Resettling nearly 1,000 households in Dong Nai to expand airport connecting roads

HÀ ANH CHIẾN |

Dong Nai - Project to upgrade and expand DT. 769 road, recover land of about 135.5 ha in 3 communes Dau Giay, Binh An and Long Thanh, resettle 996 households.

On April 3, the Dong Nai Provincial Land Fund Development Center reported on the progress of the Project on compensation, support, resettlement, and site clearance for upgrading and expanding DT. 769 road, former Thong Nhat and Long Thanh districts (now belonging to Dau Giay, Binh An, Long Thanh communes).

The project has a total investment of about 3,906 billion VND from the provincial budget (land use right auction source) implemented from 2024 - 2026.

The total land recovery area is about 135.5 hectares in 3 communes: Dau Giay, Binh An and Long Thanh.

The number of households expected to be resettled is about 996 households. Of which, Dau Giay commune is about 517 households expected to be resettled in the 15ha resettlement residential area in Hung Loc commune (now belonging to Dau Giay commune); Binh An and Long Thanh communes are about 479 households expected to be resettled in Long Phuoc resettlement area (now belonging to Long Phuoc commune), Long Duc, Long Duc expanded (now belonging to Binh An commune), Tan Hiep expanded (now belonging to Phuoc Thai commune).

It is expected to complete compensation and hand over the site to the Dong Nai Provincial Construction Investment Project Management Board from June 2026 - December 2026.

The project to upgrade and expand DT. 769 road is nearly 30 km long, starting point intersecting with National Highway 1 at Dau Giay intersection, Dau Giay commune, Dong Nai province; ending point intersecting with National Highway 51 at Loc An intersection, Long Thanh commune, Dong Nai province.

The project is divided into 4 implemented sections with a scale of 6 motorized lanes, 2 mixed lanes (sections 1, 3, 4) and 6 motorized lanes (section 2). The project has a total investment of nearly 5,900 billion VND. Of which, compensation, support, resettlement, and site clearance costs are more than 3,000 billion VND.

The project to upgrade and expand DT. 769 road is implemented to increase connectivity, shorten travel time from localities in the province and provinces in the Central Highlands and South Central Coast in general to Long Thanh airport. From there, meeting transportation needs, reducing traffic volume for National Highway 1, contributing to socio-economic development of localities with roads passing through in particular, Dong Nai province and the Southern Key Economic Region in general.

To connect localities in the province with Long Thanh airport, according to the plan, Dong Nai province will implement projects to upgrade, expand, and build 5 provincial roads including: 769, 769E, 773, 770B and the connecting road from Ma Da bridge to Ring Road 4 HCMC.

HÀ ANH CHIẾN
RELATED NEWS

Ho Chi Minh City and Dong Nai start construction of 2 metro lines connecting Long Thanh airport in 2026

|

Ho Chi Minh City and Dong Nai have just agreed to deploy two metro lines directly connecting Long Thanh airport, preparing to start construction in 2026.

Dong Nai to start construction of 3 large-scale industrial parks near Long Thanh airport

|

Dong Nai - Long Duc 3 Industrial Park, Bau Can - Tan Hiep and Xuan Que - Song Nhan are being accelerated to start construction in May 2026.

Lack of embankment land, tens of trillions VND resettlement project serving expressway delayed

|

Lang Son - Pac Luong resettlement area is currently behind schedule due to lack of embankment land.

My Wedding", "50 Years Later" and the vocal race between famous singers and AI

|

The success of the songs "My Wedding", "50 Years Later" as well as the explosion of AI singers poses challenges for Vietnamese singers.

Submitting to Ho Chi Minh City People's Council a plan to exempt bus tickets in April

|

Ho Chi Minh City - The plan to exempt buses for people is being finalized to submit to the Ho Chi Minh City People's Council for consideration and approval at the session scheduled to take place at the end of April.

Vietnam is about to have World Cup 2026 copyright?

|

Data from FIFA shows that VTV is recorded as the unit holding the broadcasting rights for the 2026 World Cup in Vietnam, although the station has not announced official information.

Iran still has half of its missile arsenal, thousands of UAVs

|

Iran's core military capabilities have not been neutralized despite more than a month of intense airstrikes by the US and Israel.

Midfielder Hoang Hen: Vegetarian diet helps me recover my physical condition

|

Midfielder Hoang Hen shared that he did not encounter any obstacles in the training and competition process when maintaining a vegetarian diet.

Ho Chi Minh City and Dong Nai start construction of 2 metro lines connecting Long Thanh airport in 2026

MINH QUÂN |

Ho Chi Minh City and Dong Nai have just agreed to deploy two metro lines directly connecting Long Thanh airport, preparing to start construction in 2026.

Dong Nai to start construction of 3 large-scale industrial parks near Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Long Duc 3 Industrial Park, Bau Can - Tan Hiep and Xuan Que - Song Nhan are being accelerated to start construction in May 2026.

Lack of embankment land, tens of trillions VND resettlement project serving expressway delayed

Khánh Linh |

Lang Son - Pac Luong resettlement area is currently behind schedule due to lack of embankment land.