Road worth over 41,000 billion VND in Ho Chi Minh City "congested" because of 4 houses

TÚ QUÂN |

HCMC - Four houses located in the middle of the Ring Road 3 project site, passing through Thu Duc City, are hindering construction progress.

The Ho Chi Minh City Ring Road 3 project through Thu Duc City has completed the installation of girders at many sections of the overpass. However, 4 houses located in the middle of the construction site have not been relocated, directly affecting the construction progress.

Do vuong 4 can nha, du an Vanh dai 3 chua the thi cong 3 tru cau can.  Anh: Anh Tu
Due to the obstruction of 4 houses, the Ring Road 3 project has not been able to construct 3 overpass piers. Photo: Anh Tu

Mr. Pham Van Thang - Deputy General Director of Thai Yen Construction Investment Joint Stock Company - a member of the consortium implementing the XL3 package, said that due to the land acquisition of 4 houses, the construction of 3 overpass piers could not be carried out.

Mr. Thang emphasized: "It is necessary to quickly resolve the site clearance to ensure the project is completed on schedule."

The Ho Chi Minh City Ring Road 3 project has just launched a competition movement "365 days and nights to speed up progress" with the goal of completing the technical traffic opening of the entire elevated section of more than 14km through Thu Duc City by December 31, 2025.

4 can nha giua cong truong Vanh dai 3 chua di doi.  Anh: Anh Tu
4 houses in the middle of the Ring Road 3 construction site have not been relocated. Photo: Anh Tu

According to Mr. Vo Tri Dung - Head of the Compensation and Site Clearance Board of Thu Duc City, the recovery of the above 4 houses is not part of the compensation project of Ring Road 3 but belongs to the project land of the enterprise. In principle, the enterprise compensates and hands over the site to Thu Duc City.

Currently, people are asking for compensation of about 100 million VND/m2. However, Mr. Dung said that this area is planned for traffic land, not land for commercial housing or park land, so the investor does not accept this price.

“Thu Duc City is coordinating with businesses to continue negotiating with households. If residents still demand excessive compensation, they will be forced to comply with legal regulations. The city aims to resolve this issue by January 2025,” Mr. Dung affirmed.

Beltway 3 through Ho Chi Minh City is more than 47km long, of which the section through Thu Duc City is more than 14km long, designed as an elevated road with 4 lanes in phase 1.

This route connects from Ho Chi Minh City - Long Thanh - Dau Giay Expressway, passes through Thu Duc City and ends at Tan Van intersection (Binh Duong).

Vanh dai 3 qua TP Thu Duc (TPHCM) dai hon 14km se di tren cao, du kien hoan thanh va thong xe cuoi nam 2025.  Anh: Anh Tu
Beltway 3 through Thu Duc City (HCMC) is over 14km long and will be elevated, expected to be completed and open to traffic by the end of 2025. Photo: Anh Tu

The total investment for Beltway 3 through Ho Chi Minh City is about 41,387 billion VND, of which site clearance costs account for 18,975 billion VND.

In addition to the section of Ring Road 3 through Thu Duc City expected to open to traffic at the end of 2025, the sections in Cu Chi, Hoc Mon, and Binh Chanh districts, nearly 33km long, will be technically opened to traffic at the end of April 2026.

TÚ QUÂN
TIN LIÊN QUAN

Ho Chi Minh City's Ring Road 3 sprints to the finish line

|

After more than 18 months of delays due to a lack of sand supply for filling, the Beltway 3 project through Ho Chi Minh City is entering the accelerated construction phase. Some sections will be technically opened to traffic in 2025, the entire route is expected to be completed in 2026.

The 14km long elevated road connecting Ho Chi Minh City and Binh Duong is gradually emerging

|

HCMC - The 14km-long, 4-lane elevated road passing through Thu Duc City (belonging to Ho Chi Minh City's Ring Road 3) is expected to be completed and put into operation by the end of 2025.

Viewing Ho Chi Minh City Ring Road 3 after more than 1 year of construction

|

HCMC - The Ho Chi Minh City Ring Road 3 project through Hoc Mon district has reached 15% progress after more than 1 year of construction.

Strong earthquake in Tonga just a few days after Myanmar earthquake

|

A 7.1-magnitude earthquake near Tonga prompted an initial Tsunami warning but was later lifted.

The Cong Viettel beat Hoang Anh Gia Lai to advance to the semi-finals of the National Cup

|

On the evening of March 30, The Cong Viettel defeated Hoang Anh Gia Lai with a score of 2-0 to win a ticket to the semi-finals of the 2024-2025 National Cup.

Updated gold price at the end of session 30.3: Profit despite surfing

|

Updated gold price at the end of the session on March 30: The difference between buying and selling is at a high level, investors still make a profit even if investing in the short term.

The army and police set out to support overcoming the consequences of the earthquake

|

The delegation of officers and soldiers of the Ministry of National Defense and the Ministry of Public Security have set out to support Myanmar in overcoming the consequences of the earthquake.

Waiting for the end of living with wastewater in industrial parks

|

Quang Tri - The lives of people living next to industrial parks have been disrupted by wastewater. Meanwhile, the wastewater treatment plant has not yet come into operation

Ho Chi Minh City's Ring Road 3 sprints to the finish line

MINH QUÂN |

After more than 18 months of delays due to a lack of sand supply for filling, the Beltway 3 project through Ho Chi Minh City is entering the accelerated construction phase. Some sections will be technically opened to traffic in 2025, the entire route is expected to be completed in 2026.

The 14km long elevated road connecting Ho Chi Minh City and Binh Duong is gradually emerging

TÚ QUÂN |

HCMC - The 14km-long, 4-lane elevated road passing through Thu Duc City (belonging to Ho Chi Minh City's Ring Road 3) is expected to be completed and put into operation by the end of 2025.

Viewing Ho Chi Minh City Ring Road 3 after more than 1 year of construction

Minh Tâm - Anh Tú |

HCMC - The Ho Chi Minh City Ring Road 3 project through Hoc Mon district has reached 15% progress after more than 1 year of construction.