Machinery and manpower accelerate on the civil construction site of Phan Thiet Airport

Duy Tuấn |

Lam Dong - After 3 months of construction, machinery and many personnel are accelerating construction, gradually bringing many civil items of Phan Thiet Airport into operation.

On August 3, at the construction site of the civil aviation item of Phan Thiet Airport (Mui Ne ward), many machines and engineers and workers are urgently constructing to speed up the project progress.

After more than 3 months since the groundbreaking day, the project's appearance has gradually taken shape. Many foundation items have been completed, creating a premise for deploying the next items according to the plan.

Thi công ép cọc đại trà nhà ga hàng không dân dụng và đài kiểm soát không lưu thuộc dự án Cảng hàng không Phan Thiết. Ảnh: Duy Tuấn
Machinery and manpower for mass pile driving at the civil airport terminal and air traffic control tower under the Phan Thiet Airport project. Photo: Duy Tuan

According to the Department of Construction of Lam Dong province, by the beginning of August, the contractor had completed the construction site operating office, finished piloting the passenger terminal and air traffic control tower.

Currently, the construction unit is deploying mass pile driving for the passenger terminal and air traffic control tower. In parallel, there are items such as clearing, peeling organic soil, leveling the taxiway area, aircraft parking lot, regulating lake and auxiliary works.

Chủ đầu tư báo cáo tiến độ thi công dự án Cảng hàng không Phan Thiết - Hạng mục hàng không dân dụng. Ảnh: Duy Tuấn
Investor reports on the construction progress of Phan Thiet Airport project - Civil aviation item. Photo: Duy Tuan

To ensure progress, Phan Thiet Sun Airfield Co., Ltd. has mobilized nearly 40 machines and equipment and nearly 70 engineers and workers working at the construction site. In the coming time, the unit will continue to supplement manpower and equipment to accelerate construction volume.

For fire prevention and fighting appraisal dossiers, the investor has completed and submitted them to functional agencies for consideration. After having the appraisal results, many items will continue to be implemented synchronously according to the plan.

Ông Đặng Hồng Sỹ - Phó Bí thư Thường trực Tỉnh ủy Lâm Đồng kiểm tra hiện trường thi công dự án. Ảnh: Duy Tuấn
Mr. Dang Hong Sy - Standing Deputy Secretary of the Lam Dong Provincial Party Committee inspects the project construction site. Photo: Duy Tuan

Inspecting the construction progress at the project, Mr. Dang Hong Sy - Standing Deputy Secretary of the Lam Dong Provincial Party Committee requested the investor to mobilize machinery and human resources to accelerate the progress.

At the same time, develop a detailed schedule for deploying project items in the form of a Gantt diagram, in accordance with the contract implementation deadline. The requirement is to ensure the completion of construction work and technical infrastructure system within the committed time.

Phối cảnh hạng mục hàng không dân dụng Cảng hàng không Phan Thiết. Ảnh: Phạm Duy
Perspective of the civil aviation item of Phan Thiet Airport. Photo: Investor

According to the design, Phan Thiet Airport is a dual-use airport including a military area and a civil area. In which, the military item has been completed and put into use from the end of 2025.

The civil aviation item is invested according to 4E-class airport standards, with a total capital of nearly 3,900 billion VND, with a capacity scale of about 2 million passengers per year by 2030.

Bên trong công trường thi công dự án. Ảnh: Duy Tuấn
Inside the project construction site. Photo: Duy Tuan

The project has a land use area of 75 hectares in Mui Ne ward, including a passenger terminal, aircraft parking lot, taxiway, air traffic control tower and many synchronous technical infrastructure works.

According to the plan, the project will be completed and put into operation in 2027. When put into operation, Phan Thiet Airport is expected to expand the connection of inter-regional economic and tourism space. At the same time, it creates motivation for tourism development, attracts investment in trade and services, and promotes economic growth in the eastern region of Lam Dong province.

Duy Tuấn
RELATED NEWS

Mobilize machinery to dismantle works, relocate assets to implement the National Highway 6 upgrade project

|

Functional forces mobilize vehicles and machinery to support households to dismantle works and move assets to implement the National Highway 6 upgrade project.

Phan Thiet Civil Airport will open the sky, attracting investment

|

Lam Dong - Phan Thiet Civil Airport was started on April 27. When completed, it will attract investment and create thousands of jobs for workers.

Expected start time for construction of Phan Thiet Airport

|

Lam Dong - Phan Thiet Airport, civil item with a total investment of nearly 3,800 billion VND. Expected commencement time in the second quarter of 2026.

Metro No. 2 progress after nearly 7 months of construction, passing through 14 wards of Ho Chi Minh City

|

Ho Chi Minh City - After nearly 7 months of construction, Metro Line No. 2 (Ben Thanh - Tham Luong) is accelerating construction at two underground stations Pham Van Bach and Le Thi Rieng.

Submit to the National Assembly specific policies to accelerate projects serving APEC 2027

|

The Government submits to the National Assembly for consideration 5 specific policy groups to accelerate projects serving APEC 2027 in Phu Quoc.

Government approves dossier of project to establish wards under Bac Ninh province

|

The Government decided to approve the dossier of the Project on establishing wards under Bac Ninh province at the request of the Ministry of Home Affairs.

National Assembly discusses expanding the scope of state compensation

|

On the morning of August 3, the National Assembly listened to the submission and appraisal report on the Law amending and supplementing a number of articles of the Law on State Compensation Liability.

Mobilize machinery to dismantle works, relocate assets to implement the National Highway 6 upgrade project

Anh Tuấn |

Functional forces mobilize vehicles and machinery to support households to dismantle works and move assets to implement the National Highway 6 upgrade project.

Phan Thiet Civil Airport will open the sky, attracting investment

Duy Tuấn |

Lam Dong - Phan Thiet Civil Airport was started on April 27. When completed, it will attract investment and create thousands of jobs for workers.

Expected start time for construction of Phan Thiet Airport

Duy Tuấn |

Lam Dong - Phan Thiet Airport, civil item with a total investment of nearly 3,800 billion VND. Expected commencement time in the second quarter of 2026.