Tet on the highway worth over 27,500 billion VND in the West

Tạ Quang |

Although it is New Year's Day, at the Can Tho - Ca Mau highway construction site, workers and engineers are still working non-stop.

The Can Tho - Ca Mau Expressway was started in January 2023, with a length of more than 110km, with a total investment of more than VND 27,500 billion. The project is divided into two component projects including the Can Tho - Hau Giang section (more than 37km) and the Hau Giang - Ca Mau section (more than 73km).

Cao toc Can Tho – Ca Mau tich cuc thi cong ngay dau nam. Anh: Ta Quang
Can Tho – Ca Mau Expressway is actively under construction on the first day of the year. Photo: Ta Quang

According to Lao Dong Newspaper reporters at Lo Da Bridge located in the Can Tho - Hau Giang Expressway section, in Vi Thuy District, Hau Giang Province, on New Year's Day, January 1, 2025, at the construction site, there were many workers, engineers, equipment and machinery focused on working on items such as leveling the ground, assembling iron for the bridge abutment to prepare for pouring concrete, etc.

After two years of working on the construction site and in the bridge construction team, Mr. Nguyen Van Thanh (52 years old, Ha Tinh province) shared that during the last and first days of the year, the workload was very heavy, so the workers and engineers had to continuously work overtime to regain progress, because before that it was the rainy season so the construction encountered many difficulties.

Tai cau Lo Da, cac cong nhan, ky su dang thi cong hang muc lap ghep sat phan mo cau de chuan bi do be-tong,…Anh: Ta Quang
At Lo Da bridge, workers and engineers are assembling the bridge pier's iron structure to prepare for pouring concrete. Photo: Ta Quang

“Having received information that the Can Tho – Ca Mau Expressway must be completed by the end of this year (December 31, 2025), our brothers and sisters always try their best and work hard to achieve progress and soon bring the expressway to the finish line. When the expressway is completed and put into operation, the people of the West will be happy one, and we will be ten times happier. Because we have contributed a small part to the country’s development. In addition, this is also an opportunity for the Mekong Delta region to develop more and more,” Mr. Thanh happily said when asked about his determination to complete the expressway.

According to Mr. Nguyen Van Thanh, on the first day of the New Year, the bridge construction team still has to maintain work to ensure progress, but will not work overtime. Instead, the team will give up this overtime so that workers and engineers can celebrate Tet.

Having worked at the highway construction site for about a year now, Mr. Huynh Trung (35 years old, Quang Binh province) said that doing manual work is the hardest, especially on hot and humid days, when workers have to rest constantly. However, recently, the weather has been very pleasant, and the workers have been mobilized to work overtime and shift shifts regularly.

Anh Huynh Trung (35 tuoi, tinh Quang Binh) miet mai voi cong viec. Anh: Ta Quang
Mr. Huynh Trung (35 years old, Quang Binh province) is diligent in his work. Photo: Ta Quang

“Although we often have to work overtime, sometimes late at night, the company does not abandon us. We are always encouraged by the company and given extra overtime. Every time we are encouraged like that, we promise ourselves that we must always try our best to complete the goals set by the unit,” Trung said excitedly.

Lieutenant Colonel Vu Hong Quan - Deputy Director of Truong Son Nam Management Board - informed that he is currently in charge of the construction site of the Km49 - 53 section of the Can Tho - Hau Giang Expressway project. Up to this point, the project is accelerating its progress to complete by the end of 2025. The unit is focusing all its human and material resources to ensure the construction meets the requirements of the project's progress and quality.

According to Mr. Quan, in terms of human resources, there are about 200 engineers and workers at the construction site, who can synchronously deploy items from bridges, culverts, and weak ground treatment.

Thiet bi lu dang thi cong tich cuc. Anh: Ta Quang
Roller equipment is actively working. Photo: Ta Quang

“At the construction site, we have to divide into 3 shifts and 4 teams to work continuously, including holidays and days off. Even in the new year 2025, the construction site is still operating normally to ensure the requirements and progress set out.

For our brothers at the construction site who work with high intensity and large volume, we always encourage their spirit. In particular, we will check in overtime for our brothers to increase their income. There are meals during shifts, and on holidays, we can increase their salary and food allowance, ensuring that their health is always maintained to complete their tasks well", the Deputy Director of the Executive Board of Truong Son Nam clearly stated.

Lieutenant Colonel Vu Hong Quan emphasized: "As a military unit, we affirm that once assigned a task, everyone must be determined and united to best complete the assigned task."

Tạ Quang
TIN LIÊN QUAN

Basically completed the relocation of the landfill blocking the Can Tho - Ca Mau highway

|

Can Tho - According to the Cai Rang District Land Fund Development Project Management Board, by December 31, the relocation of the landfill blocking the highway was basically completed.

Racing progress at the Western highway construction site

|

In the last days of 2024, at the two North-South expressway construction sites, Can Tho - Ca Mau and Chau Doc - Can Tho - Soc Trang sections, the labor pace is urgent and bustling towards the goal of reaching the finish line on time.

Can Tho - Ca Mau Expressway paved the first meters

|

The laying of the first meters of asphalt marks the transition from the roadbed construction phase to the road surface completion phase of the Can Tho - Ca Mau expressway.

Dengue fever: Don't let the " mosquito problem" get too big!

|

Every 12 minutes, one person in the world dies from dengue fever. According to a report from the Ministry of Health, from December 14, 2024 to February 17, 2025, Vietnam recorded 16,607 cases, including one death due to dengue fever. The Department of Prevention (Ministry of Health) assessed dengue fever as one of the major challenges for the Vietnamese health sector in 2025.

President Trump may exempt tax reductions for many countries

|

US President Donald Trump said he could exempt more countries from tariffs as the deadline for imposing counterpart tariffs on US trade partners is approaching.

Gold price update on the morning of March 25: Domestic gold may decrease

|

Gold price update on the morning of March 25: World gold prices decreased, leading to the risk of domestic gold prices falling when the market opened today.

Confusing to understand the admission combination of many universities

|

Many universities enroll students in the English Language major but the admission combination does not have English or Physics Pedagogy but the combination does not require Physics.

Starting construction of 2 social housing projects in Dong Anh

|

Hanoi - Dong Anh District People's Committee is assigned to urgently carry out land acquisition, with the goal of starting construction of 2 social housing projects in September 2025.

Basically completed the relocation of the landfill blocking the Can Tho - Ca Mau highway

TẠ QUANG - YẾN PHƯƠNG |

Can Tho - According to the Cai Rang District Land Fund Development Project Management Board, by December 31, the relocation of the landfill blocking the highway was basically completed.

Racing progress at the Western highway construction site

TẠ QUANG - YẾN PHƯƠNG |

In the last days of 2024, at the two North-South expressway construction sites, Can Tho - Ca Mau and Chau Doc - Can Tho - Soc Trang sections, the labor pace is urgent and bustling towards the goal of reaching the finish line on time.

Can Tho - Ca Mau Expressway paved the first meters

Tạ Quang |

The laying of the first meters of asphalt marks the transition from the roadbed construction phase to the road surface completion phase of the Can Tho - Ca Mau expressway.