Hung Yen promotes progress of a series of key projects in Van Giang

Mai Hương |

Hung Yen - Chairman of the Provincial People's Committee requested departments, branches, and localities to focus on removing obstacles and accelerating the progress of many key projects in the Van Giang area.

On May 14, Mr. Nguyen Manh Quyen - Chairman of Hung Yen Provincial People's Committee - chaired a meeting of the Provincial People's Committee to listen to departments, branches, and localities report on the progress of implementing a number of projects in the province.

At the meeting, delegates reported on the progress of many key projects, including: PVF Youth Football Training Center project; roads connecting the PVF stadium area; Mixed-use urban area in Nghia Tru - Van Giang - Hoan Long commune; Van Giang Industrial Park - phase I; adjusting the construction plan of sub-zone E1, Van Giang urban area.

According to the report, the PVF Youth Football Training Center project is being implemented on an area of about 92.2ha in Nghia Tru and Van Giang communes, with a total investment of more than 2,051 billion VND. Phase 1 of the project has been completed and put into operation. For the expansion phase 2 with a scale of about 71.89ha, site clearance has been 100% completed; the investor is carrying out land procedures to be allocated and leased land according to regulations.

For traffic routes connecting the PVF stadium area, localities are focusing on site clearance, building resettlement areas, completing land acquisition dossiers, inventorying assets and paying compensation and support to people. Some key projects such as Dong - Tay I road, Thanh Nien extended road and connecting route from DT. 378 to DT. 382B are being accelerated.

Chủ tịch UBND tỉnh phát biểu chỉ đạo tại cuộc họp. Ảnh: Tất Đạt
Chairman of the Provincial People's Committee delivers directing speech at the meeting. Photo: Tat Dat

The Mixed-use Urban Area project in Nghia Tru - Van Giang - Hoan Long commune has an area of about 171.8ha, with a total investment of about 21,000 billion VND. Currently, the Department of Construction is carrying out procedures to select consulting contractors to organize investor selection according to regulations.

For the Van Giang Industrial Park project - phase I, the recovered area is about 273ha in Nghia Tru commune, the locality has completed the review, assigned ownership of 100% of the area and issued a notice of land recovery of about 110ha.

Regarding the adjustment of the construction planning of sub-zone E1, Van Giang urban area, the Department of Construction and related units are seeking opinions from departments, branches, localities and residential communities to complete the dossier for submission to the Provincial People's Committee for approval.

Concluding the meeting, Mr. Nguyen Manh Quyen assessed that the progress of some projects has not met requirements, and requested departments, branches, localities and investors to strengthen coordination, focus on removing difficulties to accelerate progress.

The Chairman of the Provincial People's Committee requested to urgently complete the land allocation for the PVF Youth Football Training Center project; accelerate site clearance and resettlement for connecting roads, striving to complete the entire project before March 2027.

For the Mixed-use Urban Area project in Nghia Tru - Van Giang - Hoan Long commune, units need to complete procedures and strive to complete investor selection before July 15, 2026. For Van Giang Industrial Park - phase I, localities need to strengthen propaganda and mobilize people to agree to hand over land, ensuring the progress of land handover to investors.

Mr. Nguyen Manh Quyen also reminded departments, branches, localities and investors to implement projects strictly, publicly, transparently, in accordance with legal regulations, and at the same time ensure the progress, quality and aesthetics of the works.

Mai Hương
RELATED NEWS

Vinh Long removes obstacles for key project group

|

Vinh Long - The province focuses on removing difficulties at An Hiep landfill, Ba Lai bridge and Bung Lac Dia area to promote economic growth in the Eastern region.

Quang Ninh determined to complete site clearance for 22 key projects

|

Quang Ninh sets a target to complete site clearance (GPMB) for 22 key projects before September 2026.

Vinh Long Party Secretary inspects many key projects on environment and traffic

|

Vinh Long - Provincial Party Secretary inspects many key projects to remove difficulties, promote investment progress and complete inter-regional infrastructure.

7 cars collide in a chain reaction on Kim Nguu street in Hanoi

|

Hanoi - A multi-vehicle accident between 7 cars occurred near the Minh Khai - Kim Nguu - Tam Trinh intersection, causing traffic congestion on the afternoon of May 14.

Trade union officials contribute ideas to strengthen the application of AI and social networks in propaganda

|

Khanh Hoa - Contributing opinions to the draft documents of the 14th Vietnam Trade Union Congress, many trade union officials proposed to promote digital transformation in trade union activities.

The owner of the hit "Walking in the Brilliant Sky" promises to explode at Green Transformation Day 2026

|

In addition to free experience activities, Green Transformation Day 2026 also has the participation of many famous singers to spread meaningful messages.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Vinh Long removes obstacles for key project group

HOÀNG LỘC |

Vinh Long - The province focuses on removing difficulties at An Hiep landfill, Ba Lai bridge and Bung Lac Dia area to promote economic growth in the Eastern region.

Quang Ninh determined to complete site clearance for 22 key projects

Nguyễn Hùng |

Quang Ninh sets a target to complete site clearance (GPMB) for 22 key projects before September 2026.

Vinh Long Party Secretary inspects many key projects on environment and traffic

HOÀNG LỘC |

Vinh Long - Provincial Party Secretary inspects many key projects to remove difficulties, promote investment progress and complete inter-regional infrastructure.