Project to open 40m wide road in Hanoi after 5 months of construction

HỮU CHÁNH |

Hanoi - The assigned land has caused many difficulties for the contractor in implementing the construction of the 3.5km Tam Trinh road expansion, with a capital of nearly 3,400 billion VND.

Since the end of July 2024, after Hoang Mai district (Hanoi) handed over a part of the cleared site, the contractor of Truong Son 97 branch (Truong Son Construction Corporation) has mobilized human resources and machinery to carry out the construction of expanding Tam Trinh road.

The project has a total length of 3.5km, the cross-section is expanded according to the planning to 40m. The starting point connects with Minh Khai Street, the end point intersects with Ring Road 3. The total investment capital of the project is nearly 3,400 billion VND.

The total land acquisition area (after boundary adjustment) is about 54,009m2, involving about 1,590 households and 20 organizations, located in the 3 wards of Mai Dong, Hoang Van Thu and Yen So.

According to Mr. Nguyen Trong Vinh - representative of the contractor of Truong Son 97 branch, the Tam Trinh road expansion project is divided into 2 construction phases.

Phase 1 will be constructed on the left side of the route in sections where the ground is already cleared. Phase 2 will be constructed on the existing section of Tam Trinh Street.

Mr. Nguyen Trong Vinh said that up to now, the contractor has only been able to construct about 800m, divided into 4 sections, in a rolling manner.

In the cleared sections, the contractor has constructed the final base layer (aggregate layer) and cannot deploy the asphalt concrete layer because some electric poles are still within the construction roadway.

While waiting for the handover of the next sections of the site, the contractor is implementing items that do not depend on the site.

After about 5 months of implementation, the construction output to date is nearly 30/294 billion VND of the contract value.

Regarding the difficulties in implementing the project, Mr. Vinh said that because this is an important route in Hoang Mai district, the traffic volume of people and vehicles is large. This requires the contractor to both construct and ensure traffic.

The assigned site is still uneven and not continuous, so the contractor has not yet maximized the efficiency of machinery and equipment.

"The handover of the site at many times only reached 40m/section while for effective construction and cost optimization, the continuous site length needed to be over 100m" - Mr. Vinh said.

According to the contractor representative, the construction period of this project is 650 days, from July 31, 2024, the unit is determined to stick to the schedule. If the entire site is received in the first quarter of 2025, the project will "reach the finish line" in February 2026.

s
A section of cleared land from the Kim Nguu River bridge intersection to alley 587 Tam Trinh is being expanded by the contractor. Photo: Huu Chanh
s
The construction site area is fenced with corrugated iron to serve the construction, ensuring traffic safety. Photo: Huu Chanh
He thong dien, vien thong den nay van chua duoc di doi. Anh: Huu Chanh
The electricity and telecommunications systems on the route have not been relocated yet. Photo: Huu Chanh
Mat bang phia trai tuyen duoc giao dut doan, anh huong den viec thi cong cua nha thau. Anh: Huu Chanh
The left side of the route is broken, affecting the contractor's construction. Photo: Huu Chanh
s
Many constructions have not yet been cleared to hand over the site for the project. Photo: Huu Chanh
May moc thi cong hang muc bo ke doc song Kim Nguu. Anh: Huu Chanh
Machinery and workers constructing the retaining wall along the Kim Nguu River. Photo: Huu Chanh
Nhieu doan tuong chan phia song Kim Nguu (ben phai tuyen) duoc thi cong hoan thanh. Anh: Huu Chanh
Construction of many sections of the Kim Nguu River retaining wall has been completed. Photo: Huu Chanh
a
The contractor is implementing the sidewalk project on the right side of the road. Photo: Huu Chanh
a
This is the item with the best progress in the whole project. Photo: Huu Chanh
a
Tam Trinh Street is narrow and often congested. After being expanded, it will have a cross-section of 40m, accommodating 6 lanes. According to the plan, the project will be completed in February 2026 but depends largely on site clearance. Photo: Huu Chanh
Phia chinh quyen quan Hoang Mai cho biet, se phan dau hoan thanh cong tac giai phong du an mo rong duong Tam Trinh vao dau nam 2025. Anh: Huu Chanh
Hoang Mai district authorities said they will strive to complete site clearance for the Tam Trinh road expansion project by early 2025. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

The first locality to hand over full land for Hanoi Ring Road 4 project

|

Of the 7 districts in Hanoi that Ring Road 4 passes through, only one locality has handed over enough land for the project.

27-span flyover on Hanoi's Ring Road 4 to be completed in 2025

|

Hanoi - It is expected that by the second quarter of 2025, the North-South railway overpass, nearly 590m long, with 27 spans (part of the Ring Road 4 parallel road project through Me Linh) will be completed.

Review of Xuan Son's 2 goals in the Vietnam vs Thailand match

|

Striker Nguyen Xuan Son scored a double in the match between Vietnam and Thailand, the first leg of the 2024 ASEAN Cup final. Watch the 2024 ASEAN Championship Mitsubishi Electric Cup live and in full on FPT Play, at: http://fptplay.vn.

Reward for driver who stopped couple from beating someone on the street

|

Ho Chi Minh City - District 1 police have rewarded Mr. Ha Huu Vinh (a technology car driver) for his brave action in stopping a man and a woman from beating someone on the street.

More than 100 taxi drivers in Ca Mau stop protesting the company

|

Ca Mau - More than 100 drivers of an electric taxi company stopped working after the director banged on the table and said "disband", the company has spoken up to explain.

Meeting my first love after 17 years at the class reunion (Part 1)

|

Hour 9 - Two people who were each other's first loves meet again after 17 years at a class reunion. What will happen to them?

647m of Nhon - Hanoi Railway Station urban railway tunnel has been drilled

|

Hanoi – The Urban Railway Management Board (MRB) said that the Nhon – Hanoi Railway Station urban railway project has reached 80.32% of the overall progress.

Approval of Ho Chi Minh City planning

|

The Prime Minister has just signed Decision No. 1711/QD-TTg approving the Ho Chi Minh City Planning for the 2021-2030 period, with a vision to 2050.

The first locality to hand over full land for Hanoi Ring Road 4 project

HỮU CHÁNH |

Of the 7 districts in Hanoi that Ring Road 4 passes through, only one locality has handed over enough land for the project.

27-span flyover on Hanoi's Ring Road 4 to be completed in 2025

NHÓM PV |

Hanoi - It is expected that by the second quarter of 2025, the North-South railway overpass, nearly 590m long, with 27 spans (part of the Ring Road 4 parallel road project through Me Linh) will be completed.

Xe tải bốc cháy ngùn ngụt trên Vành đai 3, ùn tắc nhiều km

HỮU CHÁNH |

Hà Nội - Xe tải đang lưu thông trên đường cao tốc Vành đai 3 hướng Linh Đàm - Mỹ Đình bất ngờ bốc cháy, ùn tắc kéo dài trên tuyến.