Many cracks appear on an overpass on the Tien Yen - Mong Cai expressway

Đoàn Hưng |

Quang Ninh - Hoa Hong Bridge on the Tien Yen - Mong Cai expressway has many cracks. The investor is inspecting and determining the cause to have a handling plan.

Lao Dong Newspaper has just received feedback from readers about the Hoa Hong bridge across the Tien Yen - Mong Cai expressway showing many cracks.

Readers expressed concern that if this situation continues to develop, it may affect the safety of the project as well as vehicles traveling on the expressway below.

Toàn cảnh cầu Hoa Hồng bắc qua cáo tốc . Ảnh: Đoàn Hưng
Panorama of Hoa Hong Bridge spanning Tien Yen - Mong Cai highway. Photo: Doan Hung

On August 13, Lao Dong Newspaper reporters were present at Hoa Hong bridge, Duong Hoa commune to verify the incident. According to reporters' observations, cracks appeared a lot at both ends of the bridge; there is one crack extending along the length of the bridge body.

Talking to reporters, the leader of Duong Hoa Commune People's Committee said that the locality has just received feedback on the cracking situation at Hoa Hong bridge deck and has assigned a professional department to inspect the site.

Vết nứt tỏa thành 3 nhánh tại khu vực đầu cầu Hoa Hồng. Ảnh: Đoàn Hưng
Cracks spreading into 3 branches at the Hoa Hong bridgehead area. Photo: Doan Hung

According to the reporter's investigation, Hoa Hong bridge belongs to the Sub-project of construction of auxiliary works under the Project to Invest in the construction of the Tien Yen - Mong Cai expressway.

The investor is the Quang Ninh Provincial Traffic Construction Investment Project Management Board (now the Quang Ninh Region II Construction Investment Project Management Board).

Cốt thép tại lan can cầu lộ ra, han gỉ. Ảnh: Đoàn Hưng
The steel core at the bridge railing is exposed, rusty. Photo: Doan Hung

According to information from the Construction Investment Project Management Board of Region II of Quang Ninh province, Hoa Hong overpass has an investment value of 5.6 billion VND, constructed by Bridge 75 Construction Joint Stock Company and subcontractor Phuong Dong Construction and Trading Joint Stock Company.

The bridge consists of a 38.3m long span, a total length of 60.4m, a width of 4.7m, and has been put into use since 2022.

Regarding the appearance of cracks on Hoa Hong bridge, the Project Management Board for Construction Investment Area II of Quang Ninh province has also received a written reflection from Van Don Infrastructure Investment and Development Co., Ltd. (the unit managing, operating, and exploiting the Tien Yen - Mong Cai expressway).

Vết nứt tại vị trí tiếp giáp giữa lan can và mặt cầu. Ảnh: Đoàn Hưng
Cracks at the junction between the railing and the bridge deck. Photo: Doan Hung

According to the company's reflection, during the patrol and inspection of the route on August 11, the unit discovered damage at the overpass on the Tien Yen - Mong Cai expressway, Km136+900 (Hoa Hong bridge).

Preliminary inspection of the scene, the route management unit recorded that cracks in the road surface appeared in the bridge deck area on the side of the railing, including a location where the crack was extended. Some locations of concrete structure in the railing area showed signs of cracking and breaking; cracks appeared on the upper part of the railing; the beam wing area below showed signs of damage.

According to the expressway operating unit, the above situation needs to be inspected and specifically assessed for the causes and extent of impact on the load-bearing capacity and operational safety of the project.

The company requests the investor to urgently organize a field inspection, coordinate with the operating unit and related consulting units to assess the current state of damage.

Phần tiếp giáp giữa mặt cầu và mố cầu xuất hiện vết nứt. Ảnh: Đoàn Hưng
The interface between the bridge deck and the bridge abutment shows cracks. Photo: Doan Hung

Talking to a reporter of Lao Dong Newspaper, Mr. Tran Viet Dung - Director of the Project Management Board for Construction Investment Area II of Quang Ninh province - said that immediately after receiving information from the expressway management and operation unit, the Board informed the local authorities to coordinate preliminary inspection, and at the same time requested special attention to ensuring safety during the operation of the Tien Yen - Mong Cai expressway.

In the immediate future, it is necessary to ensure that materials and components from the bridge do not fall onto the expressway, affecting people and vehicles traveling below.

The Board has also directed professional departments to inspect and preliminarily assess the current situation; coordinate with the project management and exploitation unit and hire an inspection consulting unit for specific assessment.

The inspection results will be the basis for determining the cause, level of damage and đưa ra long-term handling measures, ensuring the safety of project operation" - Mr. Dung said.

Đoàn Hưng
RELATED NEWS

Accident on Phan Thiet - Dau Giay expressway: Truck encounters problem, stops in emergency lane

|

Lam Dong - A passenger car carrying 18 foreign passengers crashed into the rear of a truck that had an accident and stopped on the emergency lane.

Quang Ninh expands student transportation support in the new school year

|

Quang Ninh - In the 2026 - 2027 school year, Quang Ninh province will implement many policies to support student transportation right from the beginning of the new school year.

Quang Ninh Provincial Party Secretary dialogues with exemplary students

|

Quang Ninh - On August 14, Quang Ninh province organized the program "Meeting with typical students of the 2025-2026 school year".

Multiple collisions on the Noi Bai - Lao Cai expressway cause traffic congestion

|

Lao Cai - A collision between a passenger car, a 16-seater car and a car on the Noi Bai - Lao Cai expressway caused prolonged traffic congestion in the area.

Dak Lak verifies KOL cardholders accused of speaking inappropriately at durian festival

|

Dak Lak - Functional agencies are verifying and clarifying the case of a KOL cardholder being reported for speaking inappropriately at a durian festival.

21 teams participate in the 7th Vietnam Textile and Garment Industry Skills Competition

|

On the morning of August 16, the 7th Vietnam Textile and Garment Industry Skilled Workers Contest in the field of sewing - thoi weaving took place in Hanoi with 21 participating teams.

524 land plots handed over by people to build expressways in Dong Nai

|

Dong Nai - 524 land plots agreed by people in Binh Phuoc ward to be handed over to the State for the Gia Nghia - Chon Thanh expressway project.

Accident on Phan Thiet - Dau Giay expressway: Truck encounters problem, stops in emergency lane

Duy Tuấn |

Lam Dong - A passenger car carrying 18 foreign passengers crashed into the rear of a truck that had an accident and stopped on the emergency lane.

Quang Ninh expands student transportation support in the new school year

Đoàn Hưng |

Quang Ninh - In the 2026 - 2027 school year, Quang Ninh province will implement many policies to support student transportation right from the beginning of the new school year.

Quang Ninh Provincial Party Secretary dialogues with exemplary students

Nguyễn Hùng |

Quang Ninh - On August 14, Quang Ninh province organized the program "Meeting with typical students of the 2025-2026 school year".