Lack of embankment land, tens of trillions VND resettlement project serving expressway delayed

Khánh Linh |

Lang Son - Pac Luong resettlement area is currently behind schedule due to lack of embankment land.

The Pac Luong resettlement area project serving resettlement for the Dong Dang - Tra Linh expressway site clearance sub-project is being implemented in Trang Dinh commune, with a total investment of more than 75.1 billion VND from the state budget, implementation period 2024-2026.

The project invests in synchronous technical infrastructure for a resettlement area with a scale of 104 land plots, serving about 416 people.

The main items include ground leveling, 6 traffic routes more than 1.16 km long, water supply and drainage system - rainwater - wastewater, wastewater treatment station with a capacity of 100 m3/day and night, along with electricity, lighting and fire prevention and fighting systems.

Recorded in March, the ground of Pac Luong resettlement area has gradually shown its true form after more than 3 months of construction.

a
Pac Luong resettlement area has clearly shown its shape after 3 months of construction. Photo: Khanh Linh

At the construction site, the items of peeling off the organic soil layer have been completed, the stone embankment has also been completed, and many locations continue to have foundations and leveling to prepare for the technical infrastructure construction phase.

In terms of land, the project has completed the inventory of 51/51 households, recovered all 36,378.4 m2 of land and paid more than 10.98 billion VND in compensation, support, and resettlement through two phases.

Up to now, the investor said that the project no longer has site clearance problems.

However, the actual construction progress is still slow compared to the contract. The EC mixed package has an initial implementation time of 6 months, from June 23, 2025 to December 22, 2025, then was extended to June 2026.

a
Although not entangled in site clearance, the project is still behind schedule due to lack of embankment land. Photo: Khanh Linh

Talking to PV, Mr. Nguyen Manh Duc - Deputy Director of the Lang Son Provincial Construction Investment Project Management Board said that the project actually started construction from December 2, 2025.

To date, the value of the volume implemented has reached about 12.3 billion VND out of a total contract value adjusted by more than 44.24 billion VND.

Some items have achieved quite high progress such as the organic layer peeling work reaching 100%; the stone embankment item has been completed 100%; the roadbed embankment has reached about 48,000/50,799 m3, equivalent to 94.49%.

The contractor has also gathered materials for electricity and other technical infrastructure items. However, the investor assesses that the overall project is still behind schedule. However, the biggest bottleneck currently is the lack of embankment soil materials.

Previously, the project was allowed to take advantage of excess land from the Dong Dang - Tra Linh expressway to level. But at the time the expressway was under construction, the Pac Luong resettlement area did not have a clean ground to receive land.

By October 2025, when the expressway will basically complete the foundation excavation, most of the excess soil and rocks will be transported to temporary dumping yards, and the remaining volume will not be enough to serve the project," Mr. Duc said.

In addition, soil transportation also faces many obstacles. The embankment is located at Km38+800, but the road to the embankment is the only road, while many projects are being implemented at the same time, causing traffic conflicts, depending on the construction progress of the Dong Dang - Tra Linh route.

a
The project is taking advantage of the excess soil during the expressway construction process. Photo: Khanh Linh

The permitted time for soil transportation is currently extended to the end of the first quarter of 2026.

Also according to the leader of the Lang Son Provincial Project Management Board, currently the contractor has added more machinery and increased shifts.

In the first quarter of 2026, the project focuses on transporting embankment soil, completing the leveling of the resettlement area and constructing technical infrastructure.

The goal is to complete the entire project, accept and hand over the resettlement area to arrange resettlement for households no later than June 2026.

The project "Pac Luong village residential area" was approved by Lang Son Provincial People's Committee according to Decision No. 654 dated March 15, 2025.

The EC bidding package implementation consortium includes 8 contractors: Hoang Ha Lang Son Co., Ltd., Green Technology Solution Joint Stock Company, Lang Son Water Supply and Drainage Joint Stock Company, Le Quang Trading and Technical Services Joint Stock Company, Hung Phat LS Construction Investment One Member Limited Liability Company, Thanh An Lang Son Construction Investment Joint Stock Company, Thanh Nam Investment and Development Joint Stock Company, Tan Minh Construction and Trading One Member Limited Liability Company.

Khánh Linh
RELATED NEWS

8 units won the bid to build the resettlement area for the Dong Dang - Tra Linh expressway

|

Lang Son - 8 units have just won the bid to build a resettlement area for site clearance (GPMB) for the Dong Dang - Tra Linh Expressway in Trang Dinh district.

Lang Son poures more capital, expands land for Dong Dang - Tra Linh Expressway

|

Lang Son - The Provincial People's Committee has just adjusted the land acquisition area and total investment of two sub-projects for site clearance on the Dong Dang - Tra Linh expressway.

Mr. Nguyen The Phuoc elected Deputy Secretary of Lao Cai Provincial Party Committee

|

Lao Cai - Mr. Nguyen The Phuoc - Standing Vice Chairman of the Provincial People's Committee was elected to hold the position of Deputy Secretary of the Provincial Party Committee.

2 Senior Colonels, 1 Lieutenant Colonel of the Army receive new assignments

|

2 Senior Lieutenant Colonels, 1 Lieutenant Colonel have just been assigned the task of Deputy Attaché of National Defense, in charge of the Border Guard field.

Ministry of Education and Training awards certificates of merit to students who rushed into a fire to save people

|

Nguyen Le Tu - a student at Hanoi University of Science and Technology, who rushed into the fire that occurred in Linh Nam (Hanoi) - to save people was awarded a certificate of merit by the Ministry of Education and Training.

Hanoi requests leaders to overcome the situation of "talking a lot - doing little"

|

Hanoi - Each Party Committee member, leading and managing cadre, especially the head, must resolutely overcome the situation of "hot above - cold below", "talking a lot - doing little".

Gasoline and oil prices forecast to continue to decrease in the next operating session

|

According to current market developments, it is predicted that in the next operating period, gasoline and oil prices may continue to decrease.

Hanoi plans to reduce 35 public schools at commune and ward levels, keeping high schools the same

|

It is expected that in the period 2026-2027, Hanoi will maintain high schools under the Department, reducing 35 public schools under wards and communes.

Đường dân sinh tan hoang vì dự án tái định cư cao tốc Đồng Đăng - Trà Lĩnh

Khánh Linh |

Lạng Sơn - Việc triển khai thi công dự án khu tái định cư phục vụ cao tốc Đồng Đăng - Trà Lĩnh đã cày nát đường dân sinh, khiến người dân bức xúc.

8 units won the bid to build the resettlement area for the Dong Dang - Tra Linh expressway

Tô Công - Khánh Linh |

Lang Son - 8 units have just won the bid to build a resettlement area for site clearance (GPMB) for the Dong Dang - Tra Linh Expressway in Trang Dinh district.

Lang Son poures more capital, expands land for Dong Dang - Tra Linh Expressway

Khánh Linh |

Lang Son - The Provincial People's Committee has just adjusted the land acquisition area and total investment of two sub-projects for site clearance on the Dong Dang - Tra Linh expressway.