Many key projects in Lam Dong are behind schedule, with low disbursement rates

Duy Tuấn |

Lam Dong - Many key transport projects in the province are behind schedule, the capital disbursement rate in 2025 will only reach 11.12%.

On July 19, the Lam Dong Province Traffic Construction Investment Project Management Board said that the DT.719B coastal road project, Phan Thiet - Ke Ga section, with a total investment of VND 1,274 billion, is a key project of the province.

This project is 25.61 km long. Of which, 17.8km from National Highway 1 to Suoi Nhum Bridge has been completed and put into operation. The remaining 3.88km section through the Titan mining area of Tan Quang Cuong Company Limited has not yet handed over the construction site.

The construction volume is currently about 80% of the contract value. However, according to the investor's assessment, the project's capital disbursement plan for 2025 has only reached 9.19%.

Du an duong truc ven bien DT.719B doan Phan Thiet - Ke Ga. Anh: Duy Tuan
DT.719B coastal axis road project Phan Thiet - Ke Ga section. Photo: Duy Tuan

The DT.719B Coastal Axis Project, Hon Lan - Tan Hai section, with a total length of 10.4km, is expected to be completed on December 31, 2025. The project's construction progress has reached about 32% of the contract volume. The site has been handed over about 92%. Capital disbursement in 2025 will reach 8.69%.

Similarly, the Van Thanh Bridge project (Phan Thiet), with an implementation period of December 30, 2025, is also behind schedule due to land clearance problems, and construction measures must be adjusted. Currently, the project has reached about 54% of the volume, and the capital disbursement in 2025 has reached 10.28%.

The road project from Tan Minh town to Son My is 23.71km long, expected to be completed on September 1, 2027. The capital disbursement volume in 2025 will reach 5.93%.

The DT.719 bypass project and the bridge over the Dinh River are expected to be completed on June 15, 2027; the disbursement in 2025 will only reach 0.35%.

Vi tri bi vuong mo titan anh huong den tien do. Anh: Duy Tuan
The coastal road project DT.719B, Phan Thiet - Ke Ga section, is stuck in titanium mine work, so it is affecting progress. Photo: Duy Tuan

According to the report of the Department of Construction, the disbursement of investment capital for transport projects in 2025 only reached 11.12%.

Vice Chairman of Lam Dong Provincial People's Committee - Nguyen Hong Hai has requested the Traffic Project Management Board to report in detail the problems and have more drastic and focused instructions to promote the disbursement of capital.

He also requested that communes and wards where projects have passed through reports of difficulties and problems affecting project progress so that departments and branches can advise and propose to coordinate in removing them.

Du an Cau Van Thanh dang thi cong. Anh: Duy Tuan
The Van Thanh Bridge project is under construction. Photo: Duy Tuan

Mr. Nguyen Hong Hai - Vice Chairman of Lam Dong Provincial People's Committee also said that the disbursement rate of capital for the above works and projects is very low. Subjective causes are largely the responsibility of the Traffic Project Management Board.

Vice Chairman of the Provincial People's Committee - Nguyen Hong Hai has directed specific solutions and solutions for each project. In which, tasks are assigned to each commune, ward, department, branch and project management board.

At the same time, set a specific time for units to focus on urgently resolving the issue to promote the progress of the projects.

The Vice Chairman of the Provincial People's Committee also requested the Department of Agriculture and Environment to submit technical regulations for approval in July as a basis for site clearance.

For the Department of Finance, every month it will preside over and work with the Department of Construction to inspect the projects to urge the progress and quality of the projects.

Duy Tuấn
RELATED NEWS

Land clearance problems slow down the progress of Van Thanh bridge in Phan Thiet

|

Binh Thuan - After more than 2 years of construction, the progress of the Van Thanh bridge project has only reached about 51% of the contract volume due to land clearance problems.

Still stuck in land clearance for DT.719B project, Hon Lan - Tan Hai section

|

Binh Thuan - Site clearance faces many difficulties and obstacles affecting the progress of the DT.719B Coastal Axis project, Hon Lan - Tan Hai section.

The current situation of titanium mines causes the DT.719B road project to stagnate

|

Binh Thuan - 3.8 km through the titanium mine that has not been cleared yet has caused the project to renew the coastal road DT.719B, Phan Thiet - Ke Ga section, to "standstill".

Continuously losing money, Thai Nguyen lottery company shows signs of financial insecurity

|

Thai Nguyen - Phase 2018 - 2024, Thai Nguyen Lottery Co., Ltd. operates ineffectively, continuously losing money.

Gold price update at the close of the session on July 11: Sideways, experts forecast short-term prospects

|

Gold price update at the close of the session on July 11th: Continued struggle. Experts divide when predicting short-term prospects.

Close-up of the hundred billion Ring Road 2.5 section Trung Kinh - Hoang Quoc Viet

|

Ring Road 2.5 section from Trung Kinh to Hoang Quoc Viet (Hanoi) is expected to contribute to reducing traffic pressure for the Cau Giay area.

Sophisticated activities of inter-provincial gambling ring during the 2026 World Cup season

|

Quang Tri - Provincial police dismantled an inter-provincial gambling ring operating during the 2026 World Cup season, initially determining the transaction amount to be about 400 billion VND.

Fierce floods rush on the streets of Son La

|

Son La - Prolonged heavy rain caused many places to be flooded, and on the streets, cloudy and fast-flowing floodwaters appeared.

Land clearance problems slow down the progress of Van Thanh bridge in Phan Thiet

Duy Tuấn |

Binh Thuan - After more than 2 years of construction, the progress of the Van Thanh bridge project has only reached about 51% of the contract volume due to land clearance problems.

Still stuck in land clearance for DT.719B project, Hon Lan - Tan Hai section

Duy Tuấn |

Binh Thuan - Site clearance faces many difficulties and obstacles affecting the progress of the DT.719B Coastal Axis project, Hon Lan - Tan Hai section.

The current situation of titanium mines causes the DT.719B road project to stagnate

Duy Tuấn |

Binh Thuan - 3.8 km through the titanium mine that has not been cleared yet has caused the project to renew the coastal road DT.719B, Phan Thiet - Ke Ga section, to "standstill".