Forced land acquisition and return of arterial roads in Hanoi

HỮU CHÁNH |

Hanoi - Long Bien District People's Committee has completed forced land acquisition to complete the infrastructure of the Thanh Tri Bridge - National Highway 5 intersection project after many years of delay.

Labor's record on the afternoon of August 4 shows that the People's Committee of Long Bien district (Hanoi) has completed the enforcement of land recovery to complete the infrastructure of the project "Investment to adjust the intersection between Thanh Tri bridge project and National Highway". 5".

These are the last 3 households in the project area who have delayed handing over the site for the past 10 years to return the current state of Highway 5 according to regulations.

a
Households in the red zone have not handed over their land for many years to return the current state of Highway 5 (Hanoi). Photo taken on July 21.

In 2013, the Ministry of Transport approved the investment project to adjust the intersection between Thanh Tri bridge project and National Highway 5 with a total investment of more than 1,700 billion VND, of which site clearance cost is 261 billion VND. .

The project has the goal of creating convenient traffic connections between Hanoi's Ring Road 3 and National Highway 5; Improve the efficiency of exploiting relevant main roads in the area: Ring Road 3 - Thanh Tri Bridge, National Highway 1 section Hanoi - Lang Son, National Highway 5 section Hanoi - Hai Phong.

By October 2015, the project was completed, 6 months ahead of schedule. The completed rosette intersection contributes to improving transport capacity, eliminating "black spots" of congestion at the eastern gateway of Hanoi Capital.

According to Long Bien District Land Fund Development Center, to implement the project, 101,403 square meters of land in Thach Ban ward must be recovered, involving 223 households, including 31 households with residential land and 192 households with agricultural land.

After being assigned the task by the City People's Committee, Long Bien District People's Committee directed functional branches and Thach Ban Ward People's Committee to organize and carry out site clearance work.

Most households agreed to hand over the premises and move to a new resettlement place. By July 2024, there were still 3 households with 22 people who had not yet handed over the premises.

a
Three households delayed handing over the land, causing National Highway 5 to narrow, posing a potential risk of traffic accidents. Photo taken on July 21

Regarding the above issue, Mr. Bui Tri Duc - Vice Chairman of the People's Committee of Thach Ban ward (Long Bien district) - said that policies and regimes related to site clearance and resettlement support have been applied. in accordance with the law.

However, the above 3 households still did not comply even though the People's Committee of Long Bien District and the District Land Fund Development Center had repeatedly coordinated with the People's Committee of Thach Ban Ward to organize direct dialogues, as well as respond in writing.

The families' inaction and failure to hand over land has led to the unfinished location of National Highway 5, creating a "bottleneck". Highway 5 passing through this area is narrowed, risking becoming a "black spot" for accidents, causing public anger.

Faced with the above reality, the People's Committee of Long Bien District has issued a decision to enforce land recovery according to its authority, to ensure the time to hand over the site to the construction unit to complete the infrastructure of the Thanh Tri bridge project on schedule. Ensuring urban aesthetics and traffic safety for National Highway 5.

By the end of July 2024, Long Bien District People's Committee had forced land recovery and site clearance to complete the infrastructure of the Thanh Tri Bridge - National Highway 5 project in accordance with the legal process.

a
Recorded by Labor on August 4, Long Bien district government has completed site clearance for 3 households in the Project area to adjust the intersection of National Highway 5 - Thanh Tri bridge. Photo: Huu Chanh
a
A
Barriers were erected at the site clearance enforcement area. Photo: Huu Chanh
A
The works have been dismantled by the authorities according to regulations. Photo: Huu Chanh
A
The enforcement of site clearance to complete the infrastructure of the Thanh Tri Bridge - National Highway 5 project is carried out in accordance with the legal process. Photo: Huu Chanh
A
To date, Long Bien district has completed the forced clearance of the three households mentioned above, ensuring urban aesthetics and traffic safety for National Highway 5. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

Hà Nội dồn lực triển khai dự án mở rộng đường lên 10 làn xe

HỮU CHÁNH |

Hà Nội đang tập trung nguồn lực đẩy nhanh tiến độ giải phóng mặt bằng để thi công mở rộng Quốc lộ 6 dài 21,7km, mức đầu tư 8.000 tỉ đồng.

Sắp hoàn thành mở rộng đường 1,1km ở trung tâm Hà Nội

Hữu Chánh |

Hà Nội - Dự án nâng cấp đường Xuân Diệu dài 1,1km, tổng mức đầu tư gần 400 tỉ đồng đang được gấp rút thi công hoàn thiện sau nhiều năm chậm trễ.

Tháng 10, Hà Nội thi công mở rộng đường huyết mạch lên 40m

HỮU CHÁNH |

Hà Nội - Sau khi hoàn thành giải phóng mặt bằng vào tháng 10.2024, quận Hoàng Mai sẽ triển khai thi công mở rộng đường Tam Trinh lên 40m, 6 làn xe.

Tên lửa phóng loạt Nga san phẳng cứ điểm của Ukraina

Song Minh |

Quân đội Nga sử dụng hệ thống tên lửa phóng loạt MLRS Uragan xóa sổ cứ điểm của Ukraina ở Donetsk.

Khách Việt lặn biển ngắm xác máy bay rơi ở Philippines

Chí Long |

Panglao (Bohol, Philippines) được mệnh danh là "Thiên đường của thợ lặn", với những trải nghiệm thú vị có một không hai như lặn ngắm xác máy bay đắm.

Giá vàng hôm nay 16.10: Đột ngột tăng cả triệu đồng/lượng

Khương Duy |

Giá vàng hôm nay 16.10: Thị trường vàng đồng loạt tăng ở cả thị trường trong nước và thế giới. Vàng nhẫn trơn chạm mốc 84 triệu đồng/lượng.

Hộ dân tự tháo dỡ khi có thông báo cưỡng chế để làm cao tốc

CÔNG SÁNG |

Quảng Bình - Các hộ dân tại thị trấn Nông trường Lệ Ninh đã đồng ý tự tháo dỡ sau khi có thông báo cưỡng chế.

Ông Trump nhún nhảy 40 phút trong cuộc vận động tranh cử

Song Minh |

Cựu Tổng thống Donald Trump kết thúc cuộc vận động tranh cử ở Pennsylvania bằng cách nhún nhảy theo nhạc suốt 40 phút.

Hà Nội dồn lực triển khai dự án mở rộng đường lên 10 làn xe

HỮU CHÁNH |

Hà Nội đang tập trung nguồn lực đẩy nhanh tiến độ giải phóng mặt bằng để thi công mở rộng Quốc lộ 6 dài 21,7km, mức đầu tư 8.000 tỉ đồng.

Sắp hoàn thành mở rộng đường 1,1km ở trung tâm Hà Nội

Hữu Chánh |

Hà Nội - Dự án nâng cấp đường Xuân Diệu dài 1,1km, tổng mức đầu tư gần 400 tỉ đồng đang được gấp rút thi công hoàn thiện sau nhiều năm chậm trễ.

Tháng 10, Hà Nội thi công mở rộng đường huyết mạch lên 40m

HỮU CHÁNH |

Hà Nội - Sau khi hoàn thành giải phóng mặt bằng vào tháng 10.2024, quận Hoàng Mai sẽ triển khai thi công mở rộng đường Tam Trinh lên 40m, 6 làn xe.