after more than 1 year of construction.

Ms. Nguyen Hai Tram is the Standing Deputy Secretary of Tien Giang Provincial Party Committee

|

Tien Giang - Ms. Nguyen Hai Tram was mobilized and appointed to join the Executive Committee, Standing Committee of the Provincial Party Committee and hold the position of Permanent Deputy Secretary of the Tien Giang Provincial Party Committee.

Transfer high-risk invoice list to police

|

The tax authority will continue to coordinate in providing the list of taxpayers with high risks regarding invoices to the police.

Dump truck crashes into multiple cars waiting at red light, killing 1 person

|

Binh Duong - In Tan Uyen city, a dump truck accident just occurred, causing one person to die on the spot and many vehicles to be damaged.

Colonel Nguyen Huu Phuoc appointed Director of Khanh Hoa Provincial Police

|

Colonel Nguyen Huu Phuoc - Deputy Director of Phu Tho Provincial Police was appointed by the Ministry of Public Security as Director of Khanh Hoa Provincial Police.

Vietnam futsal team wins second match at Southeast Asian tournament

|

On the afternoon of November 4, the Vietnamese futsal team won 2-0 against Malaysia at the Southeast Asian championship with goals from Minh Quang and Thinh Phat.

Shape of Ring Road 3 through Cu Chi district after 14 months of construction

Anh Tú |

The atmosphere at the Ho Chi Minh City Ring Road 3 project passing through Cu Chi district is currently very bustling with the efforts of hundreds of workers working day and night to speed up the project's progress.

Ho Chi Minh City Ring Road 3 through Dong Nai clears 90% of land

HÀ ANH CHIẾN |

Dong Nai - Component 3 project of Ho Chi Minh City Ring Road 3, section through Nhon Trach district, has cleared more than 90% of the land.

Viewing Ho Chi Minh City Ring Road 3 after more than 1 year of construction

Minh Tâm - Anh Tú |

HCMC - The Ho Chi Minh City Ring Road 3 project through Hoc Mon district has reached 15% progress after more than 1 year of construction.