Hanoi starts construction, completes a series of traffic projects in 2025

|

Hanoi will complete the Southern Axis Road, Ring Road 1, Hoang Cau - Voi Phuc section and is expected to start construction of 3 bridges across the Red River in 2025.

Many routes are about to reach the finish line

The investment project to build the southern axis road of Ha Tay (now Hanoi) is over 41km long, started in April 2008 with a total construction cost of over VND6,000 billion.

By 2018, the project had put into operation 18.5km from Ha Dong to the end of Thanh Oai district. The remaining 23km has not been completed, including 14km in Ung Hoa district and 9km in Phu Xuyen district.

Duong truc phia Nam doan qua huyen Phu Xuyen (Ha Noi) dang duoc thi cong xay dung. Anh: Huu Chanh
The Southern Axis Road section through Phu Xuyen District (Hanoi) is under construction. Photo: Huu Chanh

According to the Hanoi Department of Construction, with 23km of the project, 20km of site clearance (GPMB) has been completed; the remaining 3km (mainly in Ung Hoa district) is facing difficulties related to 23 resettlement households.

Ung Hoa District People's Committee said that with the area of 2,528.4m2 of residential land of 23 households in Tram Long commune subject to recovery and needing to be resettled, it is being urgently completed.

Ung Hoa district strives to complete site clearance (GPMB) in the first quarter, hand over 100% of the site in the second quarter of 2025 and complete the entire route in 2025 according to the roadmap committed to the city.

In the city center, the project to build Ring Road 1, Hoang Cau - Voi Phuc section (in Dong Da and Ba Dinh districts) is 2,274m long, with a cross-section of 50m, which has been delayed for many years.

The investment level of phase 1 of the project is more than VND 7,211 billion. Of which, the construction cost is 627 billion VND; the site clearance cost is more than 5,818 billion VND, from the city budget.

Vanh dai 1 doan Hoang Cau - Voi Phuc nhieu nam chua the mo rong do vuong GPMB. Anh: Ngoc Thuy
Ring Road 1, Hoang Cau - Voi Phuc section, has not been able to be expanded for many years due to land acquisition problems. Photo: Ngoc Thuy

The Hanoi Civil Works Construction Investment Project Management Board (investor) said that the site clearance process encountered many difficulties due to people's lack of coordination, failure to confirm land origin, and failure to confirm boundaries. Some households have even received money but have not yet handed over the site... leading to project delays.

The Project Management Board has coordinated with the People's Committees of Dong Da District and Ba Dinh District to report to the city and propose solutions.

It is expected that in the first quarter of 2025, Ba Dinh District will complete site clearance and in the second quarter of 2025, Dong Da District will also complete site clearance. According to the schedule, the project will be completed in 2025.

In 2025, a number of projects in the area have been delayed for many years, such as the 3.5 Ring Road section through Hoai Duc district, the intersection of Provincial Road 70 - Pham Tu Street (Thanh Tri district) will also be completed.

Starting construction of 3 bridges across the Red River

According to the conclusion and direction of Chairman of Hanoi People's Committee Tran Sy Thanh at the recent meeting to listen to reports on the implementation plan for a number of investment projects to build bridges across the Red River, the city leaders agreed to start construction of Tu Lien Bridge on the occasion of May 19. After that, the city continued to start construction of Tran Hung Dao bridge.

The Chairman of the City People's Committee assigned the Department of Construction to preside over and coordinate with relevant units to complete the detailed plan to ensure the above progress.

Phoi canh cau Tu Lien noi Tay Ho voi Dong Anh. Anh: Don vi thiet ke
Perspective of Tu Lien Bridge connecting Tay Ho with Dong Anh. Photo: Design Unit

Tu Lien Bridge and the road at both ends of the bridge from Nghi Tam intersection to Truong Sa intersection with a length of about 5.15km. The project is located in Tay Ho, Long Bien districts and Dong Anh district.

The investment project to build Tu Lien Bridge and the approach roads at both ends of the bridge has a total investment of VND 20,171 billion, the construction period is about 30 months.

Tran Hung Dao Bridge is about 5.6km long, starting at Tran Hung Dao - Tran Thanh Tong Street (Hoan Kiem District), ending at Vu Duc Thuan Street (Long Bien District).

The Hanoi People's Committee plans to have a total investment of about VND15,967 billion to build Tran Hung Dao Bridge. The project implementation period is from 2025-2027.

Cau Tran Hung Dao khi hoan thanh. Anh: Don vi thiet ke
Tran Hung Dao Bridge when completed. Photo: Design Unit

For the Ngoc Hoi Bridge and approach roads construction investment project, it is expected to be submitted to the City People's Council for decision on investment policy at the March 2025 meeting of the City People's Council.

The total length of Ngoc Hoi Bridge (located on Hanoi's Ring Road 3.5) and the approach roads at both ends of the bridge is about 7.5km.

Hanoi plans a total investment of about 11,844 billion VND, from the city and central budgets, to be implemented in the period of 2025-2030.

RELATED NEWS

Unexpected risks of holding many "winter- sleeping" accounts

|

The fee is from 5,000 VND - 22,000 VND/month if the account is only "opened".

VinFuture main prize is the project with a large-scale influence on the global population

|

On the evening of December 5, the VinFuture 2025 Award Ceremony - the focal event of VinFuture Science and Technology Week 2025, will take place.

Ho Chi Minh City plans to build Can Gio Bridge worth over VND13,200 billion, starting construction in 2027

|

HCMC - The Can Gio bridge project has a total length of 6.3 km, a total of more than 13,200 billion VND under the BT contract, expected to start construction in 2027, replacing Binh Khanh ferry.

Ambulances transferred to the hospital hit a passenger bus, the patient died on the way to Ho Chi Minh City

|

Lam Dong - An ambulance took a patient to Ho Chi Minh City when he had an accident on the highway. The patient was transferred to another hospital by another vehicle but died.

Resuming search for MH370, data reveals unusual scenario

|

On December 4, Malaysia announced that marine survey company Ocean Infinity will begin searching for MH370 from December 30, with a non-continuous 55-day period.

Delegates feel heartbroken when seeing students showing off their skills and being struggled by exam pressure

|

National Assembly deputies felt heartbroken when talking about the pressure of taking the exam for students who are only 15 years old.

Khanh Hoa Trade Union represents lawsuit to collect unpaid wages and insurance for workers

|

Khanh Hoa - After a long period of being owed wages and social insurance by enterprises, many employees of Mai Linh Nha Trang Company Limited have authorized the Trade Union to file a lawsuit.

Witness reports the incident of a teacher fighting with a principal at a party on November 20

|

Lao Cai - Giang A Pao village elders affirmed that they only tried to stop them but did not participate in fights with principals or teachers.

Hanoi reclaims land from nearly 1,300 households to open a 50-60m wide road

HỮU CHÁNH |

Hanoi - Ha Dong District plans to reclaim land from 1,266 households and individuals to expand nearly 6km of National Highway 6 through the area.

The project to open a 60m wide road in Hanoi is facing major obstacles

HỮU CHÁNH |

Hanoi - Difficulties in site clearance are hindering the progress of the project to expand National Highway 6 to a length of more than 21km, with an investment capital of VND 8,100 billion.

For more than 10 years, it has not been possible to expand the arterial road in Hanoi

HỮU CHÁNH |

Hanoi - The project to upgrade and expand Linh Nam road had an investment policy more than 10 years ago but has not been implemented yet due to land clearance problems.