Removing land obstacles for Son My 1 Industrial Park project has changed but is still slow

Duy Tuấn |

Binh Thuan - Son My 1 Industrial Park project is behind schedule due to problems with compensation and site clearance. Most of the area has not been handed over.

The Son My 1 Industrial Park (IP) project in Ham Tan district, Binh Thuan province was approved by the Prime Minister in 2017 and started construction at the end of August 2022.

The progress of compensation and site clearance for Son My 1 Industrial Park project until June 10, 2025 has had some changes, but is still slow, affecting the overall progress of the project.

Phoi canh Khu Cong nghiep Son My 1 hinh thanh trong tuong lai. Anh: Nha dau tu
Perspective of the Son My 1 Industrial Park project in the future. Photo: Investor

In the priority area of 375.6 hectares, Ham Tan district has so far cleared 86.8 hectares. The Provincial People's Committee has also decided to lease land to the investor in the first phase with an area of 76.6 hectares. The remaining area of 288.8 hectares is still being urgently implemented, including 69 households and 8 organizations.

Regarding the compensation progress for households, the District Compensation Council has approved a support plan for 74 households/51 hectares in priority areas. For organizations, although the plan has been approved and a notice of invitation has been sent to receive compensation, so far no unit has agreed to receive the money. Ham Tan District is continuing to mobilize and propagate for organizations to coordinate in handing over the site.

In the remaining area, the district has issued a notice of land reclamation for 183 households and 5 organizations with a total area of 211.8 hectares. Currently, 44 households and 1 organization (49.2 ha) have been inventoried and are being considered for legality for other cases.

Regarding the resettlement area, the Department of Finance has approved the technical economic report of the Son My Resettlement Area Technical Infrastructure Project (phase 1) with a scale of 1.4 hectares. It is expected to arrange about 76 resettlement plots for households whose land is recovered in the Son My 1 Industrial Park project. The District People's Committee has also approved land prices and approved compensation plans for 7 households. The dossier is being completed for appraisal and approval according to regulations.

Mot cong vao du an KCN Son My 1. Anh: Duy Tuan
An entrance to Son My 1 Industrial Park project. Photo: Duy Tuan

According to Vice Chairman of Binh Thuan Provincial People's Committee - Nguyen Hong Hai, the Son My 1 Industrial Park project has a very slow progress in compensation and site clearance. He requested the locality to focus on propaganda so that people have land in the area to agree to receive compensation and hand over the site to the investor to implement the project. Relevant departments and branches coordinate to support localities in accelerating site clearance, ensuring project implementation progress.

When completed, Son My 1 Industrial Park project will become a power center of the province, attracting investment in developing energy industries, industries, logistics... And is very important for socio-economic development, industrialization and modernization in the Southern region and Binh Thuan province.

Duy Tuấn
TIN LIÊN QUAN

Reviewing land funds, orienting the addition of new industrial parks in Binh Thuan

|

Binh Thuan plans to add more industrial parks in the future but must ensure compliance with the planning and land use targets of the province, connecting infrastructure of industrial parks.

Building a road connecting National Highway 1 directly to Son My Industrial Park in Binh Thuan

|

Binh Thuan - The Road Project from Tan Minh town to Son My, Ham Tan district is under construction and will connect National Highway 1 (QL1) to Son My Industrial Park (IP).

Deserted at Son My 1 Industrial Park project after more than 2 years of construction

|

Binh Thuan - Son My 1 Industrial Park project with deserted landscape and surrounding corrugated iron fence after more than 2 years of construction.

Storm No. 1 is about to strengthen, forecasting the most notable impact on the mainland of Vietnam

|

According to the representative of the meteorological agency, storm No. 1 Wutip will increase in intensity in the next 24 hours, affecting both the weather at sea and on land.

Mr. Lai Xuan Mon holds the position of Secretary of the Party Committee of the Central Propaganda and Mass Mobilization Commission

|

Mr. Lai Xuan Mon was appointed to hold the position of Secretary of the Party Committee of the Central Propaganda and Mass Mobilization Commission, term 2025 - 2030.

The Minister of Justice explained that the maximum fine for any field has not been increased

|

Minister of Justice Nguyen Hai Ninh said that increasing the maximum fine is a big issue that needs to be studied and carefully assessed for impact.

Unifying salary policy, assigning the education sector to recruit teachers

|

The National Assembly Standing Committee agreed on salary policy, support and attraction for teachers; assigned authority to the education sector to proactively recruit teachers, etc.

Government approves license of Sun PhuQuoc Airways airline

|

Deputy Prime Minister Tran Hong Ha has just given instructions on granting an air transport business license to Phu Quoc Sun Airlines Company Limited.

Reviewing land funds, orienting the addition of new industrial parks in Binh Thuan

Duy Tuấn |

Binh Thuan plans to add more industrial parks in the future but must ensure compliance with the planning and land use targets of the province, connecting infrastructure of industrial parks.

Building a road connecting National Highway 1 directly to Son My Industrial Park in Binh Thuan

Duy Tuấn |

Binh Thuan - The Road Project from Tan Minh town to Son My, Ham Tan district is under construction and will connect National Highway 1 (QL1) to Son My Industrial Park (IP).

Deserted at Son My 1 Industrial Park project after more than 2 years of construction

Duy Tuấn |

Binh Thuan - Son My 1 Industrial Park project with deserted landscape and surrounding corrugated iron fence after more than 2 years of construction.