National Highway 28B worth more than 1,400 billion VND accelerates towards the finish line thanks to drastic direction

Duy Tuấn |

Lam Dong - National Highway 28B upgrade project accelerates, approaching the finish line after close directions from provincial leaders.

About 4 months ago, many people and drivers were still skeptical about the possibility of completing National Highway 28B on schedule. Even some people said that it might not be completed by the end of 2026.

However, by the end of March 2026, the reality at the construction site showed that the project had a clear change. Many sections were asphalted flat, and overpasses gradually completed, ensuring smooth traffic.

Quốc lộ 28B trên đèo Đại Ninh. Ảnh: Duy Tuấn
A section of National Highway 28B on Dai Ninh Pass has been asphalted. Photo: Duy Tuan

About 1 month ago, the construction progress of National Highway 28B was even more concerned when Lien Khuong International Airport temporarily stopped operating (from March 4) for repairs, causing travel demand through this route to increase.

In his guiding role, Mr. Ho Van Muoi - Member of the Party Central Committee, Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of Lam Dong province - directly inspected the construction site many times.

Thereby, promptly removing obstacles, especially in terms of land, in the period of the end of 2025 and early 2026 - the time when the project enters the final sprint.

Previously, in October 2025, Mr. Ho Van Muoi affirmed that the province will create all favorable conditions, and at the same time resolutely consider responsibility if progress continues to be slow, including proposing to replace the investor.

Một cầu cạn trên tuyến. Ảnh: Duy Tuấn
A viaduct on the route. Photo: Duy Tuan

During the inspection in mid-March 2026, Chairman of the Provincial People's Committee Ho Van Muoi continued to request Luong Son commune to urgently complete the handover of the remaining site.

At the same time, direct Project Management Board 5 to mobilize maximum manpower and equipment, organize overtime construction, increase shifts, and be determined to complete it completely in April 2026.

Thanks to drastic directions, the project progress has changed significantly every day. Recorded at the end of March, the Km41 area was bustling with machinery constructing hot asphalt concrete paving.

This is the final section at the top of Dai Ninh pass that is being asphalted; elevated bridge item No. 4 is also entering the final completion phase.

Chủ tịch UBND tỉnh Lâm Đồng Hồ Văn Mười trong một chuyến đi kiểm tra công trường dự án Quốc lộ 28B. Ảnh: Duy Tuấn
Chairman of Lam Dong Provincial People's Committee Ho Van Muoi on a trip to inspect the construction site of National Highway 28B project. Photo: Duy Tuan

Mr. Le Van Chung - Deputy Director of Project Management Board 5 - said that the unit is deploying many construction fronts with the highest urgency, determined to complete the entire asphalt concrete paving work in April.

For people, each asphalt road section is more convenient for travel. Mr. Nguyen Thanh Cong (living at the top of Dai Ninh pass) said that the construction progress changes every day, new road sections help traffic be safer and less difficult.

Currently, the project is still stuck with about 20m of land at the beginning of the route in Luong Son commune because 4 households have not agreed to receive compensation money.

According to Luong Son Commune People's Committee, the locality continues to propagate and mobilize; and at the same time develop a plan to protect construction and enforce if households do not comply with regulations.

Xe ô tô chạy trên Quốc lộ 28B đoạn đã hoàn thiện. Ảnh: Duy Tuấn
Cars circulating on National Highway 28B section that has been completed. Photo: Duy Tuan

The project to renovate and upgrade National Highway 28B has a total investment of more than 1,435 billion VND, about 68km long, invested by the Vietnam Road Administration and directly managed by Project Management Board 5.

Duy Tuấn
RELATED NEWS

National Highway 28B upgrade project sprints to reach the finish line on schedule

|

Lam Dong - The National Highway 28B upgrade project enters the final sprint phase to be completed in March 2026, while Lien Khuong Airport is temporarily closed.

Construction throughout the New Year holiday on the National Highway 28B upgrade project

|

Lam Dong - Currently, there are many construction teams with workers and machinery operating continuously, throughout the New Year holiday on National Highway 28B construction site.

Chairman of Lam Dong province warns investors and department leaders if National Highway 28B is still behind schedule

|

Lam Dong - The Chairman of the Provincial People's Committee warned that he would change the department's leaders and propose to change the investor and contractor if the National Highway 28B project continued to be behind schedule.

Tao Quan 2026 has special meaning for Nam Tao Trung Ruoi

|

In Tao Quan 2026, Trung Ruoi plays Nam Tao. This is the 9th year he has been associated with the program.

US surges troop numbers in the Middle East to 50,000, ready for ground combat in Iran

|

The addition of 2,500 marines and 2,500 sailors raises the number of US troops in the Middle East to 10,000 people higher than usual.

Mr. Nguyen Van Duoc re-elected Chairman of Ho Chi Minh City People's Committee

|

Ho Chi Minh City - Mr. Nguyen Van Duoc re-elected Chairman of Ho Chi Minh City People's Committee for the term 2026 - 2031.

Scene of a fierce factory fire in Hanoi that killed 1 person

|

Hanoi - 1 person was found dead at the scene of a factory fire in Thanh Liet ward.

Is there unusual ice rain in Hanoi and many places in the North in March

|

According to meteorologists, hail and thunderstorms appear during the transitional season in accordance with climate laws.

National Highway 28B upgrade project sprints to reach the finish line on schedule

Duy Tuấn |

Lam Dong - The National Highway 28B upgrade project enters the final sprint phase to be completed in March 2026, while Lien Khuong Airport is temporarily closed.

Construction throughout the New Year holiday on the National Highway 28B upgrade project

Duy Tuấn |

Lam Dong - Currently, there are many construction teams with workers and machinery operating continuously, throughout the New Year holiday on National Highway 28B construction site.

Chairman of Lam Dong province warns investors and department leaders if National Highway 28B is still behind schedule

Duy Tuấn |

Lam Dong - The Chairman of the Provincial People's Committee warned that he would change the department's leaders and propose to change the investor and contractor if the National Highway 28B project continued to be behind schedule.