Focus on solving the coastal road through Quang Binh

CÔNG SÁNG |

Quang Binh - Component project 1 - Coastal road is still stuck in land clearance, the locality has had thorough implementation plans to speed up progress.

Construction is on hold

Component project 1 - Coastal road under the Coastal road and Nhat Le bridge 3 project invested by the Department of Transport of Quang Binh province, with a total investment of nearly 2,200 billion VND, started construction on January 24, 2022 with 3 sections with a total length of 80km.

Up to now, the work of approving the plan and paying compensation for site clearance has been 71.32/80km (reaching 89.2%), of which the scope of construction site handover is 70.2/80km (reaching 87.8%). However, the construction work on the route has been interrupted and discontinuous, causing difficulties in the implementation of construction by contractors, affecting the progress.

The Department of Transport of Quang Binh province has just coordinated with the Party Committee and People's Committee of Ba Don town to inspect the site of the Coastal Road project passing through Ba Don town.

The coastal road project section passing through Ba Don town has a length of 11.7km. Up to now, the locality has handed over 99.7% of the cleared land to the investor to start construction with a length of 11.67km/11.7km. Currently, the only remaining problem is the 30m land area at a household in Quang Phuc ward because the procedures for arranging scattered resettlement land are being carried out.

Regarding the remaining compensation-related procedures, Ba Don town assigned the Town Land Fund Development and Investment Project Management Board to complete, approve, and resolve the affected households, helping them to soon have a stable life and basically return to normal life, handing over 100% of the clean site to the investor before December 15, 2024.

Speed ​​up site clearance

Mr. Nguyen Ngoc Quy - Director of the Project Management Board for Investment and Construction of Traffic Works in Quang Binh province - said that the main causes of difficulties in site clearance are mainly related to assets created on forest land, resettlement, compensation for aquaculture farms, relocation of tombs, etc.

Le Thuy district still has 114 households that have not approved the site clearance plan, greatly affecting the construction site which is not continuous and interrupted; Bo Trach district has 22 households and 2 organizations that have not approved (calculated according to the route length of 0.7km); Quang Trach has 15 households. Dong Hoi city has handed over 3.95/6km of site, reaching 66.2%. Calculated by the number of households, it is 3/7, reaching 42.85%; the remaining 4 households and organizations in Bao Ninh commune are related to compensation for aquaculture farms and livestock farms.

Mot so doan duong tren tuyen dang duoc rai nhua. Anh: Q. Nguyen
Some sections of the route are being paved. Photo: Q. Nguyen

The Department of Transport informed that the unit has also made proposals and recommendations to urgently carry out site clearance work for all levels, sectors and districts to implement.

The District People's Committee urgently established a Price Appraisal Council to determine the prices of assets of materials, machinery and equipment serving agriculture and aquaculture according to the guidance of the Department of Finance.

Regarding resettlement work, Le Thuy district directed to speed up the progress of implementing the resettlement area in Ngu Thuy commune; Bo Trach district urgently approved the detailed planning of the resettlement area in Dong Trach commune and implemented the following procedures; Quang Trach district accelerated the construction progress to quickly complete it.

In Le Thuy district alone, we continue to mobilize 17 households in Ngu Thuy commune to agree to receive compensation and support to hand over the land to implement the Project (announced for the third time); resolve land disputes between 6 households in Ngu Thuy commune...

CÔNG SÁNG
TIN LIÊN QUAN

The 2,000 billion VND road project in Lang Son is behind schedule due to land clearance

|

Lang Son - The project to upgrade section Km18-Km80, National Highway 4B had to request an extension due to difficulties in site clearance.

Recommendation on land price for compensation and site clearance in Ha Nam

|

Ha Nam - Many residents of Tien Noi ward (Duy Tien town) have petitioned about land compensation prices for site clearance.

Fierce fire at rice husk warehouse in Dong Thap, expected to last all night

|

Dong Thap - The rice husk warehouse is burning fiercely and over a large area. Local authorities mobilized firefighting forces throughout the night to control the spread of the fire.

Dak Lak today has transformed and grown strongly

|

Dak Lak - In the period of 2021 - 2023, the province's economic growth will average 7%/year, and the economic scale will increasingly expand.

School health worker job position is "forgotten"

|

Ninh Binh - Currently, many school health officials in Ninh Binh city are still in the "support and service" group, which has affected their benefits.

Proposal to add monitoring activities for citizen reception

|

National Assembly delegates proposed adding activities to monitor citizen reception to reduce voters' petitions to the Central level.

Thai Binh Provincial Party Secretary appointed Deputy of Central Propaganda Department

|

Thai Binh Provincial Party Secretary Ngo Dong Hai was transferred and appointed to the position of Deputy Head of the Central Propaganda Department.

"3 cars in, 1 car out", parking lot violations face difficulty in finding a solution

|

Currently, many parking lots for vehicles in violation are overloaded because the owners have not come to claim them for a long time.

The 2,000 billion VND road project in Lang Son is behind schedule due to land clearance

Khánh Linh |

Lang Son - The project to upgrade section Km18-Km80, National Highway 4B had to request an extension due to difficulties in site clearance.

Recommendation on land price for compensation and site clearance in Ha Nam

Thu Giang |

Ha Nam - Many residents of Tien Noi ward (Duy Tien town) have petitioned about land compensation prices for site clearance.

Bắc Ninh giải phóng mặt bằng sân bay 887 tỉ nhanh hơn dự kiến

Vân Trường |

Ngày 18.11, UBND tỉnh Bắc Ninh tổ chức phiên họp thường kỳ tháng 11.2024.