Quang Ninh Provincial Party Secretary requests strict handling of slow-progressing and illegal projects

Nguyễn Hùng |

Quang Ninh - On June 11, the Secretary of the Quang Ninh Provincial Party Committee inspected non-budget investment projects in Cao Xanh ward - where there are 26 slow-progress projects.

In Cao Xanh ward, there are currently 26 slow-progress projects. Through review, the main reasons for slow-progress projects are obstacles in investment policies; land allocation and lease; financial obligations; site clearance work; inspection and examination conclusions and due to the capacity of the investor.

Inspecting the reality of some slow-progress projects in the area, Mr. Quan Minh Cuong - Member of the Party Central Committee, Secretary of the Provincial Party Committee, Head of the Quang Ninh Provincial National Assembly Delegation - requested to resolutely and strictly handle slow-progress projects.

Do not let slow-progress projects affect people's lives, affect business confidence, affect the investment and business environment of the province, affect the rights and cooperative interests of businesses and people, affect the environmental landscape, causing waste of social resources.

In which, for the Hon Gac Tourist Area project invested by INDEVCO Group JSC, the Provincial Party Secretary requested the Provincial Inspectorate to immediately conduct an inspection of the project; on that basis, propose a handling plan; resolutely prevent the situation of slow progress from continuing to be prolonged.

 Bí thư Tỉnh ủy Quảng Ninh nghe chủ đầu tư là Công ty CP Xây dựng công trình 507 báo cáo về dự án. Ảnh: Thu Chung
Quang Ninh Provincial Party Secretary listens to the investor, Construction Joint Stock Company 507, report on the project. Photo: Thu Chung

The Provincial Party Secretary directed that an inspection decision must be issued immediately tomorrow (June 12) and a conclusion within 30 days; if the enterprise is right, the state agency is responsible and requests the enterprise to implement it immediately; if the enterprise is not right, it must be resolutely recovered immediately.

Regarding urban infrastructure investment projects of FLC Group JSC, Construction Joint Stock Company 507, the Provincial Party Secretary emphasized that these are projects that have been delayed for many years, causing waste of land resources, affecting the urban face and the development of the locality.

Therefore, functional agencies must quickly get involved in verifying and clarifying the capacity of the investor as well as the problems and obstacles in the project implementation process and the responsibilities of the related parties; resolutely implement recovery if the project continues to be behind schedule.

Regarding the project of investing in construction - infrastructure business of Cao Xanh - Ha Khanh C new urban area invested by Bien Dong Project Development Joint Stock Company, the Provincial Party Secretary requested that in addition to completing infrastructure items, the investor must have measures to handle the situation of two secondary investors jointly contributing capital on one land plot.

Mr. Quan Minh Cuong also noted that, besides economic benefits, businesses must also put prestige and social responsibility first; must closely coordinate with local authorities and functional agencies in the process of resolving existing problems and obstacles of the project.

Nguyễn Hùng
RELATED NEWS

Nghe An warns of handling investors if they continue to delay progress

|

Nghe An - Leaders of the Provincial People's Committee request the investor to focus resources and accelerate the progress of resettlement buildings.

Da Nang requests handling of 5 contractors who are not qualified and are behind schedule

|

Da Nang - Learning from experience in contractor selection, handling 5 cases of contractors being assessed as incompetent and behind schedule according to regulations.

5 localities behind schedule in building boarding schools in border communes

|

There are 5 localities that are behind schedule in building boarding schools in border communes and a few schools are facing difficulties due to complex geological locations.

Finishing the Math exam of the 2026 High School Exam: Many candidates are confident of getting 8-10 points

|

Ho Chi Minh City - At the end of the first day of the 2026 high school exam, many candidates assessed that the Math exam was differentiated, but still confidently achieved high scores, even absolute.

Landslide kills 3 young men in Lai Chau

|

Lai Chau - Heavy rain and landslides have killed 3 young people, and many properties and crops have been damaged.

Hanoi has 37,000 job seekers in May 2026

|

According to the Hanoi Employment Service Center, in May 2026, the City had 37,000 people looking for jobs.

Arranging villages and residential groups associated with grassroots security and order protection forces

|

The process of arranging villages and residential groups will prioritize selecting people who have been trained through Police and Military schools as Heads and Deputy Heads of Security and Order Protection Teams.

Nghe An warns of handling investors if they continue to delay progress

QUANG ĐẠI |

Nghe An - Leaders of the Provincial People's Committee request the investor to focus resources and accelerate the progress of resettlement buildings.

Da Nang requests handling of 5 contractors who are not qualified and are behind schedule

Trần Thi |

Da Nang - Learning from experience in contractor selection, handling 5 cases of contractors being assessed as incompetent and behind schedule according to regulations.

5 localities behind schedule in building boarding schools in border communes

PHẠM ĐÔNG |

There are 5 localities that are behind schedule in building boarding schools in border communes and a few schools are facing difficulties due to complex geological locations.