Varying prices of construction materials affect the progress of the Ho Chi Minh City Ring Road 3 project
Due to the scarcity of sand and stone, the price of construction materials fluctuated greatly, affecting the progress of the Ho Chi Minh City Ring Road 3 project.

The Binh Duong Provincial Traffic Construction Investment Project Management Board is focusing on speeding up the construction progress of 11.4 km of the Ho Chi Minh City Ring Road 3 component 5 project through the old Binh Duong province. The current difficulty is that the source of materials for construction packages has not yet reached the foot of the project.
Regarding sand for roadbed construction, the total demand for component project 5 is 0.7 million m3, but the supply capacity from existing mines is only 0.4 million m3, a shortage of 0.3 million m3. According to the Report of the Ho Chi Minh City People's Committee, the Western provinces have granted exploitation licenses for 13/16 mines to supply the Ho Chi Minh City Ring Road 3 project. Units are coordinating to ensure enough sand is needed to bring to the project.
This year, sand will continue to be collected from Binh Hoa Phuoc 2 mines, Chanh An - Vinh Long mines, Vam Cat Thia - Tien Giang mines and sand from Cambodia. See more...
People come to confirm income from buying social housing but the company does not resolve it
The Ministry of Construction Information Portal posted Ms. P.H's opinion as follows: I am applying to buy social housing and am currently an employee with a labor contract at the company.
My income at the company is under 15 million VND/month. But when I asked to confirm form 05 of the income certificate, the company did not confirm it to me because the company did not know whether I would still have income elsewhere in addition to my income from the company?
May I ask, is there any law that requires the company to confirm that employees have labor contracts? If the company still does not confirm me, which agency should I meet and work with to resolve the issue?

After studying, the Department of Housing and Real Estate Market Management, Ministry of Construction gave the following opinion:
Article 30 of Decree No. 100/2024/ND-CP dated July 26, 2024 of the Government detailing a number of articles of the Housing Law on the development and management of social housing stipulates: 1. For subjects specified in Clauses 5, 6 and 8, Article 76 of the Housing Law, the following income conditions must be ensured:
In case the petitioner is a single person, with actual monthly income, the salary is not more than 15 million VND calculated according to the Salary and Salary Table confirmed by the agency, unit, or enterprise where the subject works. See more...
Inspecting a series of urban projects with signs of slow progress in Thai Nguyen
On August 3, information from the Thai Nguyen Provincial Inspectorate said that this unit is conducting a thematic inspection of 18 residential, housing and urban area projects with signs of being behind schedule and arising legal problems in the area.

The inspection list includes 18 projects of 16 investors. Some notable enterprises include:
1. Kosy Joint Stock Company with Gia Sang Urban Area Project (now Gia Sang Ward);
2. Picenza Vietnam Joint Stock Company with the European Quarter Project on the Cau River bank (now Linh Son ward).
3. BCD Group Joint Stock Company with 2 projects in Dai Phuc commune and Dong Hy commune.
4. Truong Thuan Phat Real Estate Joint Stock Company with the Green House social housing project in Tich Luong ward.
5. Binh Minh Phat Investment Joint Stock Company with the Workers' Housing Project, Social Housing in Tich Luong Ward.
In addition, there are also projects of Viet Dung Company Limited, Hoang Mat, Tu Son Forestry Processing, Tan Dai Viet, Ha Phat, 668, Tan Duc, Yen Binh, Van Phuc Viet and Tien Hoa. See more...