Removing bottlenecks in land origin verification, ensuring the progress of key projects

Hữu Long |

Khanh Hoa - The locality is focusing on removing bottlenecks at the stage of verifying land origin to implement key projects, ensuring accuracy and tightness.

On August 13, Nam Nha Trang Ward People's Committee is focusing on removing bottlenecks in compensation, support, and resettlement work, in order to accelerate the progress of site clearance for projects in the area.

Agencies and units are reporting on the progress of compensation, support, and resettlement for many projects.

For the Nha Trang City Mixed-Use Urban Area Project, as of August 6, 2026, the ward has inventoried 1,059/1,585 plots; verified the origin of land, appraised and held meetings to consider compensation plans for 196 plots.

The ward has issued decisions to recover land for 174 plots, accounting for more than 62% of the total area to be recovered.

The project to build Khanh Hoa Provincial General Hospital into a South Central Coast Regional Hospital has inventoried 199/290 plots; verified the origin of 23 plots and issued decisions to recover land for 1 plot.

For the Provincial Police Headquarters Project, 204/206 plots have been inventoried, the origin of land of 121 plots has been verified, and decisions on land recovery have been issued for 15 plots.

The Social Housing project for police officers and soldiers has inventoried 108/115 plots and verified the origin of 7 plots of land.

Meanwhile, the Provincial Fire and Rescue Police Command Center Project has inventoried 120/135 plots, verified the origin of 118 plots of land and issued decisions to recover land for 116 plots.

For the Tac River downstream renovation project - phase II, the ward has inventoried 134/143 plots.

Specifically, the Bac Hon Ong School, Training and Vocational Training Area Project has completed the inventory, verification of land origin, listing compensation and support plans; and at the same time approved plans for 275/325 plots.

Notably, the specialized working group to verify the origin of land of the ward, established on July 24, 2026, initially promoted efficiency, contributing to accelerating the progress of verifying the origin of land, serving site clearance for projects.

However, site clearance work still faces some difficulties and obstacles such as lack of human resources to develop compensation and support plans; coordination between agencies and units is sometimes not synchronized; the organization of people's meetings to inform about the situation and progress of project implementation is not regular.

Some cases of people arbitrarily pouring soil and leveling ponds also cause difficulties in determining compensation conditions. In addition, the land fund and infrastructure in resettlement areas are not complete.

Faced with the above situation, Mr. Nguyen Van Minh - Chairman of Nam Nha Trang Ward People's Committee - requested departments and agencies of the ward to promote digitization, centrally manage records, ensure that data is fully updated, unified, and convenient for searching, developing plans and monitoring implementation progress.

Chairman of Nam Nha Trang Ward People's Committee requested to focus on removing bottlenecks at the stage of verifying land origin, ensuring accuracy, tightness, and compliance with regulations; minimize the need to adjust the plan after it has been publicized to the people.

The specialized working group to verify the origin of land continues to promote its role, mobilizing sufficient professional forces and facilities to process dossiers quickly, accurately and objectively. For contents beyond authority, it is necessary to promptly summarize and report to competent authorities or request specialized agencies for guidance, avoiding prolonged problems.

Hữu Long
RELATED NEWS

Lang Son considers terminating contract for expressway rest stop project

|

Lang Son - The Huu Lung Rest Stop project contract was signed in September 2023, but after nearly three years, it is still necessary to review obligations, progress and termination conditions.

Groundbreaking ceremony for a 418 billion VND public housing project in Dong Thap

|

Dong Thap - The provincial electronic information portal has just updated information, this morning (August 12), the Provincial People's Committee held a groundbreaking ceremony for the provincial official housing project.

Russia launches massive attacks on fuel tanks and Ukrainian military cargo ships

|

Seaport infrastructure and waterway supply continue to be priority targets in Russia's campaign to weaken the logistics of the Ukrainian army.

New low pressure strengthens into Typhoon Nangka, forecast direction in the next 24 hours

|

Tropical storm Nangka formed from a low pressure area and is currently more than 2,000km north of the northern tip of Luzon Island, moving eastward.

Thanh Hoa faces pressure to compensate for the gap to grow by 11%

|

Thanh Hoa - GRDP in 6 months increased by 7.21%, while public investment slowed down, putting great pressure on the growth target of 11% in 2026.

Weather today August 13: Northern region continues to be intensely hot

|

Weather today August 13, Northern region hot sunny day, hot sunny in some places, especially Lai Chau and Dien Bien sunny day, hot sunny in some places.

Product matrix for treating erectile dysfunction with "complete cure" commitment

|

Faced with the "matrix" of erectile dysfunction treatment products on the market, doctors warn men not to arbitrarily use the product without examination.

Lang Son considers terminating contract for expressway rest stop project

Khánh Linh |

Lang Son - The Huu Lung Rest Stop project contract was signed in September 2023, but after nearly three years, it is still necessary to review obligations, progress and termination conditions.

Vướng mặt bằng ở 2 dự án đội vốn tại Hà Tĩnh

TRẦN TUẤN |

Hà Tĩnh - Hai tiểu dự án cải thiện cơ sở hạ tầng đô thị Thạch Hà và Hương Khê vẫn đang vướng mặt bằng dù đã được gia hạn tiến độ và điều chỉnh tăng vốn.

Groundbreaking ceremony for a 418 billion VND public housing project in Dong Thap

Phong Linh |

Dong Thap - The provincial electronic information portal has just updated information, this morning (August 12), the Provincial People's Committee held a groundbreaking ceremony for the provincial official housing project.