Hanoi is about to open two 6-lane roads with a capital of over 1,200 billion

HỮU CHÁNH |

Hanoi - The Le Quang Dao extended road project and Thanh Oai economic axis road, with a capital of more than 1,200 billion VND, are in the "final stage", expected to be completed by the end of 2024.

In October 2022, Hanoi started the investment project to build the extended Le Quang Dao road with a length of 2.6km, starting at the intersection of Le Quang Dao - Thang Long Avenue (Nam Tu Liem district), ending at Duong Noi urban area (Ha Dong district).

The project has a total investment of more than 700 billion VND, of which site clearance costs are more than 163 billion VND, construction and installation costs are more than 542 billion VND and some other costs.

The route meets inter-regional road standards, with a design speed of 60km/h. The typical cross-section of the road is 40m with 6 lanes, the section connecting to Thang Long Avenue (about 110m long) has a cross-section of 100m.

According to the Nam Tu Liem District Construction Investment Project Management Board, the contract to complete this project will be signed in June 2025.

The investor said that if the weather is favorable and construction is guaranteed, the project is expected to be completed in December 2024, 6 months earlier than the contract.

Nearly 20km away, the Thanh Oai district economic development axis road project with a total investment of nearly 525 billion VND is considered a model of breakthrough thinking, creating a new axis road for even development among localities.

Of the total investment cost, construction cost is nearly 283 billion VND; compensation, support and resettlement cost is about 174.5 billion VND and some other costs.

The 6.5km long route passes through 4 communes including Thanh Thuy, Thanh Van, Tam Hung and Kim Bai town.

The cross-section of the route is divided into 2 sections, including: The section outside the urban area of ​​Kim Bai town has a cross-section of 23m, the section inside has a cross-section of 25m, meeting 6 lanes.

Currently, the project has completed about 90% of the work. At the project site, the contractor is mobilizing maximum machinery, workers, and engineers to speed up the construction progress of the remaining stages, bringing the project to the finish line in 2024.

Du an duong Le Quang Dao keo dai doan khop noi voi Dai lo Thang Long (dai khoang 110m) co be rong mat cat ngang 100m. Anh: Huu Chanh
The Le Quang Dao Street extension project connecting to Thang Long Avenue (about 110m long) has a cross-section width of 100m. Photo: Huu Chanh
a
Currently, the nearly 1km long section from Thang Long Avenue intersection to Dai Linh Street has basically completed the main items. Photo: Huu Chanh
a
The green tree system, lighting,... on this section of the route have been completed by the contractor. Photo: Huu Chanh
a
The section from Dai Linh Street to the end of the route is being focused on by contractors. Photo: Huu Chanh
a
Machines for treating weak ground and spreading crushed stone on the construction site. Photo: Huu Chanh
a
Some sections are being paved with sidewalk stones. Photo: Huu Chanh
a
The 6-lane route is expected to be completed by the end of 2024, helping to shorten travel time between Nam Tu Liem and Ha Dong districts, reducing traffic pressure on many routes in the area. Photo: Huu Chanh
Du an duong truc kinh te Thanh Oai co diem dau tai nut giao duong tinh 429. Anh: Huu Chanh
The Thanh Oai Economic Development Axis Road Project (Hanoi) starts at the intersection of Provincial Road 427 (Thanh Thuy Commune). Photo: Huu Chanh
A
Currently, the section from the beginning of the route to Yen Coc Canal Bridge, about 4km long, has basically completed the main items with a cross-section of 23m, 6 lanes. Photo: Huu Chanh
A
This is a project to celebrate the 70th anniversary of Thanh Oai District Liberation Day. Photo: Huu Chanh
He thong bien bao, cay xanh, chieu sang tren tuyen da duoc nha thau thi cong hoan thien. Anh: Huu Chanh
The remaining section, over 2km long, is under construction. Photo: Huu Chanh
May moc lam viec tren cong truong, day nhanh tien do du an. Anh: Huu Chanh
Many machines are working on the construction site, speeding up the project progress. Photo: Huu Chanh
Doan trong khu vuc do thi thi tran Kim Bai co mat mat cat 25m, thiet ke them via he cho nguoi di bo. Anh: Huu Chanh
The section in the urban area of ​​Kim Bai town has a cross-section of 25m, with additional sidewalks designed for pedestrians. Photo: Huu Chanh
Toan tuyen du kien se hoan thanh vao cuoi nam 2024, . Anh: Huu Chanh
In the photo is the end point of the project at the left dike of the Day River. The entire route is expected to be completed by the end of 2024, meeting the travel needs of the people, contributing to the socio-economic development of Thanh Oai district. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

The road is being expanded to 40m, 6 lanes in Hanoi

|

Hanoi - The Tam Trinh road expansion project was restarted in August 2024 after many years of delay. Contractors are currently working on some sections where the ground has been cleared.

Underpass under railway in Hanoi under construction in new phase

|

Two years since the groundbreaking ceremony, the Hanoi underground railway tunnel project has reached 50% progress and is entering a new phase of construction.

Unexpected images of people traveling on Hanoi's Ring Road 4

|

Hanoi - Many parallel routes of Ring Road 4 have been paved, people can use them for commuting and exercising.

6 hours with the group of brothers overcoming thorns in the heavy rain and strong winds of thousands of audiences

|

The 6th Call Me by Fire concert took place in heavy rain, causing the audience to work hard and face many difficulties.

PSG beat Atletico Madrid in the opening match of the 2025 FIFA Club World Cup

|

PSG won 4-0 against Atletico Madrid in the opening match of the FIFA Club World Cup 2025TM.

Reversal storm forecast, global weather forecast

|

Global storm forecasts and weather forecasts are changing in the context of the emergence of a neutral ENSO - a rare period not classified as El Nino or La Nina.

The hundred-billion-dong road project connecting the new Mien Dong Bus Station is still unfinished after 10 years

|

HCMC - The Hoang Huu Nam road expansion project has not been completed since 2015, due to land clearance problems, expected to be completed by the end of November 2025.

Speed up the progress of land acquisition to widen arterial roads in Hanoi to 50-60m

|

Hanoi - Land acquisition and site clearance to expand National Highway 6 from Ba La to Xuan Mai are being focused on by Ha Dong and Chuong My districts.

The road is being expanded to 40m, 6 lanes in Hanoi

HỮU CHÁNH |

Hanoi - The Tam Trinh road expansion project was restarted in August 2024 after many years of delay. Contractors are currently working on some sections where the ground has been cleared.

Underpass under railway in Hanoi under construction in new phase

HỮU CHÁNH |

Two years since the groundbreaking ceremony, the Hanoi underground railway tunnel project has reached 50% progress and is entering a new phase of construction.

Unexpected images of people traveling on Hanoi's Ring Road 4

HỮU CHÁNH |

Hanoi - Many parallel routes of Ring Road 4 have been paved, people can use them for commuting and exercising.