Da Nang requests handling of 5 contractors who are not qualified and are behind schedule

Trần Thi |

Da Nang - Learning from experience in contractor selection, handling 5 cases of contractors being assessed as incompetent and behind schedule according to regulations.

On May 18, news from Da Nang City People's Committee said that the city has just issued Official Dispatch No. 4105/UBND-STC regarding reports and periodic review of contractor capacity in the first quarter of 2026.

Accordingly, the Chairman of Da Nang City People's Committee requested the Department of Construction, Nam Tra My Commune People's Committee and Hoa Xuan Ward People's Committee to draw experience in organizing contractor selection, ensuring the selection of contractors with full capacity and practical experience in accordance with the information provided in the bidding documents, ensuring the progress of deployment and completion of the project.

In case of arising problems, it is necessary to promptly report to the City People's Committee for consideration and handling to ensure that the project is implemented in accordance with regulations.

In case of not fully and promptly reporting and allowing the situation of selected contractors not ensuring capacity and slow construction progress to occur, units must bear full responsibility before the law and the Chairman of the City People's Committee.

5 trường hợp nhà thầu bị đánh giá vi phạm. Ảnh: UBND TP Đà Nẵng
5 cases of contractors being assessed as violating regulations. Photo: Da Nang City People's Committee

The Department of Construction, Nam Tra My Commune People's Committee and Hoa Xuan Ward People's Committee urgently directed the handling of 5 cases of contractors who are not qualified according to the provisions of law.

Along with that, publicize the capacity of weak contractors who violate bidding regulations on the City Electronic Information Portal and other means of information according to regulations.

Investors and project management boards continue to fully implement the review of contractor capacity and periodically report according to the direction of the City People's Committee before the 25th of each month; reports must be complete, specific, and accurate for cases where contractors violate or are behind schedule.

If the report is incomplete and inaccurate, the investors and management boards must bear full responsibility before the Chairman of the City People's Committee.

Trần Thi
RELATED NEWS

Ready land fund to build more than 42,000 social housing units in Da Nang

|

Da Nang - As of mid-2026, Da Nang City has prepared a wealthy land fund, capable of building more than 42,700 social housing units.

Deputy Minister of Construction urges progress of social housing construction in Da Nang

|

Da Nang - Deputy Minister of Construction Nguyen Van Sinh requested Da Nang to soon remove difficulties to accelerate the construction progress of social housing projects.

Da Nang Department of Construction specifically names streets encroaching on sidewalks indiscriminately

|

Da Nang - Da Nang Department of Construction has just requested to thoroughly handle the situation of encroaching on sidewalks as places for plant pots and signs in residential areas.

Contributing ideas to the Trade Union Congress, the Three Shifts strategy for workers to master the AI era

|

Dong Thap - Trade unions need a three-pronged strategy: Converting care models - Transferring technological capacity - Transforming intellectual property into economic value.

Mud and dust overflow onto the Quang Ngai - Hoai Nhon expressway

|

Gia Lai - Muddy soil spills onto the road surface, dust arises in the construction area of Dinh Cuong rest stop on the Quang Ngai - Hoai Nhon expressway.

Organize high school graduation exams and university admissions in the direction of maintaining stability and reducing pressure

|

The Prime Minister requested to organize the high school graduation exam and university entrance exam in 2026 in the direction of maintaining stability, reducing pressure, reducing costs, and preventing fraudulent acts.

Organizing committee responds to the night running race in Ho Chi Minh City causing controversy online

|

The organizers of the Ho Chi Minh City Night Run Eximbank 2026 night race have spoken out about the frustrations of athletes on social networks.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Ready land fund to build more than 42,000 social housing units in Da Nang

Nguyễn Linh |

Da Nang - As of mid-2026, Da Nang City has prepared a wealthy land fund, capable of building more than 42,700 social housing units.

Deputy Minister of Construction urges progress of social housing construction in Da Nang

Nguyễn Linh |

Da Nang - Deputy Minister of Construction Nguyen Van Sinh requested Da Nang to soon remove difficulties to accelerate the construction progress of social housing projects.

Da Nang Department of Construction specifically names streets encroaching on sidewalks indiscriminately

Nguyễn Linh |

Da Nang - Da Nang Department of Construction has just requested to thoroughly handle the situation of encroaching on sidewalks as places for plant pots and signs in residential areas.