Accelerate the progress of the Ho Chi Minh road resettlement area through Tuyen Quang

Nguyễn Tùng |

Resettlement areas for the Ho Chi Minh road project section passing through Tuyen Quang province are being formed to help people whose land is recovered soon stabilize their lives.

The Ho Chi Minh road project section Cho Chu (Thai Nguyen) - Trung Son intersection (Tuyen Quang) nearly 29km long was started in June 2024 with a total investment of more than 1,600 billion VND. In which, the section through Tuyen Quang province is about 17.1km with a total land acquisition area of nearly 81ha, compensation and site clearance (GPMB) costs of more than 250 billion VND.

Recorded at the end of March 2025, 2 resettlement areas serving site clearance for the project section passing through Tuyen Quang province, including the resettlement area of Trung Son commune and the resettlement area of Hung Loi commune, are both under construction.

In the resettlement area of Hung Loi commune, which provides accommodation for 73 households whose land has been recovered, up to now, the ground leveling, internal traffic roads, drainage system have reached nearly 90%, and the domestic water supply system is about to be completed. The domestic electricity system has not been constructed.

Các hạng mục đào đắp, san nền với khối lượng lớn tại khu tái định cư Trung Sơn.
Excavation and leveling items with large volumes at Trung Son resettlement area.

It is expected that on March 30, 2026, functional agencies will hand over land in Hung Loi resettlement area to 67/73 households. For households whose land is recovered for project implementation, the early completion of resettlement areas will also help their lives stabilize soon.

Ms. Hoang Thi Lien (Hung Loi commune) said that her family completely supports the policy of building this road, so they proactively handed over the site early.

I hope the project will be completed soon, with a new big and beautiful road, making travel more convenient. Now, I am preparing to build a new house in the resettlement area to live in, the infrastructure is completed, and living conditions here are also better than before," Ms. Lien shared.

Meanwhile, in the resettlement area of Trung Son commune, the construction progress has not met the set requirements, the volume of leveling and excavation has only reached 70%, and many road and electricity and water items have not been constructed. Currently, land has only been allocated to 3 households.

Lãnh đạo UBND tỉnh Tuyên Quang yêu cầu đẩy nhanh tiến độ dự án, bàn giao đất TĐC để người dân ổn định cuộc sống.
Leaders of Tuyen Quang Provincial People's Committee requested to accelerate the project progress and hand over resettlement land for people to stabilize their lives.

According to the Project Management Board of Construction Works No. 01 of Tuyen Quang province, up to now, there are still 11 households in 2 communes Hung Loi and Trung Son who have not received compensation money, have not handed over land for moving houses and architectural structures and assets on land.

This has affected the progress of construction and construction of items in resettlement areas as well as land allocation and housing construction for people.

Inspecting the progress of this project, Mr. Nguyen Manh Tuan - Standing Vice Chairman of Tuyen Quang Provincial People's Committee - requested the investor to closely coordinate with relevant agencies to focus on definitively resolving problems related to compensation policies for households.

Construction contractors are required to increase manpower, machinery, and accelerate construction progress. Urgently complete to hand over land to affected families to build houses and stabilize their lives.

Nguyễn Tùng
RELATED NEWS

Multiple car accident on Ho Chi Minh road, passing through Da Nang

|

Da Nang - 4 cars involved in a series of accidents on the Ho Chi Minh road, passing through Kham Duc commune at 0:00 AM on March 29.

Mr. Phan Huy Ngoc re-elected as Chairman of Tuyen Quang Provincial People's Committee

|

Tuyen Quang - On the morning of March 28, the 1st Session of the 2026 - 2031 term of the Tuyen Quang Provincial People's Council took place.

Removing bottlenecks, accelerating the construction progress of a highway more than 100km long in Tuyen Quang

|

Currently, 119 construction fronts are being deployed on the entire Tuyen Quang - Ha Giang expressway, and some sections have entered the completion phase.

Secretariat disciplines and expels 3 individuals for serious violations from the Party

|

The Secretariat has decided to impose disciplinary action of expulsion from the Party on 3 party members who seriously violated in performing their responsibilities and assigned tasks.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Multiple car accident on Ho Chi Minh road, passing through Da Nang

Hoàng Bin |

Da Nang - 4 cars involved in a series of accidents on the Ho Chi Minh road, passing through Kham Duc commune at 0:00 AM on March 29.

Mr. Phan Huy Ngoc re-elected as Chairman of Tuyen Quang Provincial People's Committee

Việt Bắc |

Tuyen Quang - On the morning of March 28, the 1st Session of the 2026 - 2031 term of the Tuyen Quang Provincial People's Council took place.

Removing bottlenecks, accelerating the construction progress of a highway more than 100km long in Tuyen Quang

Nguyễn Tùng |

Currently, 119 construction fronts are being deployed on the entire Tuyen Quang - Ha Giang expressway, and some sections have entered the completion phase.