Dong Thap - My Tho social housing is required to ensure quality, safety, and aesthetics before being handed over to workers.

On July 9, Mr. Le Van Nghia - Vice President of the Vietnam General Confederation of Labor - and the working delegation inspected the actual investment project to build trade union facilities in My Tho Industrial Park, Trung An Industrial Cluster (Trung An ward, Dong Thap province), including the My Tho social housing item for workers.

According to the report of the Project Commander of the Joint Venture of Corporation 319 Ministry of National Defense - Dai A Chau - Tan Phat - Viet Chao, the project was started on July 26, 2025, with a total construction time of 725 days.

To date, the project has been implemented for 343 days, reaching about 47.31% of the contract progress and ensuring the overall approved progress. Many structural items, construction, plastering, and technical systems have been deployed simultaneously, and some tasks have exceeded the plan.

The supervision consulting unit said that the construction site maintains sufficient manpower and machinery, ensuring requirements on material quality, labor safety, environmental sanitation and fire prevention. At the same time, it is proposed that the contractor continue to supplement manpower and equipment, proactively source materials, and closely coordinate between units to accelerate slow-progressing items and maintain the overall progress.

Một đơn vị thi công tại Dự án nhà ở xã hội Công đoàn báo cáo tiến độ thực hiện công trình với đoàn công tác Tổng LĐLĐ Việt Nam. Ảnh: Hoàng Lộc
A construction unit at the Trade Union social housing project reports on the project implementation progress to the working delegation of the Vietnam General Confederation of Labor. Photo: Hoang Loc

Inspecting the actual construction, Mr. Le Van Nghia acknowledged the efforts of the investor, the supervision consulting unit and the contractors during the construction process. He requested the units to continue to organize synchronous construction between items, not focusing on individual parts, and at the same time strictly control technical and artistic quality before acceptance.

The Vice President of the Vietnam General Confederation of Labor noted that the project needs to be monitored after completion to assess quality before handover. Contractors must ensure labor safety, especially in the elevated construction area, install elevators, electrical systems; maintain hygiene in all completed areas and carefully review interior items such as sanitary equipment, kitchen cabinets, apartment doors, stairs.

Emphasizing the social security significance of the project, Mr. Le Van Nghia requested the construction units to determine that this is a project for workers, "must build social housing here like their own home", so that each apartment when handed over ensures quality, safety and meets the expectations of union members and workers.

HOÀNG LỘC
RELATED NEWS

Workers expect to settle down as Giao Long social housing is gradually being completed

|

Vinh Long - Giao Long Trade Union Social Housing Project is gradually being completed, bringing joy and hope for settlement for workers in Giao Long Industrial Park.

Starting construction of trade union social housing project in Dong Thap province

|

Dong Thap - On the morning of July 26, in Dong Thap, the groundbreaking ceremony for the trade union social housing project under the trade union institution construction project in My Tho Industrial Park, Trung An Industrial Cluster took place.

Tien Giang spends more than 15 hectares to build social housing in the new urban area of Dong Bac My Tho

|

Tien Giang - The Provincial People's Committee has just issued Decision No. 1412/QD-UBND, approving the investment policy of the Northeast Urban Area Project of My Tho city.

Continuous landslides on National Highway 6, mobilizing manpower and machinery to urgently clear the road

|

Heavy rain due to the circulation of storm No. 1 caused many landslides on National Highway 6 through Dien Bien province.

3,300 billion VND road tunnel project across Hoang Lien pass faces difficulties

|

Lai Chau - The road tunnel project through Hoang Lien Pass is facing difficulties.

Urgently overcome the dike breach incident, black wastewater flowing to Sam Son beach

|

Thanh Hoa - After the dike breach incident occurred, causing black water to flow rushing into the Sam Son beach area, functional forces urgently overcame it.

Not arranging simultaneously 705 communes and wards that do not meet standards

|

According to the Ministry of Home Affairs, the arrangement of 705 communes and wards that do not meet standards will not be implemented simultaneously but based on the conditions and characteristics of each locality.

Workers expect to settle down as Giao Long social housing is gradually being completed

HOÀNG LỘC |

Vinh Long - Giao Long Trade Union Social Housing Project is gradually being completed, bringing joy and hope for settlement for workers in Giao Long Industrial Park.

Starting construction of trade union social housing project in Dong Thap province

Phong Linh |

Dong Thap - On the morning of July 26, in Dong Thap, the groundbreaking ceremony for the trade union social housing project under the trade union institution construction project in My Tho Industrial Park, Trung An Industrial Cluster took place.

Tien Giang spends more than 15 hectares to build social housing in the new urban area of Dong Bac My Tho

Đoàn Hưng |

Tien Giang - The Provincial People's Committee has just issued Decision No. 1412/QD-UBND, approving the investment policy of the Northeast Urban Area Project of My Tho city.