Expected start time for construction of Phan Thiet Airport

Duy Tuấn |

Lam Dong - Phan Thiet Airport, civil item with a total investment of nearly 3,800 billion VND. Expected commencement time in the second quarter of 2026.

On the afternoon of April 2nd, at the press conference in March organized by Lam Dong province, the Provincial Propaganda and Mass Mobilization Committee of the Provincial Party Committee informed about the expected start time for the Phan Thiet Airport Project - Civil Aviation item is April 28th, 2026.

Previously, on December 13, 2025, Lam Dong Provincial People's Committee approved the investment policy of the project. On March 4, 2026, the Provincial People's Committee continued to issue a decision approving the investor selection results for Phan Thiet Sun Airfield Co., Ltd.

The Department of Construction has agreed, negotiated and signed a contract with the investor. Currently, the enterprise is implementing the necessary procedures to prepare to start construction according to the plan.

The Department of Construction has agreed, negotiated and signed a contract with the investor. Currently, the investor is implementing procedures to start construction of the project.

Phối cảnh Dự án Cảng hàng không Phan Thiết - Hạng mục hàng không dân dụng. Dự kiến dự án sẽ khởi công xây dựng trong quý II.2026. Ảnh: Nhà đầu tư
Perspective of Phan Thiet Airport Project - Civil aviation item. The expected construction start time for the project is the second quarter of 2026. Photo: Investor

According to the People's Committee of Lam Dong province, the project has a scale of nearly 75ha of land, with a total investment of about 3.797 billion VND. The operating term is 50 years from the date of investment approval according to legal regulations.

The civil aviation item includes many main works such as the flight area with the airfield; air traffic control system, air and ground navigation.

The passenger terminal area is invested and built with an area of up to 18,000m2, with an expected operating capacity of 2 million passengers per year.

The project also includes inland port traffic items such as the road connecting to the airport, the system of roads connecting functional areas, parking lots, ring roads and auxiliary works.

Phan Thiet Airport was started in January 2015, according to the plan, it includes two items: a military airport and a civil airport. Currently, the military item deployed by the Air Defense - Air Force Service has been put into operation.

The early deployment and completion of the civil item is expected to create more motivation for tourism development. Thereby, contributing to promoting the socio-economy of the province in the coming time.

Duy Tuấn
RELATED NEWS

2026 High School Graduation Exam: Important milestone candidates need to remember

|

The 2026 high school graduation exam will take place from June 10, 2026 to June 13, 2026. Candidates need to remember the important time milestones of the exam.

Investor of Phan Thiet Airport project, civil item officially revealed

|

Lam Dong has approved the investor selection results for the Phan Thiet Airport project - Civil aviation item.

Lam Dong approves bidding documents to select investors for Phan Thiet airport

|

Lam Dong has approved the bidding documents to select investors for the Phan Thiet Airport project (civil sector) which is of great interest to the people.

Gold price update closing session 4: SJC gold bars, gold rings simultaneously decrease

|

Gold price update at the closing session 4: Domestic gold simultaneously decreased by 3.2 to 4.2 million VND/tael.

Notice of conclusion on the content of supervision for the Standing Committee of Phu Tho Provincial Party Committee

|

On April 2, Inspection and Supervision Team No. 15 led by Comrade Bui Thi Minh Hoai - Member of the Politburo, Secretary of the Party Central Committee, Chairman of the Central Committee of the Vietnam Fatherland Front - announced the conclusions on the content of supervision (phase 1) and deployed the contents of inspection (phase 2) for the Standing Committee of Phu Tho Provincial Party Committee.

Ministry of Health announces list of food safety testing facilities

|

The Food Safety Department - Ministry of Health has just announced the latest list of 26 testing facilities serving state management of food safety.

Commending 10 outstanding young faces and 80 promising young faces of the entire army

|

On the afternoon of April 2nd, the Central Military Commission and the Ministry of National Defense organized a ceremony to commend outstanding young faces and promising young faces of the entire army in 2025.

Government stipulates principles for management and use of trade union funds

|

Decree No. 105/2026/ND-CP of the Government has stipulated the subjects of application, principles for management and use of trade union funds and the deadline for paying trade union fees.

2026 High School Graduation Exam: Important milestone candidates need to remember

Minh Phương |

The 2026 high school graduation exam will take place from June 10, 2026 to June 13, 2026. Candidates need to remember the important time milestones of the exam.

Investor of Phan Thiet Airport project, civil item officially revealed

Duy Tuấn |

Lam Dong has approved the investor selection results for the Phan Thiet Airport project - Civil aviation item.

Lam Dong approves bidding documents to select investors for Phan Thiet airport

Duy Tuấn |

Lam Dong has approved the bidding documents to select investors for the Phan Thiet Airport project (civil sector) which is of great interest to the people.