Ring Road 1 is preparing for technical opening, Ring Road 2.5 and the bridge over the Red River are accelerating

SÓNG HỮU |

Hanoi - Many key traffic projects such as Ring Road 1, Ring Road 2.5, bridges across the Red River... are being accelerated during the National Day 2/9 holiday.

On the morning of September 1st, at the construction site of the Ring Road 1 project, Hoang Cau - Voi Phuc section, a group of workers braved the sun, accelerating the construction progress of many project items, including the item of completing sidewalk paving.

Mr. Tong Ba Nguyen (62 years old, from Thanh Hoa province) working at the Ring Road 1 project said that before the urgent progress of the project, many workers like him have temporarily put aside holidays and stayed at the construction site to speed up the project progress.

I also miss home and want to return to my family and loved ones to gather during the holidays, but being encouraged by the contractor, we are willing to stay" - Mr. Nguyen said.

Công nhân thi công lát đá vỉa hè dự án đường Vành đai 1, sáng 1.9. Ảnh: Sóng Hữu
Workers paving sidewalks of Ring Road 1 project, morning of September 1. Photo: Song Huu
s
Mr. Tong Ba Nguyen (in blue shirt) works in the sun at the Ring Road 1 project. Photo: Song Huu

For the male worker, contributing a part of his efforts to the city's key project is also the joy of him and many other workers working at the construction site.

The road opening will help change the urban appearance, contribute to reducing traffic congestion, and help people travel more conveniently" - Mr. Nguyen said.

At the same time, many workers are also urgently installing mobile medians at the intersection with Nguyen Chi Thanh street, ensuring the technical traffic opening progress of the project (road section), expected on September 2.

Meanwhile, 2 overpasses on the route at the Lang Ha and Nguyen Chi Thanh intersections are still under construction, expected to be completed before December 31, 2026.

ss
Temporary traffic on Ring Road 1, Hoang Cau - Voi Phuc section. Photo: Song Huu
d
Some sidewalk sections have been completed. Photo: Song Huu
d
Green trees are planted on the median strip of Ring Road 1. Photo: Song Huu
sdvdvs
The overpass at Nguyen Chi Thanh intersection is under construction. Photo: Song Huu
Tuyến đường khi hoàn thành có mặt cắt ngang 50m. Ảnh: Sóng Hữu
The road when completed has a cross-section of 50m. Photo: Song Huu

At the Ring Road 2.5 project, Cau Giay - Dich Vong New Urban Area section, many machines and workers are mobilized to maintain the construction pace at the construction site.

Project commander - Mr. Do Van Giap is always present at the construction site throughout the holidays of National Day September 2nd to urge and direct construction work.

Mr. Giap said that according to the plan, Ring Road 2.5 must be cleared in 2026, the contractor does not have much time left, so they must make efforts every day, every hour.

Although it is a holiday, all forces at the construction site are determined to stick to their positions, striving to speed up each item of work" - commander Do Van Giap said.

Công trường dự án đường Vành đai 2,5 đoạn Cầu Giấy - Khu đô thị mới Dịch Vọng, sáng 1.9. Ảnh: Sóng Hữu
Construction site of Ring Road 2.5 section Cau Giay - Dich Vong New Urban Area, morning of September 1. Photo: Song Huu
s
The project is being urgently constructed. Photo: Song Huu

According to Mr. Giap, the labor force is mostly people far from home, moving during holidays is often difficult and time-consuming, disrupting the construction pace.

Therefore, the construction site command board has proactively planned to encourage and care for the material and spiritual life, helping workers to feel secure in staying to work.

At the project construction site, male student Le Ngoc Hieu (20 years old, from Thanh Hoa, currently a 2nd year student at a university in Gia Lam commune) is diligently working on the assigned tasks.

Although it is an extra job, I still try to complete the tasks assigned at the project well. Working at the construction site is really hard, but it gives me experience and income to cover my life and studies" - Hieu said.

s
Machinery working throughout the holiday at the Ring Road 2.5 project construction site. Photo: Song Huu

In addition to the Ring Road 1 project, Hoang Cau - Voi Phuc section, Ring Road 2.5, bridges across the Red River are also entering the acceleration phase.

At the Tran Hung Dao bridge project, Mr. Mai Minh Thang - Commander of Trung Chinh contractor said that the unit still maintains construction throughout the National Day holiday September 2.

According to Mr. Thang, the progress of the entire project is in a hurried stage, the contractor is forced to take advantage of each period of favorable weather as well as holidays to concentrate manpower and encourage workers to stick to the construction site.

Công trường dự án cầu Trần Hưng Đạo. Ảnh: Sóng Hữu
Construction site of Tran Hung Dao bridge project. Photo: Song Huu

Besides the construction efforts, Mr. Thang emphasized that the contractor's biggest desire is to soon hand over a clean and synchronous site.

Currently, the relocation of technical infrastructure is being implemented, but the progress is not as expected. The site clearance problem not only affects the construction of key items such as access roads and branch bridges, but also puts pressure on the progress of the later stage.

Therefore, the contractor hopes that functional agencies will coordinate to completely handle site clearance so that the project can accelerate, towards the goal of completing the project in accordance with the city's direction, expected in 2027.

SÓNG HỮU
RELATED NEWS

Installing mobile medians, organizing traffic on Ring Road 1

|

Hanoi - Mobile median strips are being installed to organize and divert traffic on Ring Road 1, Hoang Cau - Voi Phuc section.

General Secretary and President To Lam requests to ensure the progress of the entire Hanoi Ring Road 1

|

Hanoi - General Secretary and President To Lam requested to ensure progress, strive to soon open the entire route to traffic, and maximize the efficiency of the Ring Road 1 project.

Many strong whirlpools appear, possibility of new storms in the next 2 weeks

|

On September 1, low pressure Pilandok officially strengthened into a tropical storm, warning of 4 more monsoon zones likely to form in the next 2 weeks.

Birds suddenly run amidst traffic on National Highway 18 in Quang Ninh

|

Quang Ninh - A ostrich suddenly ran amidst traffic on National Highway 18, traffic police promptly warned and regulated vehicles to ensure safety.

Current status of the nearly 4.6km long riverside road passing through the super ward in Dong Nai

|

Dong Nai - The Cai riverside road project is nearly 4.6km long, passing through Tran Bien and Tam Hiep wards, with a total investment of nearly 574 billion VND.

Installing mobile medians, organizing traffic on Ring Road 1

SÓNG HỮU |

Hanoi - Mobile median strips are being installed to organize and divert traffic on Ring Road 1, Hoang Cau - Voi Phuc section.

Diện mạo đường 8 làn xe ở Hà Nội trước ngày thông xe kỹ thuật

HOÀI ANH - ĐẶNG TIẾN |

Hà Nội - Người dân mừng vui, phấn khởi trước diện mạo của đường Vành đai 1 đoạn Hoàng Cầu - Voi Phục, dự kiến thông xe kỹ thuật dịp Quốc khánh 2.9.

General Secretary and President To Lam requests to ensure the progress of the entire Hanoi Ring Road 1

HOÀI ANH |

Hanoi - General Secretary and President To Lam requested to ensure progress, strive to soon open the entire route to traffic, and maximize the efficiency of the Ring Road 1 project.