Speedway construction at the construction site of a multi-level boarding school in Ha Tinh

TRẦN TUẤN |

Ha Tinh - Two inter-level boarding primary and secondary schools in Ha Tinh started construction in 2025 and are being accelerated by contractors to be completed before August 30.

On July 22, according to a reporter from Lao Dong Newspaper, at the construction site of Huong Khe Inter-level Boarding Primary and Secondary School (in Huong Khe commune), the contractor is focusing maximum manpower on construction.

In which, at 2 rows of classrooms in the 2-story building block, paint has been almost finished, and the installation of doors, air conditioners, and light bulbs is being carried out.

Điều hòa đang lắp trong dãy phòng học 2 tầng. Ảnh: Trần Tuấn
Air conditioning is being installed in a 2-story classroom building. Photo: Tran Tuan
Nhóm thợ đang lắp điều hòa. Ảnh: Trần Tuấn
Workers are installing air conditioners. Photo: Tran Tuan
Đã lắp cửa tại khối dãy phòng học 2 tầng. Ảnh: Trần Tuấn
Doors have been installed at the 2-story classroom block. Photo: Tran Tuan

At 3 rows of classrooms in the 3-story building block that has been roughly built, groups of workers are focusing on plastering. At this building block, there is also a part of painters who are proceeding to remove roughness to paint the walls.

In the yard area, many groups of workers are focusing on paving the brick floor. The very urgent construction atmosphere is clearly visible at the construction site.

Mr. Le Khac Tien (51 years old, residing in Huong Khe commune, Ha Tinh province) who is a construction worker at this construction site said that it is hot, so in the morning the brothers start working from 6 am to 10 am to rest, and in the afternoon from 2 pm to 6 pm.

The construction site is under pressure from the final stage of progress, so we have to work continuously," Mr. Tien shared.

As a local resident hired to construct, Mr. Tien is paid 500,000 VND per day by the contractor.

Khối dãy nhà 3 tầng đã xây xong phần thô. Ảnh: Trần Tuấn
The 3-story building block has completed the rough construction. Photo: Tran Tuan
Nhóm thợ đang da trát ở dãy nhà 3 tầng. Ảnh: Trần Tuấn
The group of workers is plastering in a 3-story building. Photo: Tran Tuan

Mr. Le Van Phong - Commander of the construction site of Huong Khe Inter-level Boarding Primary and Secondary School of Construction Mechanical Engineering Joint Stock Company under Hanoi Construction Corporation said that so far, the 2-story classroom block has been basically completed.

In the 3-story classroom block, the contractor is focusing on plastering, then painting and installing equipment.

According to Mr. Le Van Phong, currently there are about 200 workers gathering at the construction site every day to accelerate the progress of the finishing phase to complete and hand over before August 30th.

Nhóm thợ đang lát nền gạch ở sân trường. Ảnh: Trần Tuấn
Workers are paving the brick floor in the schoolyard. Photo: Tran Tuan

The Huong Khe Inter-level Boarding Primary and Secondary School project is built in Phu Gia village, Huong Khe commune on an area of more than 5 hectares, with a construction cost of about 160 billion VND.

The project started on November 9, 2025, invested by the Ha Tinh Provincial Civil and Infrastructure Construction Investment Project Management Board. According to the progress, the project must be completed and handed over before August 30, 2026.

On July 20, Deputy Prime Minister Le Tien Chau signed Official Dispatch No. 50 on accelerating the progress and completion of the construction of Inter-level Boarding Primary and Secondary Schools phase 1 nationwide (starting in 2025) to be inaugurated simultaneously on September 5, 2026, and put into operation and use right from the beginning of the new school year 2026-2027.

On July 22, Mr. Pham Anh Hao - Chairman of Son Kim 1 Commune People's Committee (Ha Tinh) said that currently the contractor is focusing on accelerating the construction progress of Son Kim 1 Inter-level Primary - Secondary Boarding School to complete before August 30.

This school was started on November 9, 2025 in Trung village on an area of more than 5 hectares with a scale of 40 classrooms for more than 1,300 students. The construction investment cost is about 140 billion VND.

According to the schedule, this project must also be completed and handed over before August 30, 2026 to be put into use right at the beginning of the new school year 2026-2027.

TRẦN TUẤN
RELATED NEWS

Lao Cai clarifies obstacles, soon resumes unfinished rural road construction

|

Lao Cai - Before reflecting on the slow progress of rural roads, Van Ban Commune People's Committee will work with relevant parties to agree on a plan to continue construction.

Strengthen construction forces for boarding schools in border areas to be on time for the new school year

|

Lam Dong - Military Region 7 will strengthen its forces to support the province in accelerating the construction to complete the inter-level boarding school in the border area in time for the new school year.

The shape of the Ho Chi Minh City - Long Thanh expressway expansion project after 11 months of construction

|

Ho Chi Minh City - Package XL01, belonging to the project to expand the Ho Chi Minh City - Long Thanh expressway, reaching 62% of output, is accelerating, determined to reach the finish line at the end of 2026.

Fire on 19th floor apartment building in Hanoi

|

Hanoi - Apartment on the 19th floor of an apartment building on Tam Trinh street caught fire fiercely on the afternoon of July 22.

New secret to help people proactively avoid traffic congestion points in Hanoi

|

Hanoi - The 36 LED system will display traffic conditions in real time, helping road users proactively avoid congestion points.

Tricks of a fake perfume production line have just been dismantled

|

Thanh Hoa - A perfume production line fakes many booths on e-commerce platforms, advertising them as smuggled goods, decanted goods to deceive consumers.

Mr. Mai Xuan Liem is assigned to be in charge of activities of Thanh Hoa Provincial People's Committee

|

Thanh Hoa - After Mr. Nguyen Hoai Anh was transferred and received a new job, Mr. Mai Xuan Liem was assigned to be in charge of the Provincial People's Committee.

Lao Cai clarifies obstacles, soon resumes unfinished rural road construction

Đinh Đại |

Lao Cai - Before reflecting on the slow progress of rural roads, Van Ban Commune People's Committee will work with relevant parties to agree on a plan to continue construction.

Strengthen construction forces for boarding schools in border areas to be on time for the new school year

Duy Tuấn |

Lam Dong - Military Region 7 will strengthen its forces to support the province in accelerating the construction to complete the inter-level boarding school in the border area in time for the new school year.

The shape of the Ho Chi Minh City - Long Thanh expressway expansion project after 11 months of construction

Anh Tú |

Ho Chi Minh City - Package XL01, belonging to the project to expand the Ho Chi Minh City - Long Thanh expressway, reaching 62% of output, is accelerating, determined to reach the finish line at the end of 2026.