Quang Tri resolutely removes obstacles to speed up the progress of the North - South expressway

HÀN NGUYÊN |

Quang Tri - The items of the North - South expressway project are basically completed, but there are still some difficulties that need to be overcome promptly to ensure progress.

According to the Department of Construction of Quang Tri province, the expressway project through the area includes three component projects: the Vung Ang - Bung section is 42.44km long, the Bung - Van Ninh section is 48.84km long and the Van Ninh - Cam Lo section is 65.53km long. The total length of the entire route is more than 156km, with 11 intersections and three rest stops located in Hoa Trach commune, Dong Son ward and Con Tien commune.

To implement the project, more than 1,481 hectares of land must be reclaimed, of which more than 753 hectares of forest need to be converted for use. The project also affects 852 households who have to be relocated and relocate nearly 4,800 graves, along with many technical infrastructure works such as high-voltage power systems and telecommunications.

Cao toc Van Ninh - Cam Lo da hoan thanh tuyen chinh. Anh: Han Nguyen
The Van Ninh - Cam Lo Expressway has completed the main route. Photo: Han Nguyen

Up to now, all site clearance work for the main route has reached 100%. All 35 resettlement areas have been completed, stabilizing housing for households. The relocation of technical infrastructure, arrangement of material mines, dumping sites, and announcement of material prices are all implemented synchronously, creating great convenience for construction.

However, progress is still facing obstacles in many auxiliary items. Specifically, the additional site of the rest stop at Km725+500 in Con Tien commune has not been completed; some sections of the fence and service road through Bo Trach, Hoan Lao, Truong Phu, Kim Ngan communes are still unfinished.

The leader of the People's Committee of Quang Tri province said that from now until mid-July is the final stage, so the People's Committee of Quang Tri province has requested the People's Committees of communes and wards that are investors in sub-projects for site clearance to proactively and thoroughly handle the backlog. At the same time, the Department of Construction and the Department of Agriculture and Environment need to coordinate in guiding and removing obstacles, ensuring unity in implementation.

Hoan tat cac hang muc tren tuyen chinh cao toc doan Van Ninh - Cam Lo. Anh: Han Nguyen
Complete items on the main expressway section Van Ninh - Cam Lo. Photo: Han Nguyen

The provincial leaders also requested Project Management Board 6, Ho Chi Minh Road Project Management Board to urgently transfer funds, fully assess the level of impact on households near the border to clear land and complete procedures to return affected residential roads.

In case people have been compensated in accordance with regulations but still do not hand over the site, localities must propagate and mobilize; if necessary, develop a construction protection plan, and resolutely strive to complete the national key project on schedule.

HÀN NGUYÊN
RELATED NEWS

Nghe An batks hands to clear the North-South high-speed railway site

|

Nghe An - The North-South high-speed railway project passing through the province is 85.5km long, affecting 2,150 households.

The Ministry of Construction responds to Thanh Hoa voters about many backlogs on the North-South Expressway

|

The Ministry of Construction has just responded to Thanh Hoa voters about the backlog of reflections on the North - South Expressway.

People suffer from mud from Van Ninh - Cam Lo Expressway

|

The construction of the Van Ninh - Cam Lo expressway project through Xuan Hoa village (Gio Linh district, Quang Tri province) has become a nightmare for many households because they are constantly experiencing flooding, mud and mud flowing into their gardens, threatening their livelihoods and daily lives.

International cultural integration, shifting from exchange to true cooperation

|

Vietnam proactively integrates internationally in culture, comprehensively transforms thinking from "interaction, meeting" to "genuine cooperation", promoting national soft power.

Securities face profit-taking pressure from state-owned stocks

|

After an impressive streak of increases, the state-owned stock group underwent profit-taking pressure, causing the stock market to decline.

Overtime to ensure environmental sanitation during the 14th Party Congress

|

Hanoi - During the peak period serving the 14th National Party Congress, environmental sanitation workers have increased working hours to keep streets clean and beautiful.

Gasoline and oil prices today 21.1: Simultaneously sharply decrease

|

Gasoline prices today 21.1: World gasoline prices today simultaneously decreased sharply. WTI oil and Brent oil are recording a decrease of more than 1%.

The 3 driving forces to bring Vietnam to break through and escape the middle-income trap

|

At the 14th Congress, according to Minister Nguyen Manh Hung, Vietnam must rely on science and technology, innovation and digital transformation to escape the middle-income trap.

Nghe An batks hands to clear the North-South high-speed railway site

QUANG ĐẠI |

Nghe An - The North-South high-speed railway project passing through the province is 85.5km long, affecting 2,150 households.

The Ministry of Construction responds to Thanh Hoa voters about many backlogs on the North-South Expressway

Xuyên Đông |

The Ministry of Construction has just responded to Thanh Hoa voters about the backlog of reflections on the North - South Expressway.

People suffer from mud from Van Ninh - Cam Lo Expressway

HƯNG THƠ |

The construction of the Van Ninh - Cam Lo expressway project through Xuan Hoa village (Gio Linh district, Quang Tri province) has become a nightmare for many households because they are constantly experiencing flooding, mud and mud flowing into their gardens, threatening their livelihoods and daily lives.