Bustling scene of moving garbage dump blocking Can Tho - Ca Mau highway

Yến Phương - Tạ Quang |

Can Tho – Following the Prime Minister’s direction, the construction of the landfill site blocking the Can Tho - Ca Mau expressway is being urgently accelerated.

Cao toc Can Tho - Ca Mau dai hon 110km, co tong muc dau tu hon 27.500 ti dong, duoc khoi cong vao thang 1.2023, hoan thanh cuoi nam 2025. Du an duoc chia thanh hai du an thanh phan. Trong do, doan Can Tho - Hau Giang co chieu dai hon 37km; doan Hau Giang - Ca Mau co chieu dai hon 73km.
The Can Tho - Ca Mau Expressway is over 110km long, with a total investment of over VND27,500 billion, and will start construction in January 2023 and be completed by the end of 2025. The project is divided into two sub-projects. Of which, the Can Tho - Hau Giang section is over 37km long; the Hau Giang - Ca Mau section is over 73km long.
Ban Quan ly du an (QLDA) My Thuan (chu dau tu) thong tin, den nay, san luong thi cong toan du an dat khoang 56%. Cong tac giai phong mat bang da ban giao tuyen chinh dat 100% va tuyen noi dat 99%; hien con 200m thuoc pham vi tuyen noi tai TP Can Tho do vuong bai rac so 8.
My Thuan Project Management Board (PMU) (investor) informed that up to now, the total construction output of the project has reached about 56%. The site clearance work has reached 100% of the main route and 99% of the connecting route; currently, there are 200m remaining within the connecting route in Can Tho City due to the No. 8 landfill.
Ghi nhan cua phong vien Bao Lao Dong vao chieu ngay 17.12, tai bai rac so 8 tren tuyen noi IC2 - Quoc lo 1 (thuoc phuong Ba Lang, quan Cai Rang), cong truong noi day nhon nhip cac thiet bi may moc va nhan cong de thuc hien di doi bai rac.
According to Lao Dong Newspaper reporters on the afternoon of December 17, at landfill No. 8 on the IC2 - National Highway 1 (in Ba Lang ward, Cai Rang district), the construction site was bustling with machinery and workers to relocate the landfill.
Trao doi voi phong vien Bao Lao Dong, ong Tran Tien Dat – Pho Giam doc Ban QLDA Phat trien quy dat quan Cai Rang (TP Can Tho) – cho biet, den nay, tien do di doi bai rac dat khoang 35%, co ban da dao xong lop 1, chuan bi dao sang lop 2.
Talking to Lao Dong Newspaper reporter, Mr. Tran Tien Dat - Deputy Director of the Land Fund Development Project Management Board of Cai Rang District (Can Tho City) - said that up to now, the progress of landfill relocation has reached about 35%, basically finished digging layer 1, preparing to dig layer 2.
Ve van de moi truong, ong Tran Tien Dat cho hay, hang tuan Ban QLDA co moi cac don vi thi nghiem den lay mau de lam thi nghiem. Truong hop vuot qua mui quy dinh theo tieu chuan, Ban se cho ngung lai de xu ly. Tuy nhien, tu luc trien khai den nay, mui van chua vuot qua muc quy dinh.
Regarding environmental issues, Mr. Tran Tien Dat said that every week the Project Management Board invites testing units to collect samples for testing. In case the odor exceeds the prescribed standards, the Board will stop the project for treatment. However, since the implementation, the odor has not exceeded the prescribed level.
Ong Nguyen Thanh Tung – Dai dien don vi thi cong bai rac so 8 - chia se, tren cong truong co khoang 30 chiec may xuc va o to, doi voi nhan cong co gan 40 nguoi gap rut thi cong de kip tien do theo ke hoach.
Mr. Nguyen Thanh Tung - Representative of the construction unit of landfill No. 8 - shared that there are about 30 excavators and cars at the construction site, and nearly 40 workers working hard to keep up with the schedule.
Truoc do, vao chieu 15.12, Thu tuong Chinh phu Pham Minh Chinh cung doan cong tac da co buoi kiem tra cao toc Can Tho - Ca Mau tai tinh Hau Giang. Thu tuong yeu cau UBND TP Can Tho phai chi dao cac so, nganh, chinh quyen co so xu ly dut diem viec di doi bai rac tren tuyen noi IC2 - Quoc lo 1, ban giao mat bang 100% trong thang 12.2024.
Previously, on the afternoon of December 15, Prime Minister Pham Minh Chinh and his delegation inspected the Can Tho - Ca Mau Expressway in Hau Giang Province. The Prime Minister requested the Can Tho City People's Committee to direct departments, branches, and local authorities to completely handle the relocation of the landfill on the IC2 - National Highway 1 connection route, handing over 100% of the site in December 2024.
Bai rac so 8 co dien tich 4,3ha voi tong khoi luong rac tren 162.000 tan. Viec di doi bai rac da duoc UBND quan Cai Rang phe duyet thiet ke va du toan voi dien tich bai rac can duoc di doi la 1,95ha; kinh phi la 13,08 ti dong; thoi gian thuc hien trong 45 ngay, bat dau tu ngay 15.11.
Landfill No. 8 covers an area of ​​4.3 hectares with a total waste volume of over 162,000 tons. The design and estimate for the relocation of the landfill have been approved by the People's Committee of Cai Rang District with an area of ​​1.95 hectares; the cost is 13.08 billion VND; the implementation time is 45 days, starting from November 15.

Yến Phương - Tạ Quang
TIN LIÊN QUAN

Prime Minister requests to completely handle the garbage dump blocking the highway

|

Hau Giang - On the afternoon of December 15, Prime Minister Pham Minh Chinh and his delegation inspected the Can Tho - Ca Mau expressway.

Site of relocation of landfill blocking Can Tho - Ca Mau highway

|

Can Tho - The relocation of the landfill blocking the highway is being urgently carried out by units to complete it soon and hand over the site before December 31.

Busy moving garbage dump blocking Can Tho - Ca Mau highway

|

Can Tho - Currently, workers are busy removing the amount of garbage overlapping with the highway at landfill No. 8, Ba Lang ward, Cai Rang district.

Health of 4 victims in coffee shop fire in Hanoi

|

Currently, the four patients in the fire at the coffee shop in Hanoi are being treated at Bach Mai Hospital and are doing quite well, but it is too early to say for sure.

Fines for buses honking loudly and overtaking recklessly on the road in Hanoi

|

Hanoi - A bus continuously overtakes and honks loudly on the road, posing a potential traffic safety risk.

Putin rejects comments that Russia is weakening

|

President Vladimir Putin said that arguments about a weakening Russia were exaggerated.

Singapore team wins ticket to ASEAN Cup 2024 semi-finals

|

On the evening of December 20, the Singapore team won a ticket to the semi-finals of the ASEAN Cup 2024 with second place in Group A after a 0-0 draw with Malaysia.

Update on the closing price of gold on December 20: Prolonged decline

|

Updated gold price at the end of the session on December 20: SJC gold bar price decreased by about 300,000 VND/tael. World gold price is under pressure from FED's interest rate policy.

Prime Minister requests to completely handle the garbage dump blocking the highway

Tạ Quang |

Hau Giang - On the afternoon of December 15, Prime Minister Pham Minh Chinh and his delegation inspected the Can Tho - Ca Mau expressway.

Site of relocation of landfill blocking Can Tho - Ca Mau highway

TẠ QUANG - YẾN PHƯƠNG |

Can Tho - The relocation of the landfill blocking the highway is being urgently carried out by units to complete it soon and hand over the site before December 31.

Busy moving garbage dump blocking Can Tho - Ca Mau highway

TẠ QUANG - YẾN PHƯƠNG |

Can Tho - Currently, workers are busy removing the amount of garbage overlapping with the highway at landfill No. 8, Ba Lang ward, Cai Rang district.